ii  Port of Seattle 3Q 2010 Report

Port of Seattle
Capital Improvement Project Report
Third Quarter 2010
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the statue of the Port's capital projects.
Background
During 2010 the Port plans to invest over $329,000,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 3Q 2010 Report  1

Aviation
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C000683 et al .......3rd Runway Program .............................................5 ........... 
C100266 et al .......Rental Car Facility ............................................... 6-7.......... ...............
C102030 ...............Stormwater Management Program .......................8 ........... ................................................................................
C102038 ...............Apron Pavement Rehabilitation 3 ........................9 ........... .............................................................................. 
C102163................Main Terminal Baggage Screening ................... 10-11 ........ ...................................
C102334 ...............Water System Isolation Valve Upgrade ................12 ..........
C102573 ...............Aireld Pavement Replacement ...........................13 ..........
C102744................2nd Floor Tenant Improvements ...........................14 .......... ...............
C800019 ...............Loading Bridge Utilities .........................................15 .......... ...............
C800020 ...............Trash Handling & Recycling System ....................16 .......... ................. ............................................
C800034 ...............North Expressway Relocation ..............................17 .......... ...............
C800036 ...............Parking Garage 4th Floor Improvements .............18 ..........
C800042 ...............Aircraft Rescue Fire Fighting Station Upgrade ....19 .......... ...............
C800061 ...............Main Terminal South Sub Low Volt ......................20 .......... ...............
C800071 ...............Consolidated Warehouse .....................................21 .......... ...............
C800095 ...............Alaska Air 2 Step Ticket Counter..........................22 .......... ...............
C800105 ...............Airport Owned Gate Infrastructure .......................23 ..........
C800107 ...............C4 UPS System Improvements ............................24 .......... ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........25 .......... ...............
C800112................Runway 16C/34C Panel/Joint Sealant .................26 .......... ..............................
C800144 ...............Security CCTV System Improvements.................27 .......... ...............
C800146 ...............RMU/Kiosk Concession Program ........................28 .......... .............................. ......................................
C800147 ...............Concessions Unit Readiness Program ................29 .......... ...............
C800148 ...............GML Arrivals Hall Concessions ...........................30 .......... ...............
C800167 ...............Runway 16L/34R Reconstruction.........................31 .......... .................................. .......................................... 
C800170 ...............Connect C1 BHS to C88 BHS ..............................32 .......... ..............................
C800174................FIS - New Primary Inspection Booths ..................33 ..........
C800237 ...............Terminal Escalators Modernization ......................34 .......... ...............
C800238 ...............Central Plant Pre-Conditioned Air ........................35 .......... ...............
C800239 ...............Fire Piping .............................................................36 .......... ..............................  ........................................
C800249 ...............2nd Floor HVAC ....................................................37 ..........
C800253 ...............Parking System Replacement ..............................38 .......... ..............................
C800254 ...............Aircraft RON Parking Post Ofce Site..................39 ..........
C800274 ...............8th Floor Weather Proong ..................................40 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......41 ..........
C800336 ...............South Satelite Delta Sky Club Extension .............42 ..........
C800360 ...............Roof Replacement Program .................................43 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................44 ..........


2  Port of Seattle 3Q 2010 Report

Other Aviation
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C102396 ...............Fire Vehicles .........................................................45 ..........
C200007...............Highline School Noise Insulation ..........................46 .......... ...............
C200015 ...............3rd Runway Residential Acquisition .....................47 ......................... 
C200037 ...............FAR Part 150 Mobile Home Park Acquisition ......48 .......... ...............
C200042 ...............Highline Community College Noise Insulation .....49 .......... ...............
C200048 ...............Home Insulation Retrot .......................................50 .......... ...............
C200093 ...............Single Family Home Sound Insulation .................51 ..........
C800046 ...............Street Vacations  Des Moines Creek 1 ..............52 .......... ...............
C800150 ...............Burien Commercial Property Acquisition .............53 .......... ...............
C800154 ...............Tenant Reimbursement ........................................54 ..........
C800381 ...............28th Ave Property Acquistion ...............................55 .......... ...............
Seaport
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C102451 ................T-115 Dock Reconstruction...................................56 .......... ............... ....................
C800085 ...............T-30/T-91 Program ............................................ 57-58........ ............... ....................
C800114................P-66 Bag. Corridor & Pass. Screening ................59 .......... ...............
C800121 ...............T-18 S. Fendering .................................................60 .......... ...............
C800123 ...............T-5 Crane Spreader Replacement .......................61 .......... ...............
C800182 ...............NH Island Mooring Dolphins (4) ...........................62 ..........
C800264 ...............T-10 Interim Redevelopment.................................63 .......... ...............
C800273 ...............T-91 Mobile Gangways .........................................64 ..........
C800343 ...............T-91 Roadway Pavement .....................................65 .......... .............................. 
C800347 ...............T-46 Upgrade Yard Lighting .................................66 ..........
C800349 ...............T-5 Crane Cable Reels .........................................67 ..........
WP Number   Project Title                 Page
E102007 ................East Marginal Way Grade Separation ..................68 ..........
E103705 et al ........T-46 ZPMC Gearboxes ........................................69 ..........
E103835 et al ........T-5/T-18 Maintenance Dredging ...........................70 .......... ...................................
E104206et al .........Water/Sewer Meter Upgrade ................................71 ..........
E104362 et al ........Street Vacations T-5/18/105 .................................72 ..........


