9c. CIP Report

Item Number:  9c_Report
Meeting Date: May 22, 2018



Capital Improvement Projects
First Quarter Report 2018

ii  Port of Seattle 1Q 2018 Report

Port of Seattle
Capital Improvement Project Report
First Quarter 2018
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic 
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the 
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high 
level information on the status of the Port's capital projects.
Background
During 2018, the Port plans to invest $895,100,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 2 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means 
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business 
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule, 
budget, change orders, risks, budget transfers, and cost growth of construction if it exceeds 10% of contract. The
report may include graphics that report project costs compared to authorization, construction costs (including change
orders (CO)) compared to the construction contract, location maps, and photographs. The Port implements a number
of different types of projects and not all information may be relevant to a specific project; as such, the reports may vary
in detail and content. Project types may range from construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase, 
and estimated completion date (substantial completion). This section also includes "Project Status" illustrating at a 
glance if the project is on schedule, and within budget, and the date Construction authorization received.
Significant Developments covers items such as accomplishments, significant events or milestones, contract 
advertisements and awards, upcoming activities, and environmental issues.
Schedule includes information on the project schedule, the total schedule variance and variance since the last 
report, contract extensions, and information on critical dates.
Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
Change Orders provides information on current quarter's COs and total project Cos, including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
Budget Transfers reports any transfers between authorized projects during the reporting period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These 
reports intend to meet the reporting requirements of Port of Seattle General Delegation of Authority and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.


Port of Seattle 1Q 2018 Report  1

Charts from PowerPoint
Project Title                        Page
Q4 CDD Projects by Status Chart................................................................6
Q4 CDD Projects by Dollar Value Chart......................................................7
Aviation
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C101107 ................160th GT Lot ..........................................................8 ..........................
C102112 ................Hennelly Service Tunnel Renewal Rep .................9 ...........
C102162 ................Air Cargo Road Safety Improvements..................10 ..........
C800061 ...............Main Terminal South Low Voltage ........................11 ......................... ..................
C800251 ...............Vertical Conveyance Modernization .....................12 ......................... 
C800335 ...............EGSE Electrical Charging Stations ......................13 .........................
C800483 ...............Aireld Pavement Program ..................................14 ..........
C800538 ...............Utility ER Backup Standby ....................................15 ..........
C800549 ...............SSAT Interior Renovations ...................................16 .........................
C800556 ...............NorthSTAR North Satellite Lobbies ......................17 ..........
C800583 ...............International Arrivals Facility ................................18 ......................... .................... 
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal ........19 ......................... 
C800605 ...............Security Exit Lane Breach Control Phase II .........20 .........................
C800612 ...............Checked Baggage Recap/Optimzation ............. 21-22 .......................
C800638 ...............Dining and Retail Infrastructure Modernization ....23 .........................
C800642 ...............CCTV Camera Data Improvements ....................24 ..........
C800655 ...............IWS Segregation Improvements ..........................25 ......................... .................... 
C800658 ...............Mechanical Energy Conservation ........................26 ..........
C800688 ...............Construction Logistics Expansion ........................27 .........................
C800695 ...............C3 Holdroom Expansion ......................................28 .........................
C800697 ...............Concourse B, C and D Restroom Upgrades ........29 ..........
C800699 ...............Electric Utility SCADA Utility .................................30 ......................... ..................
C800702 ...............2015-2016 C Concourse Roof Repl .....................31 .........................
C800717................N. Terminal Utilities Upgrade................................32 .........................
C800722 ...............CTE HVAC ............................................................33 ..........
C800724 ...............Concourse C New Power Center .........................34 .........................
C800743 ...............South Sattelite Terminal Renovation. ...................35 .........................
C800760 ...............Auburn Mitigation Rd Removal .............................36 .........................
C800761 ...............Concourse B Ramp Level Holdroom ....................37 ..........
C800762 ...............Telecommunications Meet Me Room ...................38 ..........
C800769 ...............Concourse D Hardstand Terminal ........................39 ......................... 
C800779 ...............Safedock Upgrade and Expansion .......................40 ..........

2  Port of Seattle 1Q 2018 Report

Aviation, cont.
Overall Project Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800781 ...............SSAT Narrow Body Conguration ........................41 ......................... 
C800784 ...............Emergency Generator ..........................................42 ........................ ..................
C800793 ...............PLB Renew and Replace Phase 2 .......................43 ..........
C800798 ...............SSAT HVAC Infrastructure Upgrade ....................44 ......................... 
C800801 ...............Variable Frequency Drive .....................................45 ..........
C800811 ...............Chiller Panel Upgrade ..........................................46 ..........
C800818 ...............SSAT Structural Improvements ............................47 .........................
C800825 ...............Interim Baggage System Program .......................48 .........................
C800826 ...............ARC Flash Hazard Mitigation ...............................49 ..........
C800833 ...............Holdroom Seating For Concourses B and C ........50 .........................
C800834 ...............Ground Based Augmentation System Upgrade ...51 .........................
C800841 ...............Tenant Telecommunications DEMARC Upgrade .52 ..........
C800842 ...............AOA Perimeter Fence Line Standards Comp    53 ......................... ..................
C800846 ...............ADR Kiosk Program Expansion 1 ........................54 ..........
C800858 ...............Checkpoint 5 Wall Replacement ..........................55 .........................
C800862 ...............Terminal Security Enhancements ........................56 ..........
C800873 ...............Concourse B Gate Reconguration .....................57 ..........
C800876 ...............Fire Station Westside............................................58 ..........
C800880 ...............Employee Security Screening ..............................59 .........................
C800883.................Delta Inflight Services Tenant Reimb Agmt .........60.......................... 
C800886 ...............Central Terminal Enhancements ..........................61 .........................
C800898 ...............Airport Signage Phase 1 ......................................62 ..........
C800914 ...............Taxiways ABLQ Improvements ............................63 ..........
C800920 ...............ASL Converstion at Checkpoints..........................64 ......................... 
C800925 ...............Zone 3 Common Use Counters ............................65 ..........
C800982 ...............CDD and CPO Oce Relocations .......................66 ......................... 
E104395-6 ............Lora Lake ..............................................................67 ..........
U00225 .................Flight Corridor Safety Prog Ph 1 ..........................68 .........................
U00239 .................NERA Program .....................................................69 ..........
U00356 .................Flight Corridor Safety Program Phase 2 and 3 ....70 ......................... 
U00370 .................Automated Passport Control Kiosk - Ph 3............71 .........................
Other Aviation
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C200007................. Highline School Noise Insulation.......................... 72.......................... 
C800154 ...............Tenant Reimbursement ........................................73 ..........


Port of Seattle 1Q 2018 Report  3

Maritime
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800355 ...............Shilshole Bay Marina Paving ................................74 ......................... 
C800356 ...............Shilshole Tenant Service Buildings .....................75 .........................
C800445 ...............SBM Site Pad Redevelopment .............................76 ..........
C800525 ...............FT Redevelopment Phase I ..................................77 ......................... 
C800526 ...............FT Net Sheds 3, 4, 5 & 6 Roof Replacement .......78 .........................
C800531 ...............FT Docks 3, 4, 5 & 6 Fixed Pier Impr ...................79 ..........
C800675 ...............P91 South End Fender .........................................80 ..........
C800829 ...............T-91 C173 Building Roof Overlay .........................81 ..........
C800895 ...............T-18 Stormwater Outall Renewal & Repl ..............82 ..........
C800910 ...............T-91 StandoBarges ............................................83 ..........
C800993-U00471 .Salmon Bay Marina Uplands Improvements........84 ..........
E104324 ................Viaduct Construction Coordination ......................85 .........................
U00218 .................P66 Alaskan Way Street Improvements ...............86 ..........
Economic Development
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800813-105257 ..P66 Elevator 3 & 4 Control ...................................87 ..........
C800813-105261 ..P66 Elevator 2 Control System ............................88 ..........
C800888 ...............P69 Solar Panel System .......................................89 ..........
C800889 ...............BHICC Interior Modernization ..............................90 ..........
Joint Venture
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C102858 et al ....... Street Vacations T-5/18/105 .................................91 .........................
C800546 ...............Argo Yard Truck Roadway ....................................92 ......................... 
C800620-U00064 T-46 Permit Mitigation ..........................................93 .........................
E102007 ............... East Marginal Way Grade Separation..................94 .........................
U00289 .................T-5 Pile Removal ..................................................95 ..........




4  Port of Seattle 1Q 2018 Report

Corporate
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800728 ...............Parking System Replacement ..............................96 .........................
C800729 ...............Vessel Moorage System .......................................97 .........................
C800747................Project Delivery System .......................................98 ..........
C800748 ...............Remote Data Ctr Business Continuity ..................99 .........................
C800776 ...............POS Website Redevelopment .............................100 ........................
C800782 ...............Airport Subway Info Displays ..............................101 .........
C800788 ...............Airport Data Network Switch Upgrade ................102 ........................
C800790 ...............Checkpoint Wait Time..........................................103 ........................
C800800 ...............SEA Smartphone App .........................................104 ........................
C800835 ...............South Loop Train Displays ...................................105 ........................
C800907 ...............Supplier Outreach and Procurement System .....106 .........
C800908 ...............Enterprise Network Firewal Upgrade .................107 .........
C800909 ...............PeopleSoft Financials Upgrade ..........................108 .........
C800929 ...............Rental Car Facility Fleet Tracking System ..........109 .........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are o
Both target schedule & budget are o
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date







Port of Seattle 1Q 2018 Report  5

6  Port of Seattle 1Q 2018 Report

Port of Seattle 1Q 2018 Report  7

FIRST QUARTER REPORT, 2018
So. 160th GT Lot Expansion
Project: C101107                     Improve lot drainage and complete      Project Status:
Budget: $4,326,533                   site fencing and landscaping,            Schedule:           Delayed 
Phase: Design                        rehabilitate the Ground Transportation    Budget: On or Under
Start: 2/1/2013                        (GT) Lot building, underground          Status Reset: 9/26/2017
Schedule Completion: 11/16/2018     existing overhead utility lines           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Lot improvements and utility undergrounding is complete. Bids were opened
5      4.3
for the GT Lot building rehabilitation work in March and the low bid was                           3.9
$795,000 (4.9% below engineer's estimate). PCS installed temporary restroom      4
facilities.                                                                                            3
1.6
2
Schedule                                                         Dollars in Millions  1
GT Lot building rehabilitation was removed from the project scope in 2015 and      0
restored by the Commission on September 26, 2017. Contract execution is             Authorized Forecasted   Costs
Incurred
anticipated in Q2 and work completed by Q3 2018. 
Budget                                                      Construction Contract Costs
Project is under budget with a total forecast at completion of $3,934,300.             $1.00
0.8
$0.80
Change Order
Current Quarter       Project Total            Dollars in Millions $0.60
$0.40
Number of COs               N/A                 N/A
$0.20
Amount of COs               N/A                 N/A                              0.0     0.0
$0.00
Justification for COs: N/A for this quarter
Initial    Change    Spent
Orders
Risks
Managing ground transportation operations around an active construction site.    Photo
Long lead times during construction may further delay the schedule.
Budget Transfers
Amount           From             To
$0

Temporary Restrooms

AIRPORT
8  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Service Tunnel Renewal/Replace
Project: C102112                     Project will seismically retrofit and      Project Status:
Budget: $39,505,000                 structurally strengthen the airport        Schedule:           Within or Ahead 
Phase: Construction                 Service Tunnel located between the      Budget: On or Under
Start: 11/4/2012                       Main Terminal and Airport Garage.       Status Reset: 7/25/2017
Schedule Completion: 12/31/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction work continues within the southern portion of the Service Tunnel
$50
and along the south portion of the Courtesy Van Plaza located in the Main                 39.5      39.5
Garage. At the end of Q1 construction was 12% complete with 8% of the work     $40
accomplished in the quarter.                                                       Dollars in Millions $30
$20
10.6
Schedule
$10
The project is on schedule with construction completion anticipated in Q2            $0
2020.                                                                          Authorized Forecasted   Costs
Incurred
Budget
Costs                                                                     Construction Costs
Budget was increased to add the seismic improvements for the load dock, and
for an irregular bid (high bid). Project is forecast to be completed within
$30
budget.                                                                                24.0
$25
$20
Quarter                                                                   Change Order                                                      Dollars in Millions $15
Current Quarter       Project Total             $10
4.7
Number of COs                8                   9                   $5           0.1
Amount of COs            $72,906.00           $72,906.00               $0
Initial    Change     Spent
Justification for COs: varying site conditions, scope change (addition of
Orders
concrete reveal strips), and designer errors and omissions.
Risks                                                            Photo
Other projects (International Arrivals Facility, Supervisory Control and Data
Acquisition Systems, and North Terminal Utilities Upgrade) are working within
and adjacent to the Service Tunnel and may impact this project.
Budget Transfers
Amount           From             To
$0

AIRPORT
Port of Seattle 1Q 2018 Report  9

FIRST QUARTER REPORT, 2018
Air Cargo Rd Safety Improvements
Project: C102162                     Improvements along Air Cargo Rd   Project Status:
Budget: $8,819,590                   and S 170th St to support Cell         Schedule:           Within or Ahead 
Phase:  Design                      Phone L and roadway operations,    Budget: On or Under
Start:  10/2/2013                       and meet current safety standards.     Status Reset: 7/11/2017
Schedule Completion: 9/11/2020                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Completed contract negotiations and executed Service Agreement with the
10                 8.8
H Corporation in March. Planned stakeholder engagement including City
of SeaTac, FAA, employee parking and rental car busing, ground transportation      8
operators, public transit, and adjacent tenants.                                        Dollars in Millions  6
3.6
4
Schedule
2
0.3
Project restarted Q2 2017 and is currently on schedule.                               0
Authorized Forecasted    Costs
Budget                                                                        Incurred
Project is currently within budget. Overall project budget includes $ of
Construction Contract Costs
additional project contingency to address risks.
$2
Change Order
Current Quarter       Project Total
Number of COs                 0                   0                   $1
Amount of COs                $0                  $0                Dollars in Millions       0.0     0.0     0.0
Risks                                                                $0
Initial    Change     Spent
Storm Drainage System  portions of the storm drainage system may have                   Orders
failed and needs to be replaced.
Unknown Utilities  widening and sidewalk construction require the         Photo
relocation of a number of unknown utilities.
Traffic Growth  completion of the traffic analysis identifies the need for
additional intersection improvements to accommodate growth.
Budget Transfers
Amount           From             To
$0
Air Cargo Rd Pavement Repair

AIRPORT

10  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Main Terminal Low Voltage
Project: C800061                  Renewal and replacement of low          Project Status:
Budget: 100,300,000               voltage (600 volts and below) electrical    Schedule:           Delayed 
Phase: Design                     distribution equipment in the Main         Budget: Forecast Overrun
Start: 6/28/2007                    Terminal.                                 Status Reset: N/A
Schedule Completion: 2/26/2025                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Project is at 30% design. Team evaluating measures to reduce project cost.
120                100.3
100
Schedule
80
Project is behind schedule due to substantial scope growth that resulted from
60
poor master record drawings. The scope of work, schedule and design budget
authorization will be presented to Commission for approval in QQ 2018.         Dollars in Millions 40
20      8.1                   2.6
0
Budget                                                          Authorized Forecasted  Costs
Incurred
The forecast has been revised at the conclusion of the Q3 design. An increase
in budget is ee to be required and will likely ee the $20.7M budget.
Authorization action is ee in QQ 2018.              Construction Costs
Not Applicable
Change Order
Photo
Current Quarter       Project Total
Number of COs                0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
This area is a 2 7/Q7 operation. Sequencing of this work is critical and
electrical power has to be maintained without interruptions. Significant work
growth is possible due to lack of project definition.
Budget Transfers
Amount           From             To
$0


