Presentation

Internal Audit Briefing
Presented to the Port of Seattle
Audit Committee and Tay Yoshitani, CEO
Joyce Kirangi, CPA
Director, Internal Audit
August 02, 2011

Agenda
Audit Report
Comprehensive Operational Audit
Seaport Container Management
Third-Party Arrangements Operational Audit
None
Limited Operational Audit
None
Concession and Lease Audit
CityIce Cold Storage, LLC
2011 Work Plan Status

Comprehensive Operational Audit
Seaport Container Management
Background
The mission of the department is to provide cargo facilities, equipment,
and services to enable customers to move greater amounts of cargo
through the Port of Seattle at Terminal 5, 18, 30, 46, and 115. Container
operations include five terminals located on 500 plus acres. Space is
leased to such private terminal operators as Eagle Marine Services, SSA
Terminals, Total Terminals International and Northland Services.
Summary of Operating Income and Expenses Related to Container Traffic
2008       2009       2010
Operating Revenues       $57,120,183  $61,037,545 $65,697,596
Operating Expenses         $3,880,640   $4,920,589  $2,266,983
Source: PeopleSoft

Comprehensive Operational Audit
Seaport Container Management
Audit Objectives
The objective was to determine if management implemented adequate
controls to assure:
Lease agreements are effectively managed.
Lease and billing information is effectively monitored in PROPworks.
We reviewed information related to the period from January 1, 2010 to
December 31, 2010.

Comprehensive Operational Audit
Seaport Container Management
Audit Result
Clean Audit Report

Concession and Lease Audit
CityIce Cold Storage, LLC
Background
The Port currently has five separate agreements with CityIce Cold Storage, LLC
for various locations at Terminal 91 and south end of Terminal 115. CityIce Cold
Storage, LLC provides secondary packaging, onsite processing, agricultural
storage, and Industrial Importers.
Below are CityIce Cold Storage, LLC financial highlights for the last three years:
Reported      Percentage Rental      Rent
Year   Gross Revenue  (payable if it exceeds the rent      Paid
paid)
2008       $3,802,704           $114,081    $286,936
2009      $4,220,221           $126.606    $298,882
2010               *                 *    $313,824
Total         $8,022,916              $240,687     $585,818
* Effective January 1, 2010, the Percentage Rental fee under lease agreement #131 was no longer applicable.

Concession and Lease Audit
CityIce Cold Storage, LLC
Audit Objectives
The purpose of the audit was to determine whether:
Reported concession was complete and properly calculated.
The Port and the lessee complied with provisions of the Lease and
Concession Agreement.
We examined information related to a two-year period from January 1,
2009, through December 31, 2010.

Concession and Lease Audit
CityIce Cold Storage, LLC
Audit Result
Clean Audit Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.