Port of Seattle 3Q 2010 Report  3

Real Estate
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C001706 et al........SBM Renewal and Replacement .........................73 .......... ...............
C800070 ...............T-102 HVAC Renewal/Replacement ....................74 .......... ...............
C800133 .............. T-86 Grain Facility Modernization (Phase I) ........75 ..........
C800136 ...............FT South Wall Reconstruction Phase VI ..............76 ..........
C800175 ...............MIC Central SeaWall Replacement ......................77 ..........
C800183 ...............P91 Fender System Upgrade ...............................78 ..........
C800298 ...............T-91 Watermain Replacement ..............................79 ..........
C800386 ...............FT NW Dock E. Fender System Replacement.....80 ..........
C800416 ...............T-18 Fender Replacement ....................................81 ..........
Corporate
Overall Project  Variance since
Status        last report
CIP Number   Project Title                   Page       Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ....................82 ..........
C800003...............Maximo Enterprise Implementation......................83 .......... ...............
C800227 ...............Ground Transportation Management System ......84 ..........
C800319............... Port of Seattle Internet Redesign.........................85 .......... .............................. 
C800320 ...............External Sharepoint ..............................................86 .......... .............................. ................... 
C800321 ...............Enterprise Project Cost Management ..................87 .......... ...............
C800322 ...............Records and Document Management .................88 .......... .............................. 
C800326 ...............Business Continuity ..............................................89 .......... .............................. 
C800387 ...............Time Clock System ...............................................90 ..........
C800392 ...............PeopleSoft Financial Upgrade ..............................91 ..........
C800397 ...............Port Roster ............................................................92 ..........
Key  Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Previously Reported
No Diamond  On Budget or On Schedule

4  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,           The 3rd Runway Program
On Budget
C001138, C001175,         constructed a new 8,500 foot long
0 Change Orders
C001331, C001751,         dependent runway, connecting
Total Change Orders Amount:
C001760, C100172         taxiways, and related infrastructure.
$0.00
Budget: $930,908,802
Phase: Construction                                   Budget/Costs Incurred
Start: 05/27/1997
1200
Completion: 12/31/2011
1000
Significant Developments                               Millions800
600
Remaining 2009 contract work for pond netting has been completed.
400
The 2010 construction contract work was completed except for the       Dollars in 
200
in-stream work that will be completed in 2011.
0
Authorized   Forecasted  Costs Incurred
Schedule
The remaining tasks on this project include: Des Moines Nursery
Mitigation's plant establishment, 2010 contract in-stream work,         2010 Contract Const. Costs
Alaska Maintenance Building demolition, and Pond M modifications.
1
Budget                                            0.8
To date, $615,394,000 of construction has been completed on the       Millions 0.6
overall program. Savings of nearly $1,000,000 was returned to the         0.4
overall capital program.                                                   Dollars in   0.2
0
Change Order
InitialChange OrdersSpent
None
Risks
Photo
No risks were identified at this time.
Budget Transfers
To Savings                                     $1,556,738


AIRPORT
Port of Seattle 3Q 2010 Report  5

THIRD QUARTER REPORT, 2010
Rental Car Facility
Status Snapshot  Prior Report
Delayed Schedule  4Q 08
Project:    C100266,       The program will construct a           On Budget
C102167, C800032        consolidated rental car facility (RCF)   538 Change Orders
Budget: $419,306,000     for all rental car companies at the      Total Change Orders Amount:
Phase: Construction     airport, a bus maintenance facility     $5,603,903
Start: 02/24/1998           (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.               Budget/Costs Incurred
Significant Developments                                500
400
Construction is progressing well on all aspects of the RCF. Concrete
work for three remaining (of six) sections are complete to the third          Millions300
floor. Work in the Customer Service Building is well underway. The        200
high canopy roof is complete and exterior curtain wall and glazing is       Dollars in 100
nearing completion. All retaining walls are complete. Construction           0
continues on all four quick turnaround areas. Continue averaging               Authorized  Forecasted Costs Incurred
over 310 workers daily, increasing to 320 workers for concrete work.
All suspension claims are complete and significant deductive change
orders executed. Bids for the BMF contract were opened with the       Construction Costs
apparent low bidder 18.8% below estimate. The ORI project is under
contruction with work ongoing on S160th St and work beginning on         250
the new access ramp to the Airport Expressway ramp to SR518.
200
Work is about to begin on the bridge widening and strengthening.
The Port and Gillig are finalizing bus layout, seating and finishes.            150    Millions
100
Schedule                                           Dollars in   50
The revised program schedule remains on-track for spring 2012             0
completion. BMF scheduled completion is March 2012. ORI                    InitialChange OrdersSpent
scheduled completion is December 2011. Bus delivery planned for
4Q 2011.
Photo
Budget
Customer Finance Charge revenues have increased slightly and the
trend is improving slightly with the economy. The program forecast is
within the approved budget and authorization.
Change Order
75 change orders were issued this quarter in the amount of
($4,641,003).

6  Port of Seattle 3Q 2010 Report

Risks
For RCF: claims; multiple subcontractors working in same location; quality issues; control of onsite
stormwater; and site congestion.
For ORI: weather; traffic control; and site congestion.
For BMF: weather; material deliveries; and completion of aggressive construction schedule to support
spring 2012 opening.
Budget Transfers
None this quarter
Cost Growth of Construction
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative change order percentage through
this quarter is 19.4%. Primary reason for changes is the removal of contaminated soils and
associated impacts. This work and the final contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  Cumulative change order percentage
through this quarter is 170.5%. Primary reasons for changes are for additional contractor
management, estimating, scheduling and bidding effort for cost estimate reconciliation,
constructability reviews and value engineering beyond the extent of the original scope to validate
project costs and support the rental car companies and the Port on final approval of the project. This
work and the final contract reconciliation is complete.