AIRPORT
Port of Seattle 1Q 2018 Report  11

FIRST QUARTER REPORT, 2018
Vertical Conveyance Modernization Program - Aeronautical
Project: C800251                  Perform modernization on 9 e %& %'(      Project Status:
Budget: $12,306,408               elevators and escalators: SSAF, MT-!    Schedule:           Delayed 
Phase: Construction               MT-M MT- MT-" MT- MT-) SSB,   Budget: On or Under
Start: 10/25/2011                   SSC. Install new elevators SSM and        Status Reset: 11/11/!# M
Schedule Completion: 6/30/2017   SSN. Install cooling packages on 12       (Commission Construction Auth.)
e %& %'( hydraulic elevators throughout
Main Terminal. 
Significant Developments                                           Budget/Costs Incurred
Substantial completion was achieved in Q2 2017. Started final negotiations and
20
closeout with expected completion in Q2 2018.                                          16.4
15
Schedule                                                                     10.1     10.0
10
Construction is complete as of Q2 2017                                          Dollars in Millions  5
Budget                                                        0
Authorized Forecasted    Costs
The project forecast is within the approved budgett savings is e 
Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total
4.6                  4.8
Number of COs                1                  109                   5
Amount of Cos              -               ! "#"                 4
Justification for COs: differing site conditions, sequencing of work, and            Dollars in Millions   3
administrative changes.
2
1                0.5
Risks
0
Contractor has e contract time and has failed to complete work on time
Initial    Change     Spent
in 2016.                                                                                          Orders
Budget Transfers
Amount           From             To
$0


AIRPORT

12  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Electrical G*+,/0 Support EE,1456/8 (EGSE) Electrical Charge Stations
Project: C800335                      AirportA9:;< electrical charging      Project Status:
Budget: $30,700,000                 system for electrical ground support    Schedule:           Delayed 
Phase:  Construction                equipment at the Concourses and the   Budget: On or Under
Start:  10/26/2010                     North and South Satellites=              Status Reset: N/A
Schedule Completion: 3/1/2021                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
One hundred percent design review for Concourse A work is underway.
35                30.7
Schedule                                                          30   25.6
Schedule was delayed to allow for improved design development and better        Dollars in Millions 25
18.4
20
coordination with the IAF project.                                                   15
10
Budget                                                        5
0
Project is on budget                                                                     Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
Justification for COs: None
Risks
None
Budget Transfers
Amount           From             To
$0



AIRPORT

Port of Seattle 1Q 2018 Report  13

FIRST QUARTER REPORT, 2018
Airfield Pavement Program
Project: C800483                     This is a multi-year program to       Project Status:
Budget: $10,300,000                  replace distressed pavement and       Schedule:           Within or Ahead 
Phase:  Construction                 joint seal on the airfield starting in    Budget: On or Under
Start:  5/5/2011                        2016 through 2020.                   Status Reset: 10/25/2016
Schedule Completion: 6/30/2021                                          (Commission Const Auth.)
Significant Developments                                           Budget/Costs Incurred
The 2018 Airfield Pavement Project will replace sections of asphalt pavement
12                10.3
located north and west of the South Satellite with concrete pavement to provide
10
sufficient support to aircraftsa replace distressed concrete panelsa and replace
8
the damaged joint seal at the touch down zones of RW16L/34R.
6
The project was combined with the 2018 Taxiway Improvements project as a
4
single construction contract to minimize impacts to airport operations. The         Dollars in Millions        1.5
2                            0.8
contract was awarded in Q1 and the onsite construction started.
0
Authorized Forecasted    Costs
Schedule                                                                           Incurred
The onsite construction started for Phase 1 with the completion of the combined
contract estimated for Q4 2018.                                                  2017 Construction Costs
0.5    0.4
Budget
0.4
0.4
The project is currently within budget.
0.3
Change Order                                                  0.2
Current Quarter       Project Total            Dollars in Millions  0.1
0.0
Number of COs                 0                   0
0
Amount of Cos                 $0                   $0                       Initial Change  Spent
Orders
Justification for COs: None at this time
Risks                                                            2018 Photo
Poor weather conditions will impact both the schedule and budget for the
project delivery.
Close coordination with CM team to monitor weather and develop mitigation
plans if poor weather conditions last during construction.
Budget Transfers
Amount           From             To
$None

AIRPORT
14  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Alternate Utility Facility 
Project: C800538                     Build and house a new 30MW       Project Status:
Budget: $37,200,000                  electrical bacb>? power generation    Schedule:           Within or Ahead 
Phase:  Construction                 facility for the Airport.              Budget: On or Under
Start:  8/4/2015                                                               Status Reset: 8/4/2015
Schedule Completion: 3/31/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Major construction completed. All equipment is emplaced and site is surfaced             37.2
40                34.2
in.                                                                                                   35                           30.9
30
Schedule                                                         Dollars in Millions 25
20
Project is expected to complete on schedule.                                        15
10
5
Budget
0
No changes to project budget.                                                         Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                 9                   10                       27.9
$30                         27.0
Amount of Cos              $128,480             $128,480                $25
Justification for COs: N/A                                                          Dollars in Millions  $20
$15
Risks                                                               $10
No current project risks.                                                                $5              0.1
$-
Budget Transfers                                                         Initial   Change   Spent
Orders
Amount           From             To
$0




AIRPORT
Port of Seattle 1Q 2018 Report  15

FIRST QUARTER REPORT, 2018
South Satellite Interior Renovations
Project: C80054F                  Modify the mezzanine and concourse    Project Status:
Budget: $6,256,000               levels of the South Satellite to improve    Schedule:          IJKNOJP 
Phase: Construction              the passenger experience.               Budget: On or Under
Start: 11/4/2012                                                              Status Reset: 3/22/2016
Schedule Completion: 6/30/2017                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Project is complete with the exception of one punchlist item. This is the final
6.26
report.                                                                                   6.3
6.2
Schedule                                                         6.1
Project was delayed due to phasing complications and slow production of
6
@BD                5.81
materials                                                                          Dollars in Millions                         @BCD
5.8
5.7
Budget                                                       5.6
Authorized Forecasted    Costs
Project is under budget                                                                                    Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total
4                          3.4
Number of COs                2                   50                  3.5    3.1
Amount of COs             ($2,185)             $295,294                3
Justification for COs: Not to exceed change orders resulted in a credit.
2.5
2
1.5
Risks                                                              Dollars in Millions   1
0.5                0.3
No further risks                                                                         0
Initial    Change     Spent
Orders
Budget Transfers
Amount           From             To            Photo
$0




AIRPORT
16  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
RSTUVWXYZ RSTUV Satellite Renovation and RWXW Lobbies
Project: C800556                  Renovation and expansion of the North   Project Status:
Budget: $670,671,192              Satellite ~q including NSAT         Schedule:          Within or Ahead 
Phase: Construction               Satellite Transit System ~ stations     Budget: On or Under
Start: 7/24/2012                    ]]_q ramp levelq Concourse levelq      Status Reset: 8/15/201s
Schedule Completion: Q3 2021    and new rooftop airline lounge.           (Commission Construction Auth.) 
Significant Developments                                           Budget/Costs Incurred
Met Q1 Project goal of primary structural steel installation. Completed Alaska                TOTAL
670.6      670.6
Level of Service (LOS), passenger flow analysis and reached decision to Cobus      700.0
via [\]^_`\c^ d to NSAT ground board gates. Alasf\ ghi Lounge design and  600.0
j]klc^ Board is at mhi design review. Received final building permit for the       Dollars in Millions  500.0
400.0
project on January 16th. Received passenger loading bridge installation and          300.0
133.7
caseworf bidsn Completed Puget Sound Energy gas pipe worf under east         200.0
taxiway and opened escalator NS4 in NSAT central coreo                         100.0
0.0
Schedule                                                              Authorized Forecasted  Costs
Incurred
Continuing coordination with 2018 Taxiway project and NSAT Phase 1
opening. Phase 1 expansion floor slabs nearly complete with rooficpq interior    Construction Costs
concrete walls and site utilities ongoing. Critical path Central core escalator
453.6
NS4 completed and NS3 replacement beginning on schedule. Concourse C          500
vertical transportation constructability review and redesign nearly complete.          400
Expediting design of Phase 1 dining and retail projects and finalizing Cobus          300
ground board design.
200
Budget                                                       Dollars in Millions                   65.5
100
10.1
Overall budget remains at rgshqgsuquvwx            0
MACC   Change   Spent
Change Order                                                            Orders
Current Quarter       Project Total           Photo
Number of Cos                32                   214
Amount of Cos             ruqhmyqzhw           ruhquhsqgh{
Justification for COs: Central Core Structural framing| Steel connection
clarifications| EC/CM site investigation reconciliation| 
Risks
Maintaining budget and schedule| complex central core phasing| exceeding
contractor design development allowance| completion of dining and retail
projects on time to maintain Phase 1A } 1B openings
Budget Transfers
Amount           From             To
$0

AIRPORT
Port of Seattle 1Q 2018 Report  17

FIRST QUARTER REPORT, 2018
International Arrivals Facilit (IAF)
Project: C800583                  Planning design and construction of a     Project Status:
Budget: "   new Federal Inspection Services (FIS) Schedule:   Delayed 
Phase: Construction               facility including a pedestrian walkway     Budget: Forecast Overrun
Start: 6/25/2013                    connecting the South Satellite and seven     Status Reset: 8/15/2017
Schedule Completion: 6/30/2020   Concourse A gates to the new IAF.        (Commission Authorization to start
Design & Construction)
Significant Developments                                           Budget/Costs Incurred
Ninety percent design review is completed. Finalizing the  design
766.0      766.0
documents. Civil wor continues on the Landside. On the Airside Turnover of      800
A6 and A is completed and commences construction on PO B.                 700
600
500
Schedule                                                         Dollars in Millions 400
Currently projecting delayed completion for the operational opening of the IAF      300                     
200
building. The  team (DB) is working on acceleration options in
100
order to mitigate the delays. The Pedestrian Wal (Bridge) and Sterile             0
Corridor remain on schedule.                                                          Authorized Forecasted   Costs
Incurred
Budget
Construction Costs
The DB is over the Target Budget. The Project team is currently working
through final estimates in order to complete negotiations of the final GMP                  562.6
600
Contract.                                                                           500
400
Change Orders
300
Current Quarter       Project Total             200                 148.5
Number of COs                3                   16                Dollars in Millions 100          16.4
Amount of COs            $3,400,000           $ 16,400,00               0
Initial    Change     Spent
Justification for COs: Revisions to Baggage  Scope Added PCB
Orders
Environmental costs and Increased  Services
Risks
Potential cost and schedule impacts from forecasted shortages of materials and
s labor in the current robust Seattle construction mar remains a ris 
Budget Transfers
Amount              From                To
$0


AIRPORT
18  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Enhancement
Project: C800585                     Upgrade Wi-Fi system in the public     Project Status:
Budget: $10,676,000                 and ramp operational areas of the        Schedule:           "" 
Phase: Construction                 Airport. Provide micro-distribution      Budget: On or Under
Start: 11/4/2012                       cabinets on the ramp of each             Status Reset: 8/8/201
Schedule Completion: 12/21/2018     concourse to extend communications     (Commission Construction Auth.)
infrastructure.
Significant Developments                                           Budget/Costs Incurred
Substantial completion reached for Ramp Wi-Fi on Concourses A B C  and
12     10.68      10.68
the South Satellite. Favorable bids received for Baggage Claim Bagwell  
10
Marie Lindsey  and Satellite Transit System Stations. Construction contract
for this phase now executed. " for passenger loading bridges and South    Dollars in Millions 8             6.18
6
Satellite interior progressing.
4
2
Schedule
0
The start of design for the final phase for passenger loading bridges was                 Authorized Forecasted   Costs
Incurred
delayed in order to evaluate delivery method. This has pushed out the final
completion date of the overall project.
Construction Costs
Budget                                                            2.75
3.00
On or under budget.
2.50
2.00
Change Order                                                1.50
1.37
Current Quarter       Project Total            1.00
Number of COs                11                  24                0.50  Dollars in Millions             0.03
Amount of COs                                         0.00
Initial     Change     Spent
Justification for COs: Changed conditions.                                                         Orders
Risks
Passenger loading bridge Wi-Fi wor appearing more challenging than first
anticipated due to the diversity of site conditions.
Budget Transfers
Amount           From             To
$0


AIRPORT
Port of Seattle 1Q 2018 Report  19

FIRST QUARTER REPORT, 2018
Securit E  Breach Control  Phase 2
Project: C800605                     Installation of automated security     Project Status:
Budget: $11,100,000                  breach control e at exits to   Schedule:           
Phase:  Design                      Concourse A C and North and      Budget: On or Under
Start:  10/15/2015                      South Satellite Transit System         Status Reset: 8/8/201
Schedule Completion: 2/3/2020       exits.                               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Development of Building Engineering Systems Request for Proposal                     11.1      11.1
12.000
documents continues.
10.000
8.000
Schedule
6.000
Anticipate RFQ advertisement now mid-Q2.                                                           3.1
4.000
2.000    Dollars in Millions
Budget
0.000
No change.                                                                    Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                 0                   0               None at this time
Amount of Cos                 $0                   $0
Photo
Justification for COs:
Risks
RFP responses pose the most li ris including: the number and lity of
responses and proposed cost. These ris will be evaluated and adjusted
following completion of RFP advertisement and selection of a design/build
team.
Budget Transfers
Amount           From             To
$0



AIRPORT
20  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Checked Baggage Recapitalization/Optimization
Project: C800612                  TSA approached the Airport in 2012      Project Status:
Budget: $445,050,000              with plan to replace all federally owned    Schedule:          Dp  p 
Phase: Construction               and operated baggage scanning            Budget: On or Under
Start: 2/26/2013                    er e p In addition the project         Status Reset: N/A
Schedule Completion: 2/28/2025   replaces the remainder of the outbound     (Commission Construction Auth.)
baggage system.
Significant Developments                                           Budget/Costs Incurred
Phase 1 Major Construction
The following activities currently underway:                                        500            445.1
Demolition of Central Terminal (CT) ramp has been completed.                      400
New CT ramp construction is approximately 80% complete.                        Dollars in Millions 300
Conveyor installation began in March.
200     136.3
Maintenance breakroom in Concourse B is 80% complete.
Installation of  chilled water piping has been completed.                         100
41.0
of  steam piping has begun.                                         0
E hatch removal has been completed.                                              Authorized Forecasted   Costs
Incurred
Baggage screening machine installation at North Oversize completed and is in use.
Project coordination with other Port and Tenant projects is ongoing.                      Construction Costs
Phase 2 
Maintaining operations through Phase 2 construction will re a detailed se    60  52.0
plan. Team has conducted the first construction se progress meeting to        50
develop this plan. Submitted the updated Basis of  report to TSA for final              40
determination of 4 baggage screening machines that will be installed during Phase 2.       Dollars in Millions   30
15.1
20
Schedule
10            0.9
Phase 1 contractor schedule shows Substantial Completion in Q3           0
approximately 1 month behind schedule.                                               Initial Change  Spent
Orders
Phase 2  started design pacp development. It is scheduled to allow Phase 2
construction to begin at the completion of Phase 1.
Budget
The project forecast is currently within budget. Phase 1 Dp  
and Phase 2 Dp  have been authorized.
Change Order
Current Quarter       Project Total
Number of COs                6                   16
Amount of COs             $               $   
Justification for COs: Scope change error/omissions varying site conditions 
and tenant rer p p 