AIRPORT

Port of Seattle 3Q 2010 Report  7

THIRD QUARTER REPORT, 2010
Stormwater Management Program
Project:    C102030,      The program achieves permit           Status Snapshot  Prior Report
C800026, C800030       requirements and makes the Airport a   On Schedule
Budget: $52,347,234     leader in stormwater management by    Under Budget     1Q 10
Phase: Construction     construction of flow control, water      0 Change Orders
Start: 06/11/2002          quality treatment and low stream flow    Total Change Orders Amount:
mitigation facilities.                           $0
Completion: 12/31/2011
Significant Developments                              Budget/Costs Incurred
The stormwater program (C102030) is in its adaptive management
100
phase under which additional or upgraded water quality treatment
facilities are being implemented based on the stricter effluent               80
standards of the new stormwater National Pollutant Discharge            Millions 60
Elimination System (NPDES) permit. Water quality treatment
40
upgrades at three project sites are in the 100% design review phase      Dollars in  20
and will be constructed in 2011.
0
Schedule                                              Authorized  Forecasted Costs Incurred
The new stormwater NPDES permit became effective April 1, 2009.
Current adaptive management projects will be designed and
Construction Costs
constructed during the 2010 to 2011 period, and possibly additional
No active construction
projects through 2014 depending on water quality monitoring results.
contract at this time.
The stormwater (C800026) and sanitary sewer (C800030) pipeliner
projects, which are not part of adaptive management, have been
deferred until 2011, or later.
Budget
The project forecast is within the approved budget and authorization.
During the third quarter $6,100,000 of C102030 budget was returned
to savings.
Change Order
None
Risks
Additional adaptive management facilities or upgrades may be
required beyond those currently being planned, depending upon
future water quality monitoring results.
Budget Transfers
To Savings                                  $6,100,000
AIRPORT
8  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Apron Pavement Rehabilitation - 3
Project:    C102038         Multiyear airfield pavement           Status Snapshot
Budget: $14,998,000       replacement program. This is a     Ahead of Schedule
Phase: Close Out          continuation of a program for the     Under Budget
Start: 01/14/2003             removal and replacement of aged     1 Change Orders
Completion: 07/09/2010     airfield apron pavement started in    Total Change Orders Amount:
1994.                              $79,875.00
Budget/Costs Incurred
Significant Developments
The apron pavement rehabilitation portion of the contract was             16.5
finished on July 9, 2010.                                                    16
15.5   Millions
Schedule
15
Contract closeout is in progress.
14.5   Dollars in 
Budget                                            14
The project forecast is within the approved budget and authorization.           Authorized  Forecasted Costs Incurred
The project returned $1,102,000 savings back to the overall program
on September 28, 2010.
2010 Contract 1
Change Order                                     Construction Costs
Change Order #1, which added seven Apron panels to the project,
3.5
was started on August 24, 2010 and has not yet been executed.
3
Risks                                                Millions 2.5
2
No risks have been identified at this time.                                     1.5
Dollars in     1
Budget Transfers                                        0.5
0
From CIP #C102038 (Apron Pavement Rehabilitation - 3)
InitialChange OrdersSpent
$1,102,000
Photo


AIRPORT

Port of Seattle 3Q 2010 Report  9

THIRD QUARTER REPORT, 2010
Main Terminal Baggage Screening
Project:    C102163       This project creates automated         Status Snapshot  Prior Report
Budget: $223,538,762     systems for explosive detection       Delayed Schedule  4Q 08
Phase: Close Out        screening of baggage for the north     Under Budget     4Q 09
Start: 09/24/2002           Main Terminal and South Satellite.      665 Change Orders
Completion: 02/13/2009   The systems will meet all security      Total Change Orders Amount:
requirements while reducing staffing     $51,165,622
and providing capacity for future
growth.                               Budget/Costs Incurred
Significant Developments
235
The C-1 baggage handling/screening system has been placed into       230
revenue service for the Alaska Air Group. The only remaining work is     Millions 225
to relocate some fire sprinklers and to repair/replace fire proofing
220
material displaced from the main structural elements of the bagwell.
Dollars in 215
Schedule                                           210
Authorized   Forecasted  Costs Incurred
The project was delayed approximately two years from the original
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
Construction Costs
changes. Turner Construction demobilized on May 31, 2009. The
GCCM construction contract with Turner Construction has been
200
closed. The remaining fire sprinkler and fire proofing work is
scheduled for completion by year end.                                     150
Millions  100
Budget
50
The project forecast is within the approved budget and authorization.      Dollars in 
0
Change Order                                            Initial Change Orders Spent
665 Change Orders have been issued on this project.
Photo
Risks
Risks include recent TSA changes in certification requirements and
whether they will be imposed retroactively.
Budget Transfers
To C102165 (Aeronautical New Projects)            $7,000,000


10  Port of Seattle 3Q 2010 Report

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated as they were unable to meet the
project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project; which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT

Port of Seattle 3Q 2010 Report  11

THIRD QUARTER REPORT, 2010
Water System Isolation Valve Upgrade
Status Snapshot
Project:    C102334         This project replaces isolation        On Schedule
Budget: $2,147,000        valves on the aging water          On Budget
Phase: Design            distribution system, necessary for    0 Change Orders
Start: October 2010          isolating portions of the system in     Total Change Orders Amount:
Completion: 12/31/2011     the event of breaks, leaks, or tie-     $0
ins.
Budget/Costs Incurred
Significant Developments
2.5
On September 28, 2010, the Commission authorized $1,149,000 of
2
the $2,147,000 project budget for installation of landside valves by
Port Construction Services, for pre-purchase of all valves needed for      Millions 1.5
the project, and for design of the airfield valve installation under a            1
2011 Airfield project. The project will return to the Commission for         Dollars in 0.5
Airfield construction funds in the spring of 2011.
0
Authorized   Forecasted  Costs Incurred
Schedule
The project is currently on schedule.
Construction Costs
Budget                                         Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None at this time
Budget Transfers
From C102166 (Aeronatical Renewal/Replacement)      $147,000


AIRPORT

12  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Airfield Pavement Replacement
Project:    C102573         The project is intended to be a        Status Snapshot
Budget: $30,800,000       multi-year pavement replacement    On Schedule
Phase: Design            program to replace some of the      On Budget
Start: 05/02/2010             worst pavement and joint seal on      0 Change Orders
Completion: 12/31/2016     the airfield.                      Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
The Commission approved $394,000 of design funds on August 10th
35
for the South Satellite Slot Drain/Apron Replacement. The 30%
30
design was issued in September.
Millions 25
20
Schedule
15
The construction work in 2011 is the initial phase of a multi-year           Dollars in  10
pavement replacement program scheduled from 2011 to 2015.            5
0
Budget                                              Authorized Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
Construction Costs
be requested when the design and bid documents are completed.
Not Applicable
Change Order
Photo
None
Risks
None identified at this time.
Budget Transfers
None



AIRPORT

Port of Seattle 3Q 2010 Report  13

THIRD QUARTER REPORT, 2010
2nd Floor Tenant Improvements
Project:    C102744         This project constructs a shell        Status Snapshot  Prior Report
Budget: $377,864          space for new tenant offices and     Delayed Schedule  1Q 10
Phase: Construction       provides utility pathways to the      On Budget
Start: 08/22/2006             shell space and makes code          0 Change Orders
Completion: (See          improvements to adjacent lobby     Total Change Orders Amount:
and corridors.                          $0
C800249)
Significant Developments                              Budget/Costs Incurred
Project construction activities are substantially complete except for
0.6
one project element, which is awaiting completion of tenant office
0.5
build out and relocation of current tenant offices. The remaining
0.4
portion of the work will be completed once the tenant has moved out
0.3
of the former space. The tenant project to build out the office space       in Millions
0.2
is complete.                                                              Dollars 0.1
Schedule                                            0
Authorized   Forecasted  Costs Incurred
The remaining work is now scheduled for late 2010.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.   Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

14  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Loading Bridge Utilities
Project:    C800019    This project will upgrade all Port-          Status Snapshot  Prior Report
Budget: $9,385,000    owned loading bridges to the same       Delayed Schedule       2Q 09
Phase: Design        standards, including 400Hz power and     On Budget
potable water. It will reduce air
Start: 06/28/2007                                                  0 Change Orders
emissions, improve energy efficiency
Completion: TBD                                        Total Change Orders Amount:
and save money for the airlines.             $0
Budget/Costs Incurred
Significant Developments
The project site walk for condition changes and related projects was       10
completed with Operations, Engineering and Port Fire Department.         8
Requests for competition waivers for equipment to be pre-purchased     Millions  6
have been submitted.
4
Schedule                                           Dollars in  2
The current schedule has the 90% design drawings and                   0
specifications being submitted for review in mid-January 2011.                 Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.   Construction Costs
Not Applicable
Change Order
None
Risks
The project budget could increase due to the design being placed on
hold and restarting at 90%, and potential increases in the
construction market.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 3Q 2010 Report  15

THIRD QUARTER REPORT, 2010
Trash Handling & Recycling System
Project:    C800020      To improve trash handling and           Status Snapshot  Prior Report
Budget: $1,612,000     recycling operations and to meet        On Schedule
Phase: Close Out       future trash volume demands;          Under Budget          2Q 10
Start: 04/22/2008         decentralize tenant trash disposal and     9 Change Orders
Completion: 02/28/2010  recycling; and centralize airline trash     Total Change Orders Amount:
disposal and recycling.                    $28,468
Significant Developments                              Budget/Costs Incurred
Project is now complete except for contract close out and the CPO
1.7
contract administrator is working to finalize the remaining work. All
1.6
major airlines are utilizing the six new sites and utilization of these
compactors is improving. This will be the last quarterly report for this       1.5
project.
Millions
1.4
Dollars in 
Schedule                                           1.3
Project close out is under way.                                            1.2
Authorized    Forecasted  Costs Incurred
Budget
The project is under the approved budget and authorization. The       Construction Costs
project is anticipating a savings of approximately $250,000 after
closeout is complete.                                                      0.35
0.3
Change Order                                      Millions 0.25
0.2
None
0.15
Risks                                                Dollars in  0.1
0.05
None identified at this time.
0
Initial   Change Orders   Spent
Budget Transfers
None this quarter
Photo
Cost of Construction Growth
Three electrical changes during construction affected the project's
costs. At Concourse D, 1) the home run conduit proposed for re-use
did not exist in the field, so the project installed new conduit; 2) the
Ethernet converters specified for the fiber conversion were changed
to analog to accommodate the Port's existing communication
system; and 3) fusible disconnect switches were added at all twelve
trash compactors for safety and maintenance reasons.
AIRPORT
16  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
North Expressway Relocation
Project:    C800034
The project is a collaboration         Status Snapshot  Prior Report
Budget: $110,347,700      between the Port and Sound        Delayed Schedule  1Q 10
Phase: Construction       Transit. It reconstructs the North     On Budget
Start: 07/27/2004             Airport Expressway and brings light   193 Change Orders
Completion: 03/31/2012     rail to the Airport.                 Total Change Orders Amount:
$9,350,934
Significant Developments
Budget/Costs Incurred
The work in the main contract includes reconstruction of the North
Airport Expressway and light rail transit components. This work is         115
complete. The intelligent transportation management system has         110
been implemented. A final contract to complete paving, landscaping,      Millions105
the north entry art features, and other miscellaneous work has been       100
awarded and is underway.
95
Dollars in  90
Schedule
85
The main contract reached substantial completion in August 2008;             Authorized  Forecasted Costs Incurred
and only completion of plant establishment remains. A contract for
final paving, landscaping, and reclamation is underway and is
planned to be complete in early 2011, followed by a first year plant      Construction Costs
establishment period to be complete in early 2012.
120
Budget                                             100
80
The project forecast is within the approved budget and authorization.      Millions
60
Change Order                                         40
Dollars in     20
Six change orders were issued this quarter in the amount of $50,000.
0
Initial   Change Orders   Spent
Risks
None identified at this time.
Photo
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2010 Report  17

THIRD QUARTER REPORT, 2010
Parking Garage 4th Floor Improvements
Project:    C800036
The project includes the design and   Status Snapshot
Budget: $9,131,000        construction of a pedestrian bridge   On Schedule
Phase: Construction       and a walkway from Sound         On Budget
Start: 02/14/2006             Transit's Airport Station to the         56 Change Orders
Completion: 12/31/2009     Terminal.                       Total Change Orders Amount:
$177,015
Significant Developments
Budget/Costs Incurred
The project was delivered in two contracts: the pedestrian bridge
between the Airport Station and the Parking Garage, and a walkway       9.2
on the 4th floor of the garage between the pedestrian bridge and           9
northernmost sky bridge to the main terminal. Both contracts are          Millions 8.8
substantially complete and opened in conjunction with Sound             8.6
8.4
Transit's Airport Station on December 19, 2009.
Dollars in 8.2
8
Schedule
7.8
Punch list work is complete for the walkway and the pedestrian                Authorized  Forecasted Costs Incurred
bridge. Multiple User Flight Information Display Systemwill be
installed in 4th Quarter 2010.
Construction Costs
Budget
4
The project forecast is within the approved budget and authorization.
3
Change Order                                       Millions  2
Five change orders were issued for the walkway this quarter in the
amount of $81,627.                                                      1
Dollars in 
0
Risks                                                     Initial Change Orders Spent
None
Budget Transfers                                     Photo
None this quarter


AIRPORT
18  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Aircraft Rescue & Fire Fighting Station Upgrade
Project:    C800042         Upgrade the Sea-Tac International    Status Snapshot  Prior Report
Budget: $4,972,000        Airport Aircraft Rescue & Fire       Delayed Schedule  1Q 09
Phase: Close Out          Fighting (ARFF) station to meet      On Budget
Start: 06/13/2006             current Airport needs and comply     26 Change Orders
Completion: 01/31/2010     with current safety codes.          Total Change Orders Amount:
$173,099
Significant Developments                              Budget/Costs Incurred
Contractor has returned and completed waterproofing of training
5.2
tower. Remaining work on this project includes installing additional
pick points on the training tower and altering the grade of the asphalt        5
around it.                                                                     Millions 4.8
4.6
Schedule
Dollars in 4.4
The project and punchlist are now substantially complete.                 4.2
4
Budget
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
None this quarter
3
Risks
2
None at this time                                                          Millions
1
Budget Transfers                                       Dollars in 
None this quarter                                                           0
Initial  Change Orders  Spent