Port of Seattle 1Q 2018 Report  21

Risks
Equipment manufacturers may differ between phases, requiring Port
Maintenance crews to maintain and replace many models of equipment.
Shutdowns may impact airline operations if they last longer than
anticipated.
Contractor is behind on conveyor submittals and installation. Contractor
submitted a mitigated schedule that indicates the project will be completed
on-time. The Contractor continues to miss key start dates and mitigates by
shortening schedule durations to show on-time completion. Various
meetings have been conducted with the contractor representatives and
executives to help the Contractor mitigate schedule delays.
Budget Transfers
Amount            From              To
None









AIRPORT
22  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
SecuritS EE L Breach Control  Phase 2
Project: C800605                     Installation of automated security     Project Status:
Budget: $11,100,000                  breach control eq !" #% at exits to   Schedule: & ' 
Phase:  Design                      ConcourseC A C and North and      Budget: On or Under
Start:  10/15/2015                      South Satellite Transit System         Status Reset: 8/8/2018
Schedule Completion: 2/3/2020       exits.                               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Development of Building Engineering Systems Request for Proposal                     11.1      11.1
12.000
documents continues.
10.000
8.000
Schedule
6.000
Anticipate RFQ advertisement now mid-Q2.                                                           3.1
4.000
2.000    Dollars in Millions
Budget
0.000
No change.                                                                    Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                 0                   0               None at this time
Amount of Cos                 $0                   $0
Photo
Justification for COs:
Risks
RFP responses pose the most lil risl including: the number and q lity of
responses and proposed cost. These risl will be evaluated and adjusted
following completion of RFP advertisement and selection of a design/build
team.
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 1Q 2018 Report  23

FIRST QUARTER REPORT, 2018
V()*+ S,-.*/ Improvements
Project: C800642                  Add cameras and improve the video      Project Status:
Budget: $13,000,000              management system at the Airport.       Schedule:          Within or Ahead 
Phase: Construction              Project funded by a TSA Other          Budget: On or Under
Start: 11/4/2012                    Transaction Agreement (OTA)            Status Reset: 5/23/201F
Schedule Completion: 7/1/201B                                  (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Started construction of Terminal Cameras including infrastructure in Concourse
13.00      13.00
A, B, C, D and S. Satellite. Completed 01234 Management System (0567     14
configuration and testing. Plan to switch over to new 056 in May.          12
Dollars in Millions 10
8                           ?@AA
Schedule
6
Project remains on schedule. Due to previous favorable bids and other cost           4
saving, a further project phase is being prepared in order to fully expend the          2
OTA grant funding. This further phase will be completed in Q3.                     0
Authorized Forecasted    Costs
Incurred
Budget
No Changes                                                         Construction Costs
Change Order                                                   6
4.88
5
Current Quarter       Project Total
4
Number of COs                0                   9
3
Amount of COs                $0                $81,496
2                         1.20
Justification for COs: None this quarter                                             Dollars in Millions   1
0.08
0
Risks                                                                    Initial   Change   Spent
Orders
Schedule Risk 9 TSA OTA funding expires in July :;<=> Completion of all
worw and invoicing needs to occur prior to expiration.
Budget Transfers
Amount           From             To
$0



AIRPORT
24  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
IIG Segregation Improvements
Project: C800655                     Install  Total  Organic  Carbon  (TOC)  Project Status:
Budget: $1,142,000                   analyzers  into  the  exisiting  Industrial   Schedule:          [JK\MJR 
Phase:  Design                      Wastewaster conveyance system serving   Budget: Forecast Overrun
Start:  8/1/2016                        the Terminal Areas of the Airport.           Status Reset: 4/13/2018
Schedule Completion: UWXYWXZYU               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Given the complexity of the construction and stringent schedule requirements,             1.1       1.1
1.2
it is no longer feasible to use Port of Seattle crews and small works contracts to
1
complete the construction phase of this project. This is now a traditional design,
0.8
bid, build delivery project. The sponsor and key stake holders concur this is the
0.6
best delivery method. Additional authorization will liHJKM be reNOPQJR to update  Dollars in Millions 0.4            0.24
the design and complete the construction.
0.2
0
Schedule                                                            Authorized Forecasted   Costs
Incurred
Construction start is delayed due to the change in construction methodology.
The prior plan to use Port of Seattle crews and small worHT contracts is not      Construction Costs
feasible given the projects construction complexity and stringent schedule.        Not Applicable at this time
Budget
Additional authorization will liHJKM be reNOPQJR to update the design and
complete the construction
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: None at this time
Risks
None
Budget Transfers
Amount           From             To
$0

AIRPORT
Port of Seattle 1Q 2018 Report  25

FIRST QUARTER REPORT, 2018
Mechanical Energ] Conservation
Project: C800658                     Perform ESCO audit identify and    Project Status:
Budget: $6,800,000                   prove savings design and construct    Schedule:           Within or Ahead 
Phase:  Construction                 project.                           Budget: On or Under
Start:  6/24/2014                                                             Status Reset: 
Schedule Completion: 11/25/}~                    (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The ESCO performance contract with the Washington State ^_`abcd_fc of    o|  6.8   6.8
Enterprise Services has been executed. ^_ghif is progressing                       o{
oz
Schedule                                                         Dollars in Millions oy
ox
On schedule                                                                ov
ou
Budget                                                        ot                 0.3
os
On budget                                                                   Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Number of COs                 0                   0                   oy
3.8
Amount of COs                $0                  $0                   ox
Justification for COs:                                                                   ov
Risks                                                              Dollars in Millions  ou
ot
No risjg at this time.                                                0.0    0.0
os
Initial    Change     Spent
Budget Transfers
Orders
Amount           From             To
$0                                                       Photo
Cost of Construction Grokmn
No construction costs growth anticipated.


AIRPORT

26  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Construction  Expansion
Project: C800688                     The expansion and reconfiguration of     Project Status:
Budget:   "                the existing construction logistics         Schedule:          Delayed 
Phase:  Closeout                    facilities (including the contractor         Budget: On or Under
Start:  8/1/2014                        parking lot and associated bus stops),       Status Reset: 2/23/2016
Schedule Completion:   and the renovation of Port field offices. (Commission Construction Auth.) 
Significant Developments                                           Budget/Costs Incurred
Construction is complete and completion memos have been issued for the
12.0
Contractor Parking Lot (CPL), Logistics Lots, Field Office Renovation, and                10.0
10.0                8.6        8.2
CPL Bus Stops. CPL and Logistics Lots are closed out. Field Office             Dollars in Millions  8.0
Renovation and CPL Bus Stops are in closeout. Warranty items are being
6.0
addressed with the replacement field office  scope before final
4.0
payment is made.
2.0
0.0
Schedule
Authorized Forecasted   Costs
Incurred
The overall project schedule was delayed with completion dates of Q1  for
CPL Bus Stops lays due to weather and errors and omissions and Q4  
for the replacement field office lay due to scope change and procurement   Construction Costs
6
Budget                                                              
5                          4.4
Project forecast is within the revised budget. Anticipate additional final
4
closeout savings with CPL Bus Stops in Q2 2018 and Field Office Renovations
3
in Q4 2018.                                                                   Dollars in Millions   2
1
Change Order                                                             0.1
0
Current Quarter       Project Total                  Initial   Change   Spent
Number of COs                0                   6                             Orders
Amount of COs                $0                 
Justification for COs: None this rter.                                           Photo
Risks
None
Budget Transfers
Amount           From             To            Replacement Field Office
$0
Cost of Construction Gro
CPL Bus Stops: Additional project contingency was included within the
project budget for unknown substandard pavement risk. Two change orders
were issued representing 13.8% of the original contract value.
AIRPORT
Port of Seattle 1Q 2018 Report  27

FIRST QUARTER REPORT, 2018
C3 " E
Project: C8006                     Provide a 1,500 sf building addition  Project Status:
Budget: $6,300,000                   to increase the size of Gate C3        Schedule:           Delayed 
Phase:  Permitting                   passenger holdroom. Provide 1,130    Budget: On or Under
Start:  4/4/2016                        sf renovation of existing holdroom.    Status Reset: 7/11/2017
Schedule Completion: 7/30/201                                 (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Advertised construction bid.
7.000      6.30        6.30
6.000
Schedule
5.000
Construction bid advertisement occurred later than originally scheduled. Bid       4.000
opening scheduled for May and construction to start in July.                       3.000
2.000    Dollars in Millions                                 0.74
Budget                                                      1.000
0.000
On budget
Authorized  Forecasted     Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               None at this time
Amount of COs                $0                  $0
Risks
None at this time.
Budget Transfers
Amount           From             To
$0




AIRPORT
28  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Concourse B, C, and D Restroom Upgrades
addition                                                 Project: C                       Renovate eight sets of public         Project Status:
Budget: $33,047,000                  restrooms on Concourses B, C, and    Schedule:           Within or Ahead 
Phase:  Design                      D. Increase the size of a portion of    Budget: On or Under
Start:  7/12/2016                       the e restrooms build new      Status Reset: 9/12/2017
Schedule Completion: 1/19/2022      restrooms build space for displaced   (Commission Construction Auth.)
e tenant functions and
enlarge the building to add one
additional new set of restrooms.
Significant Developments                                           Budget/Costs Incurred
Phase 1 - Started construction on Phase 1 Enabling work on Concourse B.                         33.0
$35.0
Phase 2 - Completed 60% Design on Phase 2 Enabling.
$30.0
Phase 3  Completed 90% design on Prototype. This phase uses FAA funding.   $25.0
$20.0
Schedule                                                        $15.0  Dollars in Millions      7.6
The project is on schedule.                                                         $10.0
$5.0
$0.0                            1.7
Budget
Authorized Forecasted    Costs
Quarter                                                                  The project is within budget.                                                               Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total
2
Number of COs                0                  0                      1.5
Amount of COs              $7,620               $7,620               1.5
1
Risks
.08
Air handling capacity limits on Concourse C may require additional work to        Dollars in Millions 0.5
0.0
ensure that there is enough air for additional restrooms.
0
FAA Funding requirements will need to be incorporated into the scheduling of           Initial   Change    Spent
Phases  through 5.                                             Orders
Budget Transfers
Amount           From             To
$0

AIRPORT

Port of Seattle 1Q 2018 Report  29

FIRST QUARTER REPORT, 2018
Electric Utility SCADA
Project: C                     Install a Supervisory Control and     Project Status:
Budget: $9,600,000                   Data Acquisition (SCADA) system    Schedule:           Delayed 
Phase:  Design                      for the Airport's 12.47 kV Medium    Budget: Forecast Overrun
Start:                          Voltage (MV) power distribution      Status Reset: 8/
Schedule Completion: 10/2019   network.                 Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Started a third party review of the design package.                                                   9.6
10
Schedule                                                          8
The project is behind schedule due to turnovers in project management and the       6
project sponsor.                                                                    Dollars in Millions  4
1.6                   1.5
2
Budget
0
The project remains within the authorized budget but is projected to require an          Authorized Forecasted   Costs
Incurred
increased budget. Turnover in project management and project sponsors,
combined with rising construction costs, has contributed to this forecast
Construction Costs
overrun.
Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: None at this point. 
Risks
The project carries an inherent risk of power outages during construction. The
project team will coordinate with all involved to minimize any potential
impacts 
Budget Transfers
Amount           From             To
$0


AIRPORT
30  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Concourse B  C Roof Replacement
Project:  C800770 ,C800702        Overlay the existing roof system        Project Status:
Budget: $13,183,000                (approximately 86,500 SF of roofing     Schedule:           Delayed 
Phase:  Construction              system on Concourse B and 83,000 SF   Budget: On or Under
Start:  3/1/2010                      on Concourse C) install a new           Status Reset: 1/2
Schedule Completion: 6/25/2018    elastomeric roofing system ladders      (Commission Construction Auth.)
and fall protection and replace and
refurbish the e skylight
window/walls.
Significant Developments                                           Budget/Costs Incurred
Contract suspension lifted and work has re-started.                                        13.18     13.18
14
12
Schedule
10
Project is behind schedule. Roofing contract was suspended for the winter          Dollars in Millions  8                      6.22
months so that roofing would not be performed during wet weather. Anticipate       6
4
completing work in June.
2
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Project is within budget.
Change Order                                               Construction Costs
5.7
Current Quarter       Project Total             6
4.7
Number of COs                14                  26                  5
Amount of COs             $23,975             $122,720               4
Justification for COs:                                                                Dollars in Millions  3
2
Risks                                                               1           0.1
0
Extended wet weather conditions causing additional delays.
Initial     Change     Spent
Orders
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 1Q 2018 Report  31

FIRST QUARTER REPORT, 2018
Terminal   Project
Project: C800717                     Replace and extend the steam,        Project Status:
Budget: $21,335,000                  condensate and chilled water          Schedule:           Delayed 
Phase:  Construction                 supply and return piping from the     Budget: On or Under
Start:  9/21/2010                       Central Mechanical Plant to the end    Status Reset: N/A
Schedule Completion: 1/30/2021      of mechanical room four and to the    (Commission Construction Auth.)
ends of the South and West Loops. 
Significant Developments                                           Budget/Costs Incurred
The Early Work project construction contracts have been terminated. This
25                21.3
scope of work will now be included in the design of the main project.
20
Schedule                                                         Dollars in Millions 15
9 
The 90 percent main project design submittal schedule has been delayed in          10
order to include the Early Work project scope.                                       5                       2.4
0
Budget                                                          Authorized Forecasted  Costs
Incurred
On Budget
Change Order                                               Construction Costs
Current Quarter       Project Total             $2.0
Number of COs                 0                   0
Amount of Cos                 $0                   $0
$1.5
$1.0
Risks
This project directly supports the North-Star program. The North Terminals        Dollars in Millions $0.5
0.0        0.0        0.0
Utility Upgrade Project construction will be phased in order to support the             $-
Initial    Change     Spent
North-Star program.                                                                          Orders
Budget Transfers                                                 Photo
Amount           From             To
$0