AIRPORT

Port of Seattle 3Q 2010 Report  19

THIRD QUARTER REPORT, 2010
Main Terminal South Sub Low Voltage
Project:    C800061     This project covers the renewal and       Status Snapshot  Prior Report
Budget: $1,925,000     replacement of low voltage (600 volts     Delayed Schedule  1Q 08
Phase: Design         and below) electrical distribution         On Budget
0 Change Orders
Start: 06/28/2007         equipment in the southern part of the
Total Change Orders Amount:
Completion: TBD       Main Terminal.
$0
Significant Developments
Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
and building codes, the design phase changed from 100% to 90%        2.5
complete. The Port is in the process of finalizing and executing a
2
Service Agreement (SA) to finish the design. The SA should be
completed in 4th quarter 2010.                                           Millions 1.5
1
Schedule                                           Dollars in 0.5
The project was reactivated on June 24, 2009 and is in the process         0
of determining the scope of work, schedule and final design budget.
Authorized   Forecasted  Costs Incurred
Expect to remobilize the Design Consultant in 4th quarter 2010.
Budget                                         Construction Costs
The project forecast is within the approved budget and authorization.   Not Applicable
Change Order                                     Photo
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area of the Main Terminal is a 24/7/365 operation and
sequencing of this work is critical and electrical power has to be
maintained without interruptions.
It is not known when the construction will proceed. There may be an
impact on project costs due to changes in market conditions at that
time.
Budget Transfers
None this quarter
AIRPORT
20  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Consolidated Warehouse
Project:    C800071       This project will construct a 50,000      Status Snapshot  Prior Report
Budget: $9,300,000       square foot warehouse for storage     Ahead of Schedule      3Q 09
Phase: Close Out        and inventory management of spare    On Budget
Start: 06/27/2006           parts for the Aviation Maintenance      34 Change Orders
Department.
Completion: 02/15/2010                                   Total Change Orders Amount:
$770,658
Significant Developments                              Budget/Costs Incurred
The project is complete and in close out, with the building open for
use and in operation. The architect will submit the final as-built             9.4
drawings November 2010.                                          9.3
Millions 9.2
Schedule                                           9.1
9
The project was completed ahead of schedule.
Dollars in 8.9
8.8
Budget                                           8.7
The project forecast is within the approved budget and authorization.           Authorized  Forecasted Costs Incurred
Change Order
Construction Costs
None this quarter
6
Risks
None                                                   Millions  4
Budget Transfers                                         2
None this quarter                                                        Dollars in 
0
Initial  Change Orders  Spent
Cost of Construction Growth
Project anticipated CO's exceeding 10% due to the following:
1. Soil and foundation changes due to the site being an old,            Photo
unconsolidated fill of unknown material;
2. Perceived market conditions during bidding, structural mezzanine
was deleted. The bid climate changes allowed the mezzanine to
be installed; and
3. Pallet racks were anticipated to be a Port purchase and install.
The purchasing officer recommended the contractor purchase and
install as a CO.

AIRPORT
Port of Seattle 3Q 2010 Report  21

THIRD QUARTER REPORT, 2010
Alaska Air 2-Step Ticket Counter
Project:    C800095         This project provides Port of          Status Snapshot  Prior Report
Budget: $10,707,000       Seattle support for Alaska Airlines'    Delayed Schedule  1Q 08
Phase: Close Out          2-step ticket counter projects (the    On Budget
Start: 04/11/2006             "Airport of the Future"). The work     0 Change Orders
Completion: 02/13/2009     includes: asbestos abatement;       Total Change Orders Amount:
concessions relocations; and          $0
related building modifications.
Budget/Costs Incurred
Significant Developments
12
The onsite work is complete. The Port has reached a tentative
10
agreement with Alaska Airlines to reconcile the reimbursable
amount.                                                         Millions 8
Dollars in 
6
Schedule                                            4
2
The project work is complete.
0
Authorized   Forecasted  Costs Incurred
Budget
The project could incur additional costs over the current budget for
Port performed tasks which will be reimbursed by Alaska Airlines.       Construction Costs
After reimbursement, the anticipated forecast is within the approved    Not Applicable
budget and authorization.
Change Order
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
22  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Airport Owned Gate Infrastructure
Project:    C800105         This project purchases and
Status Snapshot
Budget: $6,000,000        replaces loading bridges at gates
On Schedule
Phase: Construction       throughout the airport.
On Budget
Start: 07/24/2007                                                  0 Change Orders
Completion: 12/31/2011                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The project was presented to the Commission in July for
authorization of the remainder of the budget. Currently, the team is in
7
the process of procuring a design firm.                                      6
5
Schedule                                           Millions 4
Dollars in 
3
The remainder of the project will be completed in 2011.
2
1
Budget
0
The project forecast is within the approved budget and authorization.           Authorized  Forecasted Costs Incurred
Change Order
None                                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2010 Report  23

THIRD QUARTER REPORT, 2010
C4 UPS System Improvements
Project:    C800107     Project will replace existing UPS          Status Snapshot  Prior Report
Budget: $2,336,000     System, including batteries, with a new   Delayed Schedule  1Q 09
Phase: Construction    new system located in the Airport        On Budget
Start: 06/28/2007         Combined Communications and           0 Change Orders
Completion: TBD       Command Center (C4).               Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
2.5
and building codes, the design phase changed from 100% to 90%
complete. The Port is in the process of finalizing and executing a            2
Service Agreement to finish the design. The Service Agreement          Millions 1.5
should be completed in the fourth quarter of 2010.
1
Dollars in 0.5
Schedule
0
The project was reactivated on June 24, 2009 and is in the process
Authorized   Forecasted  Costs Incurred
of determining the scope of work, schedule and final design budget.
Expect to remobilize the Design Consultant in the fourth quarter of
2010.
Budget                                         Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Photo
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions.
It is not known when the construction will proceed as this is
specialized equipment and complex and requires rigorous testing
during the commissioning phase.
Budget Transfers
None this quarter
AIRPORT
24  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Garage Escalator & A-Bank Elevator Upgrade
Project:    C800109       This project renews and replaces        Status Snapshot
Budget: $7,315,000      aging elevators and escalators in the    Delayed Schedule
Phase: Construction     Parking Garage to provide reliable      On Budget
Start: 09/11/2007          vertical transportation to customers for   23 Change Orders
Completion: 10/31/2011  years to come.                     Total Change Orders Amount:
$219,523
Significant Developments                              Budget/Costs Incurred
All contractor work on the seven A-Bank Elevators was completed.
8
Port Construction Services will install rain protection covers over
7
exterior vents. Contractor pre-award submittals for the Garage
Escalator work were completed and the contract is expected to be        Millions  6
5
executed during the fourth quarter.                                          4
3
Schedule                                           Dollars in  2
1
Contractor work on the Garage Escalators will start during the fourth
0
quarter and will require approximately ten months.
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.   Construction Costs
Change Order                                         2.5
Six change orders were issued for the A-Bank Elevator work this             2
quarter.                                                                    Millions   1.5
Risks                                                   1
None identified at this time.                                                  Dollars in    0.5
0
Budget Transfers                                            Initial  Change Orders  Spent
None this quarter