AIRPORT
32  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Central Terminal Infrastructure Upgrade
Project: C800722                     Install H elevators, stairways   Project Status:
Budget: $16,834,000                  for mezzanine levels of the central     Schedule:          Within or Ahead 
Phase:  Construction                 terminal. Reconfigure tenant spaces   Budget: On or Under
Start:  5/8/2015                        on the Concourse level of the          Status Reset: 6/27/2017
Schedule Completion: 12/26/2019     central terminal in order to improve    (Commission Construction Auth.)
customer service and ee 
Significant Developments                                           Budget/Costs Incurred
Phase I construction in the southern half of the Central Terminal started as
20
planned on February 8, 2018.                                                           16.8      16.8
Schedule
15
Project is on schedule                                                               Dollars in Millions 10
5                            1.9
Budget
0
Project is on budget                                                                     Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                2                    2                 $12.0   10.3
Amount of COs              $1,026               $1,026               $10.0
Dollars in Millions  $8.0
Justification for COs: Varying site conditions
$6.0
$4.0
Risks
$2.0                0.0        0.1
Construction delays due to equipment manufactures/suppliers not meeting
$-
commitments.                                                                  Initial   Change   Spent
Orders
Budget Transfers
Amount           From             To            Photo
$6,190,000             C800638              C800722



AIRPORT

Port of Seattle 1Q 2018 Report  33

FIRST QUARTER REPORT, 2018
Concourse C New Power Center
Project: C800724                   Add new 3200A double ended unit       Project Status:
Budget: $10,500,000                substation on Ramp level at column       Schedule:           Delayed
Phase:  Design                    line F/40 for a new electrical room in     Budget: On or Under
Start:  10/26/2014                   Concourse C. Existing distribution        Status Reset: n/a
Schedule Completion: 12/28/2019  panels will be re-fed from the new        (Commission Construction Auth.)
power center, new distribution panels
and branch circuit panels will be added. 
Significant Developments                                           Budget/Costs Incurred
Ninety percent Design Review is in progress and requiring more time than
12                 10.5
typical due to high level of design complexity and heavy staff workloads.
10
Schedule                                                         Dollars in Millions  8
6
Project is behind schedule due to design development complexities and heavy
4
staff workloads.                                                                            2.0
2                             1.0
Budget                                                         0
Authorized  Forecasted    Costs
Project is on budget                                                                                          Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
None
Budget Transfers
Amount           From             To
$0


AIRPORT

34  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
South Satellite (SSAT) Terminal Renovation
Project: C800743                      Programing, planning, design and    Project Status:
Budget: TBD                      construction for renovation of the     Schedule: Delayed 
Phase:  Planning                     SSAT                            Budget: On or Under
Start:  Q1 2017                                                               Status Reset: N/A
Schedule Completion: TBD 
Significant Developments                                           Budget/Costs Incurred
Planning and programming efforts continue on a range of options including full
6
renovation and shorter-term programs to address facility needs for the next 10-           4.6
5
15 years.                                                                          Dollars in Millions 4
3                          2.4
Schedule
2
Q4 2017 Port-wide goal to recommend a preferred design concept was not met.
1
By the end of Q2 2018, the project team will identify a full range of options for
0
consideration.                                                                        Authorized Forecasted   Costs
Incurred
Budget                                                           Construction Costs
This project was included in the 2018 - 2022 capital budget and plan of finance  None
with preliminary estimated total cost of $600 million.  This estimate will be
refined as the scope and timing of the project is more clearly understood.          Photo
Peak Hour Operation
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None
Budget Transfers
Amount            From              To
$0
Cost of Construction Growth
N/A

AIRPORT

Port of Seattle 1Q 2018 Report  35

FIRST QUARTER REPORT, 2018
AuA Mitigation Road Removal
Project: C800760                     Wetland mitigation site              Project Status:
Budget: $720,000                     enhancements, including installing    Schedule:          Delayed 
Phase:  Construction                 perimeter chain-link fence and        Budget: On or Under
Start:  8/1/2017                        converting interior paths/roads to      Status Reset: 6/28/2016
Schedule Completion: 12/15/2017     forest.                              (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Bids for fence construction contract due on April 25, 2018. Fencing scheduled
0.8      0.7        0.7
for completion by June 30.                                                        0.7
0.6
Schedule                                                         Dollars in Millions 0.5
0.4                            0.3
Road removal and plant installation were completed on schedule in 2017.           0.3
Contracting delays have pushed expected fencing completion to June 2018.         0.2
0.1
0
Budget                                                          Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Risks
None
Budget Transfers
Amount           From             To
$0



AIRPORT

36  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Concourse B Ramp L 
Project: C800761                     Construct a ramp level holdroom on  Project Status:
Budget: $5     Concourse B to serve airline  Schedule:   Within or Ahead 
Phase:  Construction                 passengers bussed to and from        Budget: On or Under
Start:  4/12/2015                       remotely parked flights at             Status Reset: 3/27/2018
Schedule Completion: 6/2 6    hardstands.           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Site activated in Q1 and is in-use. Work has commenced to provide added
6.2      6.0        6.0
scope elements and complete corrections.
6
5.8
Schedule                                                         Dollars in Millions 5.6
Project now on schedule.                                                         5.4                      5.2
5.2
Budget                                                        5
4.8
Additional budget received.                                                           Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                11                  32
3.5                            3.1
Amount of COs             $48,247             $310,921                    2.8
3
Justification for COs: Changed site conditions and design issues.                   Dollars in Millions 2.5
2
Risks                                                              1.5
1
No significant      risks                                                                                0.3
0.5
0
Budget Transfers                                                        Initial   Change    Spent
Orders
Amount           From             To
$0




AIRPORT
Port of Seattle 1Q 2018 Report  37

FIRST QUARTER REPORT, 2018
Telecommunications Meet Me Room
Project: C800762                     Airport Telecommunications $%&&'   Project Status:
Budget: $3 !" ###    Me Room$ is a gateway to the  Schedule:   Within or Ahead 
Phase:  Design                      internet and allows quick, reliable,    Budget: On or Under
Start: 11/20/2016                      and costc&((&)'*+& network            Status Reset: 9/26/2017
Schedule Completion: 5/4/2020        connections for all of the airporta,      (Commission Construction Auth.)
tenants
Significant Developments                                           Budget/Costs Incurred
Design work has started and the preliminary Site Plan has been developed.
5.000
3.93        3.93
Schedule                                                        4.000
On schedule.                                                                 3.000
2.000
Budget                                                       Dollars in Millions                    0.96
1.000
On budget.
0.000
Authorized  Forecasted     Costs
Change Order                                                                  Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                  $0               None at this time
Risks
None
Budget Transfers
Amount           From             To
$0





AIRPORT
38  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Concourse D -/0124/71 Terminal
Project: C80076C                     Construct a 32,500 SF building       Project Status:
Budget: $38,400,000                  using the alternative public works     Schedule:           Delayed 
Phase:  Construction                 design/build method to support       Budget: On or Under
Start:  2/28/2016                       passengers bused to and from          Status Reset: N/A
Schedule Completion: 8/1/2018       airline flights parked at remote        (Commission Construction Auth.)
hardstands.
Significant Developments                                           Budget/Costs Incurred
The project team is evaluating the addition of a covered canopy over the                   38.4      8:;<
40.000
passenger drop-off area at top of the sloped walkway.                             35.000
30.000
Schedule                                                        25.000                 18.0
20.000
Project has been delayed due to unforeseen conditions in the ground at the site    15.000
which caused additional work to mitigate. The project team is now tracking to    10.000
5.000    Dollars in Millions
August 1, 2018 activation.                                                        0.000
Authorized Forecasted    Costs
Budget                                                                        Incurred
Project is on budget
Construction Costs
Change Order
30.000
24.28
Current Quarter       Project Total          25.000
Number of COs                 3                   19               20.000
Amount of COs             $207,383             $433,608            15.000
Justification for COs: Changed conditions                                         10.000                       =;<>
5.000    Dollars in Millions                    0.23
Risks                                                             0.000
Initial     Change     Spent
Potential of unforeseen conditions.                                                                 Orders
Budget Transfers                                                 Photo
Amount           From             To
$0




AIRPORT
Port of Seattle 1Q 2018 Report  39

FIRST QUARTER REPORT, 2018
Safedock Upgrade and Expansion
Project: C80077I                     Install Safedock units at 90 gates.     Project Status:
Budget: $JIKJ@@K@@@    Connect all existing Safedock units Schedule:   Within or Ahead 
Phase:  Design                      to communications. Install           Budget: On or Under
Start:  IMNMJ@OP                        Safedock Gate Operating System.      Status Reset: 2/13/2018
Schedule Completion: 5/22/2020                                          (Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred
This work will complete the installation of Safedock units at all gates at SeaTac                     28.0
30
Airport. The project will enhance safety as well as assisting the airlines in
25
efficient use of gate resources. Design Approval received on February 13th.
20
15
Schedule
10
30% design complete July 2018.                                               Dollars in Millions       3.6
5                            0.1
60% design complete September 2018.
0
90% design complete November 2108                                           Authorized Forecasted   Costs
Commission approval for construction expected January 2019.                                          Incurred
Budget                                                      Construction Contract Costs
On budget
1
0.8
Change Order
Current Quarter       Project Total
0.6
Number of COs                 0                   0
0.4
Amount of COs                $0                  $0                Dollars in Millions  0.2
0.0        0.0        0.0
Justification for COs: None                                                             0
Initial    Change     Spent
Orders
Risks
Without a great deal of coordination with multiple projects there is a potential
for delays.
Budget Transfers
Amount           From             To
$981,750             C800779              C?@@B?D
Cost of Construction GroGEF
None

AIRPORT

40  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
South Satellite Narrow Body Configuration
Project: C800781                     Planning, design and construction    Project Status:
Budget: $5,500,000                   of three new narrow body positions    Schedule:           Delayed 
Phase:  Construction                 at the S. Satellite. Scope includes     Budget: On or Under
Start:  2/23/2016                       new: 1 passenger loading bridge       Status Reset: 2/23/2016
Schedule Completion: 9/30/2019      (PLB), 1 fuel pit, a passenger ramp    (Commission Construction Auth.)
at S10, portable equipment, and
pavement marking.
Significant Developments                                           Budget/Costs Incurred
Fuel Pit Work Continues to progress in support of the IAF program.                       5.5       5.5
6
5
Schedule
4
Construction coordination continues to progress in conjunction with the IAF       Dollars in Millions  3
program.                                                                    2                    1.0
1
Budget                                                        0
Project is currently within budget                                                        Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
4.6
Number of COs                 0                   0                   5
Amount of Cos                 $0                   $0                    4
Risks
3
Potential cost and schedule impacts from forecasted shortage of materials and       Dollars in Millions   2
1.0
skilled labor in the current robust Seattle construction market remains a risk.            1
0.0
0
Initial    Change     Spent
Orders
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 1Q 2018 Report  41

FIRST QUARTER REPORT, 2018
EmergencQ Generator Control Renewal and Replacement
Project: C800784                    Replace and re-program generator       Project Status:
Budget: $2,640,000                 programmable logic controllers          Schedule:          Delayed 
Phase: Design                      (PLCs). Install load bank with controls    Budget:        Forecast Overrun
Start: 12/28/2015                      for RSTU SafetyV code required            Status Reset: N/A
Schedule Completion: 1/2/2021       generator load testing.                   (Commission Construction Auth.)
Significant Developments                                            Budget/Costs Incurred
Sixty percent design review resulted in sponsor's request for added scope. New
4                  3.0
scope impact to budget and schedule is under development.
3
3
Schedule
2
Schedule is delayed due to limited staff resources.                                   Dollars in Millions  2
0.8
1
0.4
Budget                                                         1
0
Budget overrun is anticipated due to project delays and added scope                      Authorized  Forecasted    Costs
Incurred
Change Orders
Current Quarter       Project Total           Construction Costs
Number of COs                0                   0                Not applicable
Amount of Cos                 $0                   $0
Justification for COs: None this quarter
Risks
None
Budget Transfers
Amount           From             To
$0




AIRPORT
42  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
PLB ReneW X Replace Phase 2
Project: C800793                     Replace nine passenger loading      Project Status:
Budget: $10,000,000                  bridges (PLB's)                     Schedule:           Within or Ahead 
Phase:  Construction                                                  Budget: On or Under
Start:  12/17/2015                                                            Status Reset: 2/28/2017
Schedule Completion: 12/12/2020                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design is in progress for the loading bridges at gates S11 and B10.
12                10.0
10
Schedule
8
Project is on schedule
6
4      2.3
Budget                                                       Dollars in Millions 2                 0.2
Project is within budget
0
Authorized Forecasted    Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Construction Contract Cost
Number of COs                 0                   0
Not Applicable
Amount of COs                $0                  $0
Risks
None
Budget Transfers
Amount           From             To
$0





AIRPORT
Port of Seattle 1Q 2018 Report  43

FIRST QUARTER REPORT, 2018
SSAT HVAC Infrastructure Upgrade
Project: C800798                     Replace hot and cold deck fans,      Project Status:
Budget: $13,925,000                  coils and controls with energy         Schedule:           Delayed 
Phase:  Design                      efficient new air handler, coils and    Budget: On or Under
Start:  9/19/2016                       controls. New scope will replace      Status Reset: 8/8/2017
Schedule Completion: 12/30/2020     ceiling, lights, fire sprinklers,         (Commission Construction Auth.)
signage, and carpet.
Significant Developments                                           Budget/Costs Incurred
Single bidder responded to contract advertisementY bid result was 180% of
16     13.9       13.9
engineers estimate. Team is evaluating alternatives, with project stakeholders,       14
including the addition of new project scope.                                        Dollars in Millions 12
10
8
Schedule                                                          6
4
Project is behind schedule due to irregular bid result.
2                            0.7
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Project team anticipates the addition of scope that will likely increase the
budget, TBD.                                                            Construction Contract Costs
Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
Market conditions, difficult site conditions, and material availability may
impact project costs and schedule.
Budget Transfers
Amount           From             To
$0




AIRPORT
44  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Variable Frequency Drive
Project: C800801                     Replace 47 of the oldest Variable  Project Status: Design
Budget: $6,834,000                   Frequency Drives (VFDs) installed   Schedule:           Within or Ahead 
Phase:  Design                      at  Seattle  Tacoma  International   Budget: On or Under
Start:  7/10/2017                       Airport.                              Status Reset: 5/2lmnoqr
Schedule Completion: 5/26/2020                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Received 30% design submittal.
8                 6.8
7
Schedule                                                          6
5
Project design is progressing on schedule                                            4
3      2.0
2
Budget                                                       Dollars in Millions 1                 0.1
Project budget remains unchanged                                                0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Contract Costs
Number of COs                 0                   0
6
Amount of COs                $0                  $0
5
Dollars in Millions    4
Risks
3
None
2
1
Budget Transfers                                                          0.0     0.0     0.0
0
Amount           From             To                  Initial  Change   Spent
Orders
$0
Z[\ p]^_`bdf a ghi jk motor
AIRPORT
Port of Seattle 1Q 2018 Report  45

FIRST QUARTER REPORT, 2018
Chiller Panel Upgrade
Project: C800811                     Convert integrated control panels     Project Status:
Budget: $900,000                     for 3 central mechanical plant         Schedule:          Within or Ahead 
Phase:  Construction                 chillers                           Budget: On or Under
Start:  9/20/2017                                                             Status Reset: 1/9/2018
Schedule Completion: 4/15/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Completed 30% design. Working towards 90% design.
1      0.9        0.9
Schedule                                                         0.8
On Schedule                                                             Dollars in Millions 0.6
0.4
Budget
0.2
0.0
On Budget
0
Authorized Forecasted    Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Construction Contract Costs
Number of COs                 0                   0
Amount of COs                $0                  $0                   1
Justification for COs:                                                                  0.8
0.6
Risks
None                                                          Dollars in Millions  0.4
0.2
0.0        0.0        0.0
Budget Transfers                                                     0
Initial    Change     Spent
Amount           From             To                       Orders
$0
Photo
Cost of Construction Growth
None



AIRPORT

46  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
SSAT Structural Improvements
Project: C800818                     Improvements to the South Satellite  Project Status:
Budget: $3,850,000                   (SSAT) building to address           Schedule:           Delayed 
Phase:  Construction                 structural deficiencies. Work         Budget: On or Under
Start:  12/28/2015                      includes abatement of regulated        Status Reset: 8/8/2017
Schedule Completion: 9/26/201     materials.                      (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Executed construction contract with second low bidder in January and issued
5.0
notice to proceed in March. PCS began work on Phase 1 of the concourse level              4.2
3.9
work in March.                                                                 4.0
3.0
Schedule                                                         Dollars in Millions   2.0
The completion of design was delayed into Q4 2017 due to scope changes and                               0.6
1.0
resource constraints. Contract execution was delayed to Q1 2018 due to               0.0
contract compliance. Phase 2 concourse level work has been delayed until Q4             Authorized Forecasted  Costs
Incurred
2018 due to operational and tenant coordination requirements.
Budget                                                      Construction Contract Costs
Overall project budget has decreased from $4,150,000 to $3,850,000 due to
$2.00     1.7
favorable bid results. Project is on budget.
$1.50
Change Order
$1.00
Current Quarter       Project Total
Number of COs                 0                   0                 Dollars in Millions $0.50
0.0       0.0
Amount of COs                $0                  $0                   $-
Justification for COs: None issued this quarter.                                              Initial   Change    Spent
Orders
Risks
Photo
Regulated Materials Support: stuvwx than anticipated monitoring and
support required given Contractoryz schedule and phasing.
Tenant Restoration: Phase 2 of the concourse level work impacts restaurant
operations and is now scheduled to occur when the restaurants are closed
for remodeling. If the restaurant work is delayed, additional budget will be
required for addition of restoration scope and e{|w}~w~ schedule.
Budget Transfers
Amount           From             To
$0
Strengthened Column (Concourse 
AIRPORT
Port of Seattle 1Q 2018 Report  47

FIRST QUARTER REPORT, 2018
C60 Interim Baggage System Project
Project: C800825                  Implement four distinct scope elements   Project Status:
Budget: $13,450,000               with the objective of increasing            Schedule: Delayed 
Phase:  Construction             reliability and capacity on the C60        Budget: On or Under
Start:  12/13/2015                  baggage system through the interim         Status Reset: N/A
Schedule Completion:             period before the Baggage Optimization    (Commission Construction Auth.)
10/10/2017                        Project.
Significant Developments                                           Budget/Costs Incurred
TSA Search Room Expansion Project: Internal Port resources including PCS
14.5     14.2
and AVM Conveyor Shop are continuing to complete remaining puncist
items at contractor cost. This is the final report.                         14
13.5
Schedule                                                         Dollars in Millions             12.8
13
Project is substantially complete, with only punch list items remaining.                                       12.5
12.5
Budget                                                        12
Authorized Forecasted    Costs
Projecting budget to come in under budget and authorization. $750,000 of                                 Incurred
savings was returned in first quarter, remaining savings will be returned upon
completion.                                                                  Construction Costs
Change Order                                                   6   5.4        5.1
5
Current Quarter       Project Total
Number of COs                                    20
4
Amount of COs                                $ 102,136.34
3
Justification for COs: Varying site conditions, error/omissions by owner and       Dollars in Millions   2
1            0.1
designer, and regulatory requirements.
0
Risks                                                                   Initial Change Spent
Orders
No risks anticipated at this time, contingency funds available if needed.
Budget Transfers
Amount           From             To
$750,000             C800825         C800753 (Savings)



AIRPORT

48  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Arc Flash Hazard Mitigation
Project: C800826                     Replace medium voltage fused       Project Status:
Budget: $7,533,000                   switches with medium voltage        Schedule:           Within or Ahead 
Phase:  Design                      circuit breakers at six power          Budget: On or Under
Start:  9/21/2016                       centers.                               Status Reset: 9/26/2017
Schedule Completion: 11/9/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Reached 90% completion in Design.                                                  7.53      7.53
8.000
7.000
Schedule
6.000
Project is on schedule.                                                              5.000
4.000
3.000
Budget
2.000    Dollars in Millions
Project is within budget                                                            1.000                        0.13
0.000
Authorized  Forecasted     Costs
Change Order                                                                  Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                  $0               None at this time
Risks
None
Budget Transfers
Amount           From             To
$0





AIRPORT
Port of Seattle 1Q 2018 Report  49

FIRST QUARTER REPORT, 2018
Holdroom Seating for Concourses B  C
Project: C800833                     Replace existing passenger           Project Status:
Budget: $    holdroom seating in Concourses B Schedule:   Delayed 
Phase:  Construction                 and C. Provide electrical             Budget: On or Under
Start:                         improvements to support required      Status Reset: 4/11/2017
Schedule Completion: 8/10/2018      power for new seating.               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction bid was advertised. Seating procurement was expedited in order to                  
10
improve the passenger experience.
8
Schedule                                                          6
Construction bid advertisement occurred later than originally scheduled.              4
Construction bid opening scheduled for May and construction to start in July.      Dollars in Millions  2
0.2
0
Budget                                                          Authorized Forecasted  Costs
Incurred
On budget
Change Order                                               Construction Contract Costs
Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None at this time
Budget Transfers
Amount           From             To
$0




AIRPORT
50  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Ground Based Augmentation System (GBAS) Upgrade
Project: C800834                     Upgrade Sea-Tac's Ground Based    Project Status:
Budget: $3,529,000                   Augmentation System (GBAS)        Schedule:           Delayed 
Phase:  Design                      from a beta system to a fully         Budget: On or Under
Start:  1/5/2017                        functioning navigational aid.          Status Reset: 9/12/2017
Schedule Completion: 12/31/2020                                         (Commission Const Auth.)
Significant Developments                                           Budget/Costs Incurred
Contract with  I still in review. Additional meetings scheduled      4.6
5
through Q2.
4                 3.5
Schedule                                                          3
Delay in schedule due to negotiations taking additional time.                       Dollars in Millions  2
1
0.1
Budget
0
Project is within budget.                                                                  Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Number of COs                 0                   0                   1
Amount of COs                $0                  $0                  0.8
Dollars in Millions   0.6
Risks
0.4
None at this time.
0.2
0.0        0.0        0.0
Budget Transfers                                                     0
Initial    Change     Spent
Amount           From             To                       Orders
$0




AIRPORT
Port of Seattle 1Q 2018 Report  51

FIRST QUARTER REPORT, 2018
Tenant Telecommunications DMARC Upgrade
Project: C800841                     Scope:                              Project Status:
Budget: $2,815,000                   Standardi tenant net demar    Schedule:           " or Ahead 
Phase:  Design                       for many e" legacy    Budget: On or Under
Start:  2/27/2017                       installations and vacant rties     Status Reset: N/A
Schedule Completion: 4/28/2021
Significant Developments                                           Budget/Costs Incurred
Com   design. " ard   design       2.82
3.000
2.500
Schedule
2.000
Project is on schedule
1.500
1.000     0.72
Budget
0.500    Dollars in Millions
0.05
Project is on budget
0.000
Authorized  Forecasted     Costs
Change Order                                                                  Incurred
Current Quarter         Project Total
Number of COs                   0                     0                 Construction Costs
Amount of COs                  $0                    $0                None at this time
Risks
None at this time
Budget Transfers
Amount            From              To
$0





AIRPORT
52  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
AOA Perimeter Fence Line Standards
Compliance
Project: C800842                     This "ect  re the          Project Status:
Budget: $6,935,000                   remaining 7-foot AOA fence line      Schedule:           Delayed 
Phase:  Design                       the ne standard height of 12-   Budget: Forecast Overrun
Start:  1/29/2017                       foot  one foot barbed " at       Status Reset: 6/1
Schedule Completion: 5/31/2019      the to                              (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Ninety " design is under Com the "-a "ess  
City of SeaTac. Coordinated  FAA and started the revie "ess for      8      6.9
certain technical s section.               7  5.7
6
Schedule
5
4
Ninety " design  is  to be distributed in Q2 for internal  Dollars in Millions 3
2
and FAA revie The overall schedule is delayed since more time is needed in      1                  0.3
design to include additional "ect sco identified.                0
Authorized Forecasted    Costs
Incurred
Budget
Need Commission authori for funds to cover the additional "ect sco  Construction Contract Costs
identified by Port Security.
1
Change Order                                                  0.8
Current Quarter       Project Total              0.6
Number of COs                 0                   0                  0.4
Amount of COs                $0                  $0                Dollars in Millions  0.2
0.0        0.0        0.0
0
Risks
Initial    Change     Spent
Orders
TSA re" changes to the "" fence height and/or mesh si  
increase the material cost and cause delays in "ect delivery.
Photo
Close coordination  Port Security to ensure the com  the most
current TSA standards.
Budget Transfers
Amount           From             To
$0

AIRPORT

Port of Seattle 1Q 2018 Report  53

FIRST QUARTER REPORT, 2018
ADR  Program 
Project:  C800846                  Install utilities to su (8) ne        Project Status:
Budget: $1,240,000                 ADR  locations. (6)               Schedule:            or Ahead 
Phase:  Design                    Intermediate  and (2)            Budget: On or Under
Start:                       Introductory                      Status Reset: N/A
Schedule Completion: 12/31/2020                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Designer submitted Introductory  conce for revie
1.4     1.24       1.24
1.2
Schedule
1
On schedule.                                                                  0.8
0.6
Budget                                                       Dollars in Millions 0.4
0.2                           0.02
On budget.                                                                   0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total
Number of COs                0                    0
Amount of COs                $0                  $0
Risks
Com s interests causing relocation or deletion of  locations.
Budget Transfers
Amount           From             To
$0




AIRPORT

54  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Checkpoint 5 l Replacement
Project: C800858                     Re c the w  at Checrp 5     Project Status:
Budget: $1,200,000                    w a new door system to impic     Schedule:           Delayed 
Phase:  Construction                 the efficiency and customer service    Budget: On or Under
Start:  8/7/2016                        as wc as the aesthetic ac  c     Status Reset: N/A
Schedule Completion: 5/4/2018       of the checrp entry.               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Emergency exit door and signage infrastructure installed in AA Final testing
1.4      1.2
and commissioning of the final exit door to be comc c in M A
1.2
0 
Dollars in Millions  1
Schedule                                                         0.8                  0.6
Resource availability has brought the p ect further behind schedule.          0.6
0.4
0.2
Budget
0
Project is w  budget.                    Authorized Forecasted Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Not A c
Number of COs                0                   0
Amount of COs              $0.00                $0.00              Photos
Risks
M   risr remaining.
Budget Transfers
Amount           From             To
$0                 N                  N 




AIRPORT
Port of Seattle 1Q 2018 Report  55

FIRST QUARTER REPORT, 2018
Terminal Security Enhancements (TSE)
Project: C800862                   The !"ect includes shatter !!#$ng     Project Status:
Budget: $12,941,000                the windows (Phase I) and security and    Schedule:           Within or Ahead 
Phase:  Construction              accessibility im !%&'&()* (Phase II)     Budget: On or Under
Start:  10/8/2017                     for the Main Terminal and SS+ bridge      Status Reset: 10/24/2017
entrances.
Schedule Completion: 6/30/2019                                       (Commission Auth. Construction Phase I
Commission Auth. Design Phase II)
Significant Developments                                           Budget/Costs Incurred
Phase I ect was advertised in J and received a favorable low bid of          12.9
$14
$2,206,466, in March, which was 52.49% lower than the Engineers' estimate of
$12
$4,644,000.                                                                   Dollars in Millions $10    7.8
Phase II received commission authoria for design. Contract negotiations     $8
started with consultant.                                                                 $6
$4
$2
Schedule                                                                             0.2
$0
Phase I is behind schedule due to delay in oning bidsb wor to shorten this     Authorized Forecasted  Costs
time by ex oe contract execution and issuing Notice to Proceed (NTP) to                Incurred
contractor.
Phase II on schedules design k scheduled for early May.          Construction Contract Costs
Budget                                                        $15
Project is within budget. Phase I will be returning budget savings on favorable      Dollars in Millions  $10
bid results in Q2.
$5
Change Order
0.0       0.0       0.0
Current Quarter       Project Total              $0
Number of COs                 0                   0                       Initial   Change   Spent
Orders
Amount of COs                $0                  $0
Risks                                                            Photo
Phase I Windows  Phase II Security
Phase I: Delay in executing contract or issuing NTP could add to schedule
delay.
Phase II: Design of security and access im o o adversely im k 
curbside orations along the Arrival and De o drives.
Budget Transfers
Amount           From             To
$0

AIRPORT
56  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Concourse B Gate Reconfiguration
Project: C800873                     Tenant reimbursement project by     Project Status:
Budget: $9,900,000                    Delta Air Lines to add two new       Schedule:           Within or Ahead 
Phase:  Closeout                     gates and reconfigure four others at    Budget: On or Under
Start:  1/16/2017                       Concourse B.                         Status Reset: N/A
Schedule Completion: 5/26/2017                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The project is complete and is in closeout status.
12      9.9
10                 8.3
Schedule                                                                             7.2
This scope of work and associated companion projects are complete.               Dollars in Millions  8
6
4
Budget
2
All CORs have been reviewed and negotiated. The Port's Cost Engineer is           0
coordinating with Delta's Cost Engineer to validate the final project cost.                Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None identified at this time.
Budget Transfers
Amount           From             To
$0




AIRPORT

Port of Seattle 1Q 2018 Report  57

FIRST QUARTER REPORT, 2018
Fire Station,-/12 Side
Project: C800876                     Install a modular type building and   Project Status:
Budget: $5,500,000                   truck shelter to facilitate an interim    Schedule:           Within or Ahead 
Phase:  Design                      Fire Station on the west side of the    Budget: On or Under
Start:  5/12/2017                       airport.                               Status Reset: N/A
Schedule Completion: 10/12/9:;<                    (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Project was authorized in February.                                                       5.5       5.5
6
5
Schedule
Overall project is on schedule, design submittals schedule has changed.
4
3
Budget                                                       Dollars in Millions 2
1                            0.2
Project is on budget
0
Authorized Forecasted    Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Construction Contract Costs
Number of COs                 0                   0
N/A
Amount of COs                $0                  $0
Justification for COs:                                                              Photo
Risks
None at this time.
Budget Transfers
Amount           From             To
$0
Cost of Construction G34678
None



AIRPORT

58  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Employee Security Screening
Project: C800880                     Add security screening checkpoints   Project Status:
Budget: $@BCDEBEEE    for employees entering the secure Schedule:   Delayed 
Phase:  Construction                 areas of the airport.                 Budget: On or Under
Start:  7/3/2016                                                               Status Reset: 11/28/2017
Schedule Completion: 3/18/201C                                 (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design changes for the North Employee Screening Room and the new Alaska
3.5      3.0        =>?
Baggage Service offices have increased the design time.
3
Dollars in Millions 2.5
Schedule                                                          2
Project site specific design issues required the design to be changed. This has        1.5
0.7
1
delayed the project by approximately three months.
0.5
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Project is within budget. Delay and design changes are being evaluated for
budgetary impact.
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total          Photos
Number of COs                $0                  $0
Amount of COs                $0                  $0
Justification for COs: None
Risks
None identified at this time.
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 1Q 2018 Report  59

FIRST QUARTER REPORT, 2018
Delta Inflight Services Tenant Reimbursement Agreement
Project: C800883                     Prepare for occupancy aFFHIKL       Project Status:
Budget: $1,196,000                   imately 4,000 square feet of vacant    Schedule:           Delayed 
Phase:  Permitting                   space for Delta Air Lines Inflight     Budget: On or Under
Start:  1/12/2017                       Services facility using a Tenant        Status Reset: N/A
Schedule Completion: 12/31/2018     Reimbursement Agreement (TRA).    (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design submitted for building permit.
1.4      1.2        1.2
1.2
Schedule
1
Tenant Reimbursement Agreement pending documentation from Delta            Dollars in Millions 0.8
0.6
Budget                                                        0.4
0.2                           0.1
On budget.
0
Authorized Forecasted    Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                  $0               None
Justification for COs:
Risks
Pre-existing conditions may impact project.
Budget Transfers
Amount           From             To
$0




AIRPORT
60  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Central Terminal Enhancements
Project: C800886                     Provide new passenger charging      Project Status:
Budget: $4,800,000                   station counters, furniture, music      Schedule:           Delayed 
Phase:  Construction                 performance area, waste receptacles   Budget: On or Under
Start:  8/8/2017                        and electrical floor outlets in the       Status Reset: 8/8/2017
Schedule Completion: 7/31/2021      Central Terminal                    (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Completed 90% design. Furniture selection underway.                                   4.8       4.8
5
Schedule                                                          4
In order to align with other project work in the Central Terminal and provide         3
good customer service, the overall project has been delayed. Construction and        2
furniture installation will be completed in phases that are coordinated with the      Dollars in Millions  1
0.2
timing of the other construction in the Central Terminal. The south end of the
0
Central Terminal is expected to be completed by Q1 2019 to accommodate             Authorized Forecasted   Costs
restaurant spaces opening in that area.                                                                        Incurred
Budget                                                      Construction Contract Costs
On budget                                                              Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None at this time
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 1Q 2018 Report  61

FIRST QUARTER REPORT, 2018
Airport Signage Phase 1
Project: CUVVUWU                     Provide shortY[Q\] improvements    Project Status:
Budget: $UXVVVXVVV    to airport signage and wayfinding Schedule:   Within or Ahead 
Phase:  Design                                                        Budget: On or Under
Start:  4/4/2016                                                               Status Reset: N/A
Schedule Completion: 3/30/2020                                          (Commission Construction Auth.)
Significant Developments                                          Budget/Costs Incurred
Early work to install new dynamic signage at Ticketing ZOPQR 1 T 2 was
10.000
completed.                                                                                 8.0
8.000
Schedule                                                       6.000
On Schedule
4.000
2.0
2.000    Dollars in Millions
Budget                                                                          0.2
0.000
On Budget
Authorized  Forecasted     Costs
Incurred
Change Order
Current Quarter       Project Total         Construction Costs
Number of COs                 0                   0              None at this time
Amount of COs                $0                  $0
Risks                                                           Photo
None at this time
Budget Transfers
Amount           From             To
$0




AIRPORT
62  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Taxiways A/B/L/Q Improvements
Project: C800914                     Ta^g`z A/B Reconfiguration of   Project Status:
Budget: $47,500,000                  transition and SMGCS routes,         Schedule:           Within or Ahead 
Phase:  Construction                 Ta^g` v Relocation and Ta^g`    Budget: On or Under
Start:  10/11/2016                      Q partial hot spot mitigation.          Status Reset: 11/n2017
Schedule Completion: 12/31/2018                                         (Commission Const Auth.)
Significant Developments                                           Budget/Costs Incurred
Contract awarded and executed. Construction Notice to Proceed is April 9th.             47.5      47.5
50
Work underway at Taxiway Q, Taxiway A and South Satellite. Concrete and
asphalt demolition and haulingh e^_`d`fgjl and trenching for electrical work.    40
30
Schedule                                                          20
Project is currently on schedule. Anticipate completion of Phase 1/spring work     Dollars in Millions 10
2.4
by May mnq 2018.                        0
Authorized Forecasted    Costs
Budget                                                                        Incurred
Project is on budget.
Construction Contract Costs
Change Order
30     24.9
Current Quarter       Project Total              25
Number of COs                 m                    m                   20
15
Amount of COs             tu100.00             tu100.00
10
Justification for COs: 1). Provide galvanized finish base cans in lieu of             Dollars in Millions   5                      0.0
stainless steel base can for Runway Status vgxyfzh 2) Furnish 6{ transformer      0
-5    Initial    Change     Spent
stands at m|{ int}`d~~lf light base cans in lieu of bricksh m Miscellaneous         0.0
Orders
update and revisions: Barricade line, Curb layout, Pavement markings,
Temporary fi^f~z and Channel Drains invert elevations.
Photo
Risks
Adverse weather is the greatest risk to causing delays in meeting project
schedule of completion of spring/Phase 1 work by May mn Operational
contingencies are being coordinated to mitigate any possible impacts.
Budget Transfers
Amount           From             To
$22,000,000             C800483              C800914
$250,000             C800406              C800914
$1,750,000             C800913              C800914

AIRPORT
Port of Seattle 1Q 2018 Report  63

FIRST QUARTER REPORT, 2018
Automated Screening Lanes Checkpoint Conversions
Project: C800920                     Procurement of Automated          Project Status:
Budget: $17,000,000                  Screening Lanes for Security          Schedule:           Delayed 
Phase:  Construction                 Checkpoints 2, 3, 5 and IAF, and      Budget: On or Under
Start:  5/21/2017                       installation at Security Checkpoints    Status Reset: 12/12/2017
Schedule Completion: 6/30/2018      2, 3 and 5.                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Automated Screening Lanes have been installed at Checkpoint 5 and TSA
20.0     17.0      17.0
training is underway. Equipment supply issues have delayed Checkpoint 2
construction which will now start after the busy summer travel season.                15.0
Checkpoint 3 will be completed after Checkpoint 2 starting in 2018.
10.0
Schedule                                                         Dollars in Millions  5.0
0.3
Project is behind schedule due to supply issues for a critical component to the
0.0
installation at Checkpoint 2.                                                                Authorized Forecasted   Costs
Incurred
Budget
Project is within budget                                                           Construction Contract Costs
Not applicable
Change Order
Current Quarter       Project Total          Photo
Number of COs                 0                   0
Amount of COs                $0                  $0
Justification for COs:
Risks
Installation of infrastructure has proven difficult due to the tight space
available.
Budget Transfers
Amount           From             To
$0
Cost of Construction Growth
None

AIRPORT

64  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
3 Ticket Counters
Project: C800                     Convert existing standard chec    Project Status:
Budget: $1,700,000                   counter arrangement at the north      Schedule:           Within or Ahead 
Phase:  Construction                 end of  3's ticketing lobby in     Budget: On or Under
Start:  11/7/2017                       the Main Terminal to create 10        Status Reset: 1/9/2018
Schedule Completion: 7/31/2018      common-use check positions.       (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design is completed and the project is in the permitting process.
2.000      1.70        1.70
Schedule
1.500
This project is on schedule.
1.000
Budget
0.500    Dollars in Millions
This project is within budget.                                                                                    0.04
0.000
Authorized  Forecasted     Costs
Change Order                                                                  Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                  $0               None at this time
Risks
Projects with accelerated schedules are inherently at a higher risk for scope
development or design errors.
Budget Transfers
Amount           From             To
$0




AIRPORT
Port of Seattle 1Q 2018 Report  65

FIRST QUARTER REPORT, 2018
CDD  CPO Office Relocation  #C800982)
Project: C800982                     Design communications             Project Status:
Budget: $9,057,000                    infrastructure, purchase and install     Schedule:           Delayed 
Phase:  Design                      furniture and communications to      Budget: On or Under
Start:  11/7/2017                       support the relocation of staff to       Status Reset: N/A
Schedule Completion: 5/1/2017       SeaTac Office Center.                (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Tenant improvements, by the building management company, at SeaTac Office
10      9.1        9.1
Center are underway. Communications design is nearing completion and final
8
furniture selections underway.
6
Schedule                                                          4
Project is behind schedule due to leasing company delay in preparing the site       Dollars in Millions  2
0.0
for Port occupancy.                                                                0
Authorized Forecasted    Costs
Incurred
Budget
Within budget
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Justification for COs:
Risks
Leasing agency could further delay completion of tenant improvements, further
delaying the project
Budget Transfers
Amount           From             To
$0
Cost of Construction Growth
None

AIRPORT

66  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Lora Lake Apt MTCA Remediation
Project: 104395, 104396               Remediation of contaminated soils   Project Status:
Budget: $24,300,000                  at   Apartments site and     Schedule:           Within or Ahead 
Phase:  Construction                 Capping and filling of the         Budget: On or Under
Start:  9/26/2010                        establishing wetland area        Status Reset: 9/1"
Schedule Completion: 12/31/2018     adjoining Miller Creek.               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Finalizing wetland design based on sediment bubble. Working on
30
options/timing to break berms between the lake-wetland and the wetland-creek            24.3
25                21.4
to allow passive draining to begin.                                                  Dollars in Millions 20
15
Schedule                                                                             8.7
10
Lake site is winterized. Phase 2 work will resume July 2018
5
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Project is within budget.
Change Order                                               Construction Costs
Current Quarter       Project Total              10   8.9
Number of COs                 2                   8
8                    6.8
Amount of COs            -$28,223.84          $106,776.16
Justification for COs: 1). CO Reconciliation of CO   
6
Apartments CWTS 2) CO Reconciliation of CO SR518 Slope Slide
4
Repair                                                                      Dollars in Millions   2
0.1
0
Risks                                                                   Initial Change Spent
Orders
Continue monitoring water accumulation. Survey of sediment bubble and lake
boundaries on going.                                                          Photo

Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 1Q 2018 Report  67

FIRST QUARTER REPORT, 2018
Flight Corridor Safety Program  Phase 1 Port Propert
Project:                        Removal of obstructions to           Project Status:
Budget: $5,806,000                   navigable airspace on Port of          Schedule:           Delayed 
Phase:  Construction                 Seattle property at Seattle-Tacoma    Budget: On or Under
Start:  5/                       International Airport, including        Status Reset: 11/14/2017
Schedule Completion: 12/2017   extensive replanting and        (Commission Construction Auth.)
revegetating on-site.
Significant Developments                                           Budget/Costs Incurred
The remaining work of Phase 1 includes the removal of invasive species and
7
replanting at Port site P-4, P-5 and Off-site Mitigation Areas (OMA). The 90%            5.8       5.8
6
design package was distributed for review in April 2018 with the final design         5
planned to be completed in May 2018.                                          Dollars in Millions                        
4

Schedule                                                          2
1
Ninety percent design package was completed with the advertisement of the          0
project planned to start in Q2 2018.                                                      Authorized Forecasted   Costs
Incurred
Budget
Construction Costs
The project is currently within budget.
2.5
2.0
Change Order
2      1.7
Current Quarter       Project Total
1.5
Number of COs                 2                   15
1.0
Amount of COs            $121,039.55          $997,516.76            Dollars in Millions   1
0.5
Justification for COs: 1) Reconciliation of CO#1 and Access Route revisions;
2) P-4 Stabilization.                                                                       0
Initial    Change     Spent
Orders
Risks
There's risk of availability/lead time of certain species of trees for replanting.     Photo
Close coordination with Environmental and CM team for alternatives of tree
species.
Budget Transfers
Amount           From             To
$0

AIRPORT

68  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
North East Redevelopment Area Program
Project: U00239                       This is an FAA funded project with   Project Status:
Budget: $5,000,000                   participation from the City of         Schedule:           Within or Ahead 
Phase:  Design                      Burien but led by Port. The project    Budget: On or Under
Start:  8/16/2015                       is to redevelop the Area north of the   Status Reset: 10/
Schedule Completion: 8/14/2018      airport in the City of Burien.          (Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred
Commission authorized amendment to consultant contract in January, to the
authorized project budget of $5 million, in order to complete the design.             $6     5.0       5.0
Quarterly design management team meeting held with FAA, providing a            $5
progress update on the status of designs for the project.                               $4
$3
Schedule                                                          $2
Project is on schedule.                                                               Dollars in Millions                          0.8
$1
$-
Budget                                                          Authorized Forecasted  Costs
Incurred
Project is within budget. The project has a $3.8 million dollar FAA Grant and
" participation from the City of Burien and " by the Port.                 Construction Costs
N/A Design Only
Change Order
Current Quarter       Project Total          Photo
Number of COs               N/A                 N/A
Amount of COs               N/A                 N/A
Risks
Manage design resources of the consultant so that all deliverable are completed
prior to the end of grant period August 2018.
Budget Transfers
Amount           From             To
$0



AIRPORT

Port of Seattle 1Q 2018 Report  69

FIRST QUARTER REPORT, 2018
Flight Corridor Safety Program Phase 2 and Phase 3
Project: U00356                       Multi-year program to manage       Project Status:
Budget: $2,605,000                   obstructions consisting of trees and    Schedule:           Delayed 
Phase:  Design                      other vegetation off Port property     Budget: On or Under
Start:  1/8/2017                        around Seattle Tacoma                Status Reset: 2/28/2017
Schedule Completion: 12/31/2019     International Airport, and             (Commission Design Auth.)
replanting lower-height vegetation.
Significant Developments                                           Budget/Costs Incurred
Phase 2 and 3 of the program will include managing obstruction on Port
8                 7.2
properties around the airport and replanting. Coordination meeting held with         7
FAA for 7460 forms.                                                        Dollars in Millions  6
5
4
Schedule                                                               2.6
3
A revised project schedule is being developed.                                       2
1                            0.4
0
Budget                                                          Authorized Forecasted  Costs
Incurred
The project is currently under budget.
Change Order                                               Construction Contract Costs
Not Applicable
Current Quarter       Project Total
Number of Cos/                  0                     0
Amount of COs                $0                  $0
Risks
Any delay in the approval process will impact the budget and schedule for the
project delivery.
Close coordination with stakeholders including Operations, Environmental, CM
team and FAA is very important for the successful delivery of the project.
Budget Transfers
Amount           From             To
$0


AIRPORT

70  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Automated Passport Control    Phase 
Project:                        Install 12 additional APC      Project Status:
Budget: $1,400,000                   and 8 Document Verification          Schedule:           Delayed 
Phase:  Construction                 Officer podiums.                   Budget: On or Under
Start:  2/7/2017                                                               Status Reset: N/A
Schedule Completion: 5/18/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Required signage design completed. Construction scheduled to complete in
1.6      1.4
early May                                                                  1.4
Dollars in Millions 1.2
0.9        0.9
Schedule                                                          1
0.8
Completion scheduled for early May 2018                                       0.6
0.4
0.2
Budget
0
Project is under budget.                                                                  Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Not Applicable
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None
Budget Transfers
Amount           From             To
$0




AIRPORT
Port of Seattle 1Q 2018 Report  71

FIRST QUARTER REPORT, 2018
Highline Schools Noise Insulation
Project: C200007                     Highline School Insulation Agreement  Project Status:
Budget: $101,797,000                was intended to provide funding for      Schedule:          Delayed 
Phase: Construction                 sound insulation for 15 schools that      Budget: On or Under
Start: 3/23/1999                       are impacted by aircraft noise from       Status Reset: N/A
Schedule Completion: 11/30/2021     Sea-Tac Airport                       (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State ofWashington             
120     102.1      101.8
and the  School District ( provide matching funds. Currently
100
working with the FAA and State  Federal  to provide a mechanism
80                          63.4
for release of federal Airport Improvement Program (AIP) grant funding for
60
this project. The  School District passed a bond for the construction of
40
Des Moines Elementary School and   School. Construction at   Dollars in Millions 20
Des Moines Elementary will commence in Q2 2018. Construction at  
0
School is scheduled to commence in 2019.                                                  Authorized Forecasted   Costs
Incurred
Schedule
If the FAA is provided a means of funding through federal legislation, then       Construction Costs
funding for Des Moines Elementary School would be required in the third        Not Applicable
quarter of 2018, and   School in the first quarter of 2019.
Ex incurred or to receiving the FAA grant may be reimbursable with
future grant funds as long as HSD used FAA procurement guidelines.
Budget
The budget forecast is within the approved budget and authorization.
Change Order
Current Quarter       Project Total
Number of COs                0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
The current risk is the availability of FAA AIP funding.
Budget Transfers
Amount           From             To
$0

AIRPORT
72  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Tenant Reim
Project: C800154                     Allows for the Port to reimburse        Project Status:
Budget: $4,709,577                   tenants for costs that are normally a      Schedule: W  or Ahead 
Phase: Construction                 landlord responsibility such as          Budget: On or Under
Start: 8/14/2007                       upgrade un-leasable space to a            Status Reset: N/A
Schedule Completion: TBD         leasable condition or correct code       (Commission Construction Auth.)
deficiencies on a tenant construction
p ect.
Significant Developments                                           Budget/Costs Incurred
Tenant reimbursements for progress of the shared kitchen for ADR's kiosk                         4.7
5
program as well as American E buildout of appro 1 ss  
feet of space added to their lounge were made during this past s rter.           4
2.8
3                          2.5
Schedule                                                          2
Schedules vary to meet the needs of the tenant performing the work.               Dollars in Millions  1
0
Budget                                                          Authorized Forecasted  Costs
Incurred
This p ect's budget was increased by $2M to cover the reimbursement to
Ivar's for building out the shared kitchen that will support the kiosk program
during the Central Terminal Infrastructure Upgrade Pro P                Construction Costs
Not Applicable
Change Order
Current Quarter          Pro P Total
Number of COs                0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
None
Budget Transfers
Amount            From              To
$           Non-Aero Allowance         C80015C
AIRPORT
Port of Seattle 1Q 2018 Report  73

FIRST QUARTER REPORT, 2018
Shilshole Bay Marina Paving
Project: C800355                     Repave areas of Shilshole Bay       Project Status:
Budget: $2,000,000                    Marina not rehabilitated in the 2    Schedule:           Delayed 
Phase: Design                        major capital redevelopment. Full     Budget: On or Under
Start: 1/1/2016                         depth replacement in some failed      Status Reset: 11/! "2 !#
Schedule Completion: 6/30/2019      areas and ee pavement         (Commission Construction Auth.)
grinding and overlay.
Significant Developments                                           Budget/Costs Incurred
One hundred percent design complete. Permits submitted with Seattle
2.5
Department of Construction & Inspections ( comments received back.      2.00
1.87
2
Schedule                                                         1.5
to be performed under a single construction contract with SBM Tenant        Dollars in Millions  1
Service Buildings ( The building project was delayed due to   0.5
0.17
consideration of a second floor alternative resulting in delay of this concurrent        0
paving work also. Target paving schedule is fall 2018, but will be left to the            Authorized Forecasted   Costs
Incurred
discretion of the contractor and may be performed in Spring of 2019 after most
of restroom construction complete. Current target is to have the new facilities
Construction Costs
to be online no later than mid-2019.
1
Budget
0.8
Project is within the approved budget.
0.6
Change Order                                                  0.4
Current Quarter       Project Total
Dollars in Millions   0.2
0.0        0.0        0.0
Number of COs                0                   0                    0
Initial    Change     Spent
Amount of Cos                 $0                   $0                              Orders
Justification for COs: N/A
Risks
tied with Restroom schedule. Phasing and coordination will be critical
on active marina parking areas. Contract includes phasing rer to limit
parking impacts.
Budget Transfers
Amount           From             To
$0

MARITIME
74  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Shilshole Tenant Service Buildings
Project: C800356                     Replacement/rehabilitation of five    Project Status:
Budget: $10,100,000                  restrooms and laundry facilities at     Schedule:           Delayed 
Phase: Design                        Shilshole Bay Marina by June 89:;    Budget: On or Under
Start: 1/6/2015                         for $10.1M.                           Status Reset: 11/:<=89:;
Schedule Completion: 6/30/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
One hundered percent design complete. Permits submitted with Seattle
12
Department of Construction % Inspections ')*+,- and comments returned.       10.10   9.52
10
8
Schedule
6
The overall schedule was tightened due to additional design effort to evaluate
4
and perform preliminary design on the second floor option. Current target is to     Dollars in Millions                         1.20
2
have the new facilities to be online by mid-2019.
0
Authorized Forecasted    Costs
Budget                                                                        Incurred
Project is within the approved budget.
Construction Costs
Change Order                                               None at this time
Current Quarter       Project Total          Photo
Number of COs                0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
Schedule and phasing the work in an active site continue to be the primary
risks. Construction costs in Seattle continue to be increasing and volatile which
may lead to higher than e/045647 bids.
Budget Transfers
Amount           From             To
$0



MARITIME
Port of Seattle 1Q 2018 Report  75

FIRST QUARTER REPORT, 2018
SBM Pad Site Development
Project: C800445                     Provide utility extensions to          Project Status:
Budget: $500,000                     support tenant development of new    Schedule:          >?@A?B or Ahead 
Phase:  Planning                    restaurant on pad site by Duke's      Budget: On or Under
Start:  1/1/2018                                                               Status Reset: N/A
Schedule Completion: 9/GHIJHKL                (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Site utilities identified, initial coordination of schedule with Duke's
0.6      0.5        0.5
0.5
Schedule
Dollars in Millions 0.4
Schedule dependent on tenant development currently in design.                    DEF
0.2
Budget                                                                          0.1
0.1
>?@A?B budget
0
Authorized Forecasted    Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Construction Contract Costs
Number of COs                 0                   0
Amount of COs                $0                  $0                   1
Justification for COs:                                                                  0.8
Dollars in Millions   0.6
Risks
0.4
Existing utility extensions must be closely coordinated with tenant construction
0.2
schedule and surrounding work.                                                         0.0      0.0      0.0
0
Initial    Change     Spent
Budget Transfers
Orders
Amount           From             To
$0
Cost of Construction Growth
None


MARITIME

76  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
FT Redevelopment Phase I
Project: C800525                     Demolition of net sheds a b c and    Project Status:
Budget: $[\]^^\^^^    the C-12 Bank Buildingd    Schedule:   Delayed 
Phase:  Design                      construction of 2 light industrial      Budget: On or Under
Start:  12/1/2009                       buildings, renovation of Ship          Status Reset: N/A
Schedule Completion: 12/]_`2019   Supply Building, open gear storage  (Commission Construction Auth.)
improvements, and associated site
infrastructure improvements. 
Significant Developments                                           Budget/Costs Incurred
Project demolition permit issued by SDCI. Ninety percent design for buildings
5
demolition completed and construction MNOmolition) funding authorized.             XYZZ    XYZZ
Master planning and QRS design for new buildings completed. Demolition      4
bidding and project design ON HOTU pending resolution of proposed Gateway    X
Building tenant lease agreement.                                                  Dollars in Millions  2
1.05
1
Schedule
0
Project currently ON HOTU for demolition of bank and Net Sheds V and 8 in       Authorized Forecasted  Costs
Incurred
2018 and start of construction of Gateway Building at Fishermen's Terminal in
2019.
Construction Contract Costs
Budget
1
Project currently within authorized budget.
0.8
Change Order                                                  0.6
Current Quarter       Project Total              0.4
Number of COs                 0                   0                 Dollars in Millions  0.2
0.0        0.0        0.0
Amount of Cos                 $0                   $0                    0
Initial    Change     Spent
Orders
Risks
None at this time.
Budget Transfers
Amount           From             To
$0
Cost of Construction Growth
None

MARITIME

Port of Seattle 1Q 2018 Report  77

FIRST QUARTER REPORT, 2018
FT Net Sheds 3,4,5, f 6 Roof Replacement
Project: C800526                     Replace the existing roofing system  Project Status:
Budget: $    on all four Net sheds with new  Schedule:   Delayed 
Phase:  Construction                 security ladders, gutters, and fall      Budget: On or Under
Start:  11/16/2014                      protection system. Install ii           Status Reset: 12/|g}|j
Schedule Completion: 11/2017   crystalline solar panels at NS 5.    (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction is complete for Net Sheds gh ih 5 and jk The final piece of this

pilot project is to provide lmnm access to the Fronius Data Manager so the data              

can be downloaded for all to see. ICT and PCS are in the process of installing                               
the lmoqtquu Access Point vlwxy on Net Shed z{k        Dollars in Millions 2.5
2
1.5
Schedule                                                          1
0.5
The project is complete. Minor lmnm connections will take place shortly.
0
Authorized Forecasted    Costs
Budget                                                                        Incurred
No budget issues anticipated.
Construction Contract Costs
Change Order
2
1.56
Current Quarter       Project Total                                 1.50
1.5
Number of COs                 0                   8
Amount of Cos                $|}~               $gh{i                  1
Justification for COs: Replacement of rotted members in the structures.             Dollars in Millions  0.5
0.04
Risks                                                                0
Initial    Change     Spent
None                                                                      Orders
Budget Transfers
Photo
Amount           From             To
$0



MARITIME
78  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
FT Docks 3, 4, and 5 Fixed Pier Improvements
Project: C8005                       the existing structural piling    Project Status:
Budget: 6,400,000             with Fiber Reinforced Polymer     Schedule:         or Ahead 
Phase:  Design                      jackets on Docks  and determine   Budget: On or Under
Start:  10/10/2017                      need for replacement in kind of the    Status Reset: 5/15/2018
Schedule Completion: 4/15/2019      existing timber fender system.         (Commission Construction Auth.)
Install cathodic corrosion protection
for steel piles under Dock 5.
Significant Developments                                           Budget/Costs Incurred
Design and permitting are currently underway.                                                    6.40
7
6
Schedule
5
The project schedule has been revised to accommodate installation of the Piling      4
and protections in 2019.                                                               Dollars in Millions  
2     0.80
1                           0.08
Budget
0
On budget                                                                   Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Number of COs                 0                   0                   1
Amount of COs                $0                  $0                  0.8
Risks
0.6
Permit conditions, Facility Operations, Stray voltage and Sole Source.              Dollars in Millions  0.4
0.2
0.0        0.0        0.0
Budget Transfers                                                     0
Initial    Change     Spent
Amount           From             To                       Orders
$0
Cost of Construction Growth
None


MARITIME
Port of Seattle 1Q 2018 Report  79

FIRST QUARTER REPORT, 2018
T-91 Fender Upgrades
Project: C800675                     Upgrade/replace existing timber      Project Status:
Budget: $4,100,000                    fender system at the South end of      Schedule:           Within or Ahead 
Phase: Design                        Pier 91                             Budget: On or Under
Start: 1/31/2016                                                              Status Reset: 8/8/201
Schedule Completion: 3/31/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction completed by American Construction Co., substantial completion
5
issued April  2018.                           4.10
4
Schedule                                                          3          2.40
All in-water work, such as pile driving, was accomplished by February 15,           2                      1.38
2018 to comply with permit fish window. Construction completed prior to start     Dollars in Millions  1
of cruise operations.
0
Authorized Forecasted    Costs
Budget                                                                        Incurred
Project is forecast to complete under authorization.
Construction Costs
Change Order                                               Not applicable at this time
Current Quarter       Project Total
Photo
Number of Cos                 2                    2
Amount of Cos              $               
Justification for COs: Change in plastic chamfering, pile driving obstructions
Risks
All work complete.
Budget Transfers
Amount           From             To
$0




MARITIME
80  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
T-91 C173 Building Roof Overlay
Project: C800829                     Overlay the existing standing seam   Project Status:
Budget: $1,561,000                   metal roof with a NEW Single Ply     Schedule: Within or Ahead 
Phase:  Construction                 P Roof Membrane, including      Budget: On or Under
Start:  9/13/2016                       downspouts with a NEW Fall          Status Reset: 1/2""
Scheduled Completion: 12/29/2017    Protection system.                   (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The P Membrane Overlay, Gutters and Fall Protection are all complete.
2
Substantial completion was issued on October  " However the two       1.56   1.50
Carlisle supplied roofing materials  and Perimeter) do not seem to be      1.5              1.27
compatible materials for welding to one another. Carlisle offered a solution to     Dollars in Millions  1
remedy the problem, so RE,  and PM are discussing options for a remedy
and repair.                                                                            0.5
0
Schedule
Authorized Forecasted    Costs
Project is now behind schedule.                                                                          Incurred
Budget                                                      Construction Contract Costs
Project is within budget.
1
0.76                 0.77
Change Order                                                  0.8
Current Quarter       Project Total            Dollars in Millions  0.6
Number of COs                0                    5                  0.4
Amount of COs                $0                $                0.2
0.04
Justification for COs: None this rter                                                 0
Initial    Change     Spent
Risks                                                                          Orders
None
Photo
Budget Transfers
Amount           From             To
$0


MARITIME

Port of Seattle 1Q 2018 Report  81

FIRST QUARTER REPORT, 2018
T-18 Stormwater Outfall Renewal  
Replacement
Project: C800895                     Remove and replace the 1 outfall    Project Status:
Budget: $4,000,000                   pipes and tides gate from the last      Schedule:           Within or Ahead 
Phase:  Design                      downstream manhole to the outlet     Budget: On or Under
Start:  9/26/2016                                                             Status Reset: 
Schedule Completion: 12/2020                         (Commission Design Auth.)
Significant Developments                                           Bu Incurr 
At  design. Permit applications are under review by the tribes and agencies.
5
Construction funding re authorized in February. Began coordination                 4.00
efforts with the Tenant contractor as the work will need to be performed in           4    4.00
conjunction with their work.                                                        
2
Schedule                                                         Dollars in Millions 1                 
Construction is scheduled to begin on five of the 1 outfalls during the summer
0
of 2018.                                                                             Authorized Forecasted   Costs
Incurred
Budget
Construct Contract Costs
Project is within authorization
1
Change Order
0.8
Current Quarter       Project Total
Number of COs                 0                   0
0.6
Amount of COs                $0                  $0                Dollars in Millions  0.4
0.2
0.0        0.0        0.0
Risks                                                                0
Initial    Change     Spent
Delay in receiving in-water permits could delay any anticipated field work                         Orders
Budget Transfers                                                 Photo
Amount           From             To
$0
Cost of Construction Growth
N/A

MARITIME

82  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
T-91 Standoff Barges
Project: C800910                     Procure five additional cruise        Project Status:
Budget: $1,100,000                   standoff barges to replace the         Schedule:           Within or Ahead 
Phase:  Construction                 existing unifloats and complement    Budget: On or Under
Start:  3/17/2017                       the existing fleet of ten purchased      Status Reset: 9/12/201
Schedule Completion: 4/15/2018      in  currently in use            (Commission Construction Auth.)
Terminal 91
Significant Developments                                           Budget/Costs Incurred
Procurement complete and awarded to PC Northwest Steel Fabrication
1.10       1.10
1.2
currently assembling barges.
1
0.8                           0.69
Schedule                                                         Dollars in Millions 0.6
Barges to be delivered June 2018 to be deployed and used for 2018 Cruise
0.4
season  season earlier than originally planned in the capital budget)
0.2
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Five barges procured under current authorization. Possibility of sufficient
budget to procure one additional barge within one year  under current  Construction Contract Costs
contract).                                                                             Not Applicable at this time
Change Order                                               Photo
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
Tight fabrication and material delivery schedules mean barges will be delivered
after first cruise call. Existing barge fleet can accommodate this, not disruption
of cruise anticipated.
Budget Transfers
Amount           From             To
$0



MARITIME
Port of Seattle 1Q 2018 Report  83

FIRST QUARTER REPORT, 2018
Salmon Bay Marina Uplands Improvements
Project: C800993-U00471             New uplands flex industrial          Project Status:
Budget: $2,000,000                   building and associated site           Schedule: Within or Ahead 
Phase:  Planning                    improvements.                     Budget: On or Under
Start:  12/6/2017                                                             Status Reset: 12/5/201
Schedule Completion: 12/31/2020                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Planning and design to start in 2018 once Miller Hull team is under contract.
2.5
2.0
Schedule                                                          2
Planning and design: 2018-2019                                                1.5
Construction: 2019-2020                                                      Dollars in Millions  1
0.5
0.0        0.2
Budget
0
Within budget.                                                                     Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Number of COs                 0                   0                   1
Amount of COs                $0                  $0                  0.8
Dollars in Millions   0.6
Risks
0.4
None at this time
0.2
0.0        0.0        0.0
Budget Transfers                                                     0
Initial    Change     Spent
Amount           From             To                       Orders
$0
Photo
Cost of Construction Growth
None


MARITIME

84  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Viaduct Construction Coordination
Project: E104324, E104535-38         Participate in the design            Project Status:
Budget: $2,900,000                   construction of the bored tunnel, N.    Schedule:          Within or Ahead 
Phase: Implementation                S. portals, Holgate to K St,      Budget: On or Under
Start: 1/1/2009                         Central Waterfront surface streets,     Status Reset: N/A
Schedule Completion: 12/31/2018      related projects to ensure           (Commission Construction Auth.)
adea connection to port
facilities.
Significant Developments                                           Budget/Costs Incurred
Interior structures of Tunnel are complete. Month-to-month lease of P4 
3.50     2.90
continued for restoration activities. Construction continued on Pier  Early      3.00
Utility Work, and Central Waterfront Transmission  Relocation Project.     2.50
Colman Dock construction continued.                                          2.00
1.75
1.41
1.50
Schedule                                                         1.00
0.50   Dollars in Millions
Tunnel opening and  closure are scheduled for Fall 2018. Central       -
Waterfront construction is expected to begin in 2019 following           Authorized Forecasted  Costs
Incurred
demolition. Colman Dock construction to continue through  
Budget                                                      Construction Costs
Not Applicable
Costs were within anticipated 2018 spending.
Photos
Change Order
Installing glass panels on the south
Current Quarter       Project Total          portal head house 2/28/18
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
Project delays due to unforeseen construction issues.
Budget Transfers
Amount           From             To
$0                                                       Southbound tunnel portal 2/15/18


MARITIME
Port of Seattle 1Q 2018 Report  85

FIRST QUARTER REPORT, 2018
P66 Alaskan W Street Improvements
Project: U     Widen a segment of Alaskan Way Project Status:
Budget: $1,657,000                   in the vicinity of the Bell Street       Schedule: Within or Ahead 
Phase:  Construction                 Cruise Terminal to improve traffic    Budget: On or Under
Start:  4/1/2015                        flow and safety during cruise days.     Status Reset: 8/23/2016
Schedule Completion: 4/14                  (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
As of end of March, Port Construction Services substantially completed all the
2      1.7        1.7
roadway and sidewalk paving with remaining signal and lighting work to be
completed by the Seattle Department of Transportation and Seattle City L    Dollars in Millions 1.5
1.1
1
Schedule
0.5
Based on the current progress, the improvements would be ready for the start of
the 2018 cruise season ( 19th).                     0
Authorized Forecasted    Costs
Incurred
Budget
Commission approved additional funding authorization of $375,000 on           Construction Contract Costs
February 27, 2018. Overall expenditure is expected to stay within the approved   In house Construction
budget.
Photo
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Risks
With all the major construction work completed, the risk of the improvement
not ready for the 2018 cruise season is very low.
Budget Transfers
Amount           From             To
$0


MARITIME

86  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
P66 Elevator ## and #4 Control
Project: C80081C)*+,-,.              Control Systems upgrade for         Project Status:
Budget: $1,067,000                   Elevator 3 and 4 at Pier 66.           Schedule: Within or Ahead 
Phase:  Construction                                                  Budget: On or Under
Start:  5/24/2016                                                             Status Reset: N/A
Schedule Completion: 4/C+/-+*1                (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The prime contractor made significant progress on elevators and during        1.10
1.20
the q rter.We did experience a delay related to meeting a code req r       0.95
1.00
for shaft pressurization. When this req r was met, the first elevator
0.80
modernized, elevator was placed back in service having met the L&I                          0.58
0.60
requirements.
0.40
0.20   Dollars in Millions
Schedule
0.00
Project is on schedule.                                                                    Authorized Forecasted   Costs
Incurred
Budget
Construction Contract Costs
On budget
0.6     0 
0.50
Change Order
0.5
Current Quarter       Project Total              0.4
Number of COs                7                    7                  0 
Amount of COs             $67,620             $67,0620               0.2
Justification for Cos:                                                                   Dollars in Millions                  0.07
0.1
0
Risks                                                                    Initial   Change   Spent
Orders
None
Budget Transfers
Amount           From             To
$0
Cost of Construction Growth
None

ECOE D ! "$%& E'

Port of Seattle 1Q 2018 Report  87

FIRST QUARTER REPORT, 2018
P66 Elevator #2 Control System
Project: C80081O 8 105261             Upgrades to the elevator controls     Project Status:
Budget: $728,000                     systems.                            Schedule:          Within or Ahead 
Phase:  Construction                                                  Budget: On or Under
Start:  5/24/2016                                                             Status Reset: N/A
Schedule Completion: 1/2/2018                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Majority of the modernization work is complete.                                         9:;<
0.80
9:=<
0.70
Schedule                                                                            0.55
0.60
0.50
All work is complete except for the installation of some electrical gear to
0.40
address a fault current issue. This work will be completed by the maintenance      9:<9
shop.                                                                         0.20
0.10   Dollars in Millions
0.00
Budget                                                          Authorized Forecasted  Costs
Incurred
Under budget.
Change Order                                               Construction Contract Costs
Current Quarter       Project Total             0.40   9:<>            9:;                                 (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Failure of some of the new equipment required a product change that will delay
3.1
the final implementation until Q2 2018. There will be no significant budget                2.98      2.98
3
impact from this development.                                                  Dollars in Millions 2.9
2.8
Schedule                                                                            2.70
2.7
Prior Report: System deployment was delayed due to an unexpected firewall
2.6
procurement requirement and opportunity. By completing a competitive            2.5
procurement during this project we are able to set a standard that will reduce            Authorized Forecasted   Costs
Incurred
maintenance costs and maximize training benefits.
Budget                                                      Construction Costs
On budget                                                              Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount            From              To
$0


CORPORATE

102  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Checkpoint Wait Time
Project: CC@@AB@                     Procure and implement an           Project Status:
Budget: $1,215,000                    automated system to track            Schedule:           Delayed 
Phase: Implementation               movement and estimate wait times    Budget: On or Under
Start: 7/12/2016                        for checkpoints 2 through 5.           Status Reset: N/A
Schedule Completion: 11/30/G@HC                    (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Checkpoint 2 construction was completed in Q4 2017. Construction began for
Checkpoint 4 and 5 in Q1 2018 and will be operational in May 2018.               1.4    1.22      1.22
Checkpoint 3 is estimated for Q3.                                                  1.2
Dollars in Millions  1
Schedule                                                         0.8
0.6                            0.38
Schedule is delayed by three months due to competing priorities for                 0.4
construction resources.                                                              0.2
0
Budget                                                          Authorized Forecasted  Costs
Incurred
On budget
Construction Costs
Change Order
0.7     0.63        0.63
Current Quarter       Project Total
0.6
Number of COs                 0                   0                Dollars in Millions 0.5
Amount of Cos                 $0                   $0                 0.4
Quarter                                                             Justification for COs: N/A                                              0.3                  0.18
0.2
0.1
Risks
0
Required construction costs are significantly higher than originally estimated prior to            Authorized Forecasted    Costs
Incurred
procurement of the selected system. This may require additional funding to complete
all planned checkpoints. In addition, coordination with other projects at Checkpoint 3
may delay schedule.
Budget Transfers
Amount            From              To
$0


CORPORATE

Port of Seattle 1Q 2018 Report  103

FIRST QUARTER REPORT, 2018
SeaTac Smartphone App
Project: C800800                     Development of a Mobile app with   Project Status:
Budget: $500,000                     SeaTac Maps, Retail, Dining, and     Schedule:          Delayed 
Phase: Implementation               Service Options, and other           Budget: On or Under
Start: 2/23/2016                        important customer service            Status Reset: N/A
Schedule Completion: 10/31/2018     features.                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Features for a first deployment of an iOS mobile app have been completed but
0.6     0.50        0.50
improvements on indoor turn-by-turn way-finding are in progress. Android
0.5
development is in progress.                                                                                  0.35
0.4
Schedule
0.3
0.2
Prior Report: The team has re-evaluated solution and the Port development         Dollars in Millions 0.1
team will partner with a design firm to deliver mobile application. . The first          0
phase deployment was delayed by four months and completed in Q4 2017.             Authorized Forecasted   Costs
Incurred
Budget
Construction Costs
On budget                                                              Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount           From             To
$0



CORPORATE

104  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
South Loop Airport Train Wait Time Display
Project: C800835                     Expand the North Loop Subway      Project Status:
with                                         Budget: IKLMNMMM                     Wait Time Display to the South       Schedule: Delayed 
Phase: Closeout                       Loop and Shuttle Stations            Budget: On or Under
Start: 6/19/2016                                                              Status Reset: N/A
Schedule Completion: 3/1/201L                                  (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
System fully deployed in Q1 2018
0.7      0.58        0.58
0.6
Schedule                                                                             0.46
0.5
Competing projects affecting construction resources continue to delay completion.          0.4
0.3
Budget                                                       Dollars in Millions 0.2
0.1
On budget
0
Authorized  Forecasted    Costs
Incurred                                                                                                                                           Change Order
Incurred
Current Quarter       Project Total
Construction Costs
Number of COs                 0                   0
Amount of Cos                 $0                   $0
0.32      0.31        0.31
Justification for COs: N/A
0.3
Risks                                                              0.28
0.26
Quarter
0.26
Resource availability from competing project may continue to delay construction
completion.                                                                          Dollars in Millions 0.24
0.22
Budget Transfers                                                       Authorized Forecasted   Costs
Incurred
Amount           From             To
$0




CORPORATE

Port of Seattle 1Q 2018 Report  105

FIRST QUARTER REPORT, 2018
Supplier Outreach and Procurement System
Project: C800907                     This project will provide an          Project Status:
Budget: OPQQRQQQ     integrated supplier outreach and Schedule:   Within or Ahead 
Phase: Implementation               procurement solution that utilizes     Budget: On or Under
Start: 7/11/2017                        vendor provided systems for           Status Reset: N/A
Schedule Completion: 3/31/2019      outreach with a Port-developed        (Commission Construction Auth.)
solution for procurement
management.
Significant Developments                                           Budget/Costs Incurred
Development is currently in progress.
1
0.80        0.80
0.8
Schedule
0.6
On schedule
0.4
Budget                                                       Dollars in Millions 0.2                0.09
On budget                                                                 0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount           From             To
$0




CORPORATE

106  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Enterprise Network Firewall Upgrade
Project: C800908                     Upgrade of the Enterprise Network   Project Status:
Budget: $1,500,000                    Firewall Software and Equipment.     Schedule:           Within or Ahead 
Phase: Planning                                                          Budget: On or Under
Start: 6/27/2017                                                              Status Reset: N/A
Schedule Completion: 12/31/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Planning and design are in progress.                                                 2
1.50     1.50
Schedule
1.5
On Schedule                                                             Dollars in Millions 1
0.58
0.5
Budget
0
On budget                                                                  AuthorizedForecasted Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount            From              To
$0





CORPORATE
Port of Seattle 1Q 2018 Report  107

FIRST UUARTER REPORT, 2018
PeopleSoft Financials Upgrade
Project: C800909                     Upgrade of the Port's PeopleSoft     Project Status:
Budget: $3,600,000                    Financials System.                   Schedule:           Within or Ahead 
Phase: Implementation                                                 Budget: On or Under
Start: 12/12/2017                                                            Status Reset: N/A
Schedule Completion: 3/31/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Implementation is in progress for a Q4 Deployment.
4     3.60       3.60
3.5
Schedule                                                         Dollars in Millions  3
2.5
On Schedule                                                               2
1.5
1
Budget
0.5                           0.24
On budget                                                                 0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount            From              To
$0





CORPORATE

108  Port of Seattle 1Q 2018 Report

FIRST QUARTER REPORT, 2018
Rental Car Facility Fleet Tracking System
Project: C800929                     Procure a fleet tracking system and   Project Status:
Budget: $1,055,000                    provide next bus displays for          Schedule:           Within or Ahead 
Phase: Implementation               passengers, voice paging, wireless     Budget: On or Under
Start: 6/27/2017                        access, and music at all pick up        Status Reset: N/A
Schedule Completion: 3/31/2019      locations.                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Implementation is in progress.
1.2     1.06       1.06
1
Schedule
0.8
On Schedule                                                              0.6
0.4
Budget                                                       Dollars in Millions 0.2                0.04
On budget                                                                 0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount           From             To
$0





CORPORATE
Port of Seattle 1Q 2018 Report  109

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.