AIRPORT

Port of Seattle 3Q 2010 Report  25

THIRD QUARTER REPORT, 2010
Runway 16C/34C Panel/Joint Sealant
Replacement
The scope of work will remove and    Status Snapshot
Project:    C800112         replace the pavement and joint seal   Ahead of Schedule
in areas on Runway 16C-34C.        On Budget
Budget: $5,650,000
1 Change Orders
Phase: Close Out                                       Total Change Orders Amount:
Start: 02/26/2008                                                  $121,175.20
Completion: 09/03/2010
Budget/Costs Incurred
Significant Developments
The 2010 construction project was completed on September 3, 2010.      6
5
Schedule                                           Millions 4
The contract is in the closeout process.                                      3
2
Budget                                           Dollars in  1
0
The project forecast is within the approved budget and authorization.
Authorized   Forecasted  Costs Incurred
Change Order
Change Order #1, which added 13 Runway panels to the project,      2010 Contract 1
was started on August 24, 2010 and has not been executed as of      Construction Costs
September 30, 2010.
3.5
Risks                                                  3
No risks have been identified at this time.                                   Millions  2.5
2
Budget Transfers                                        1.5
1
None                                                   Dollars in  0.5
0
InitialChange OrdersSpent

Photo


AIRPORT
26  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Security CCTV System Improvements
Project:    C800144         This project will install               Status Snapshot  Prior Report
Budget: $2,037,591        approximately 70 new cameras for   Delayed Schedule  3Q 09
Phase: Implementation     TSA and integrate existing Airport    On Budget
Start: 9/11/2007              camera networks which contain       0 Change Orders
Completion: 03/31/2010     over 800 cameras.                Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
The final cut overs are complete. The Port and TSA are evaluating
2.05
follow on work. A request for additional funding has been transmitted
to the TSA.                                                               2
1.95   Millions
Schedule
1.9
Project completion occurred in March 2010.
1.85   Dollars in 
1.8
Budget
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Not Applicable                                                       Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 3Q 2010 Report  27

THIRD QUARTER REPORT, 2010
RMU/Kiosk Concession Program
Project:    C800146     The project will provide design and       Status Snapshot  Prior Report
Budget: $1,209,000     fabrication of eight Retail              Delayed Schedule
Phase: Construction    Merchandising Units (RMUs); provide    Under Budget          2Q 10
Start: 11/20/2007         power, communications, and data to      0 Change Orders
Completion: 06/30/2011 sixteen RMU locations; and install floor-   Total Change Orders Amount:
mounted receptacles for the utilities to     $0
allow easy connection points as well as
flexibility for future utilization.                Budget/Costs Incurred
1.4
Significant Developments
1.2
All RMU utility installations are complete. The remaining tasks              1
include purchasing and installing the RMU kiosk units.                    Millions 0.8
0.6
Schedule                                           Dollars in 0.4
0.2
The project is on hold until the prioritization decisions are made by
0
the Port's Business Development group, related to the procurement
Authorized   Forecasted  Costs Incurred
of the RMUs.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.   Not Applicable
The project anticipates a savings of approximately $700,000 once
closeout is complete.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

28  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Concessions Unit Readiness Project
Project:    C800147         This project will upgrade             Status Snapshot  Prior Report
Budget: $2,087,000        concession locations which were     Delayed Schedule       2Q 09
Phase: Design            previously vacated or slated to be    On Budget
Start: 08/26/2008             vacated to Port standards for use     0 Change Orders
Completion: 06/30/2013     as specialty concession space.      Total Change Orders Amount:
$0
Significant Developments
This project received Commission authorization in September 2010    Budget/Costs Incurred
to design and build concession spaces in two locations.
2.5
Schedule                                            2
The construction phase has been restructured and re-sequenced,         1.5
with the intent to maximize the timing for new Concessions                Millions
1
opportunities. The project was put on hold until the prioritization
Dollars in
decisions were made by the Port's Business Development group.         0.5
0
Budget                                              Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.      Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 3Q 2010 Report  29

THIRD QUARTER REPORT, 2010
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail    Status Snapshot   Prior Report
Project:    C800148         merchandising corridor in the Gina    Delayed Schedule  4Q 09
Marie Lindsey Arrivals Hall. The       On Budget
Budget: $1,033,000
project includes installing three         0 Change Orders
Phase: Design            Retail Merchandizing Units (RMUs)   Total Change Orders Amount:
Start: 11/20/2007             and providing utilities to a new        $0
Completion: 12/31/2011     approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The 100% design is complete.                                          1
0.8
Schedule
Millions 0.6
The project completion is dependent upon issuance of a Request for      0.4
Proposal by the Aviation Business Development Group for a new         Dollars in 0.2
concession in the Arrivals Hall.                                               0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                                     Not applicable
None
Photo
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter



AIRPORT
30  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Runway 16L/34R Reconstruction
Status Snapshot
On Schedule
Project: C800167           The scope of this project includes
Budget: $66,886,538       the complete reconstruction of      Under Budget
Runway 16L/34R (the eastern       26 Change Orders
Phase: Close Out
runway) and replacement of aging   Total Change Orders Amount:
Start: 02/26/2008
infrastructure.                          $2,528,214.29
Completion: 12/31/2009
Significant Developments                             Budget/Costs Incurred
Runway 16L/34R Reconstruction project includes reconstruction of      100
11,900 foot runway and portions of five taxiways. The construction        80
was completed on September 25, 2009 and re-opened on              Millions 60
September 26, 2009 on schedule. Seeding of the slopes is               40
completed.                                                        Dollars in  20
0
Schedule                                             Authorized Forecasted Costs Incurred
The runway was re-opened on schedule on September 26, 2009
and contract closeout will continue through 2010.
Construction Costs
Budget
60
The project forecast is within the approved budget and authorization.
50
The project is anticipating an additional savings of approximately
Millions   40
$6,000,000.                                                           30
20
Change Order                                      Dollars in  10
0
No change orders have been executed during this period.
Initial  Change Orders  Spent
Risks
No risk have been identified at this time.
Photo
Budget Transfers
From CIP #C800167 (Runway 16L/34R Reconstruction) $6,603,000


AIRPORT

Port of Seattle 3Q 2010 Report  31

THIRD QUARTER REPORT, 2010
Connect C1 BHS to C88 BHS
Project:    C800170         This project connects the C1         Status Snapshot
Budget: $3,032,000        baggage handling system (BHS) to   Delayed Schedule
Phase: Construction       the C88 BHS. It installs two High-    On Budget
Start: 8/30/2009              Speed Diverters plus additional       0 Change Orders
Completion: 1/31/2011      baggage conveyor length that will    Total Change Orders Amount:
connect the two C1 sortation loops    $0
to the C88 BHS.
Budget/Costs Incurred
Significant Developments
3.5
The Port executed the construction contract on July 12, 2010. The
3
contractor duration is 180 days. The contractor has mobilized and is
Millions 2.5                                                                                                      on site.                                                                                           2
1.5
Schedule                                           Dollars in  1
Currently the project is scheduled to be completed in January 2011.       0.5
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable                                                            1.4
1.2
Risks                                                Millions  1
0.8
Dollars in 
None identified at this time.
0.6
0.4
Budget Transfers                                        0.2
None this quarter                                                           0
InitialChange OrdersSpent



AIRPORT
32  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
FIS - New Primary Inspection Booths
Project:    C800174         This project will replace existing      Status Snapshot
Budget: $2,000,000        primary inspection booths for        On Schedule
Phase: Design            Customs and Border Protection in    On Budget
Start: 7/27/2010              the International Arrivals Federal      0 Change Orders
Completion: 6/1/2011       Inspection Services (FIS) facility in   Total Change Orders Amount:
the South Satellite.                     $0
Budget/Costs Incurred
Significant Developments
2.5
Designer procurement underway. Booth procurement bid process
2
underway. Expect to advertise for bids October 2010.                     Millions 1.5  Dollars in 
Schedule                                            1
Project on schedule                                                     0.5
0
Budget
Authorized   Forecasted  Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
None                                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 3Q 2010 Report  33

THIRD QUARTER REPORT, 2010
Terminal Escalator Modernization
Project:    C800237         This project will replace 42           Status Snapshot  Prior Report
Budget: $55,000,000       escalators in the Main Terminal,     Ahead of Schedule 3Q 09
Phase: Design            Concourse B, and South Satellite.    On Budget
Start: 11/02/2007             In addition, two new escalators will    0 Change Orders
Completion: 12/31/2013     be installed at the South Satellite.    Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
This project was formerly entitled "Renew/Replace 42 Escalators &
60
two New Escalators". Proposals were received from four firms on
50
September 9, 2010. The proposals have been evaluated. Interviews
40
with the four firms will be conducted in October. Discussions with the      Millions
30
firms and evaluation of Best and Final Offers are scheduled to be
concluded by late December 2010. Selection recommendation and        20
Dollars in 
Commission authorization are scheduled for early 2011. The project       10
is utilizing the design-build contracting method to accelerate the             0
overall project schedule.                                                         Authorized  Forecasted Costs Incurred
Schedule
The schedule reflects an expedited design-build procurement as well   Construction Costs
as an accelerated construction duration with a tentative completion     Not Applicable
date in 2013.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested following the review of the proposal documents and
selection of a firm.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT
34  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Central Plant Pre-Conditioned Air
Project:    C800238       This project will provide a centralized    Status Snapshot  Prior Report
Budget: $40,600,000      pre-conditioned air plant, associated    Delayed Schedule  3Q 09
Phase: Design           heating and cooling piping systems,    On Budget
Start: 06/15/2009           and jet bridge terminal air handling      0 Change Orders
Completion: 12/10/2012   units to serve airplanes with heating    Total Change Orders Amount:
and cooling while at the gates.           $0
Significant Developments
The contract was awarded to Lydig Construction Inc. on September    Budget/Costs Incurred
13, 2010, after obtaining an $18,000,000 Voluntary Airport Low
Emissions (VALE) grant from the FAA. The contractor has mobilized       50
and is in the process of submitting required submittals before the           40
notice-to-proceed is issued.                                               Millions 30
20
Schedule
Dollars in  10
The design process took longer than anticipated and the project is
approximately two months behind the original schedule.                    0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
1.2
None                                                      1
0.8
Risks
0.6
Millions
The design schedule had to be accelerated in order to meet VALE          0.4
grant submission dates, which could impact the number of change        Dollars in   0.2
orders. The design consultant is having trouble meeting the contract
0
submittal review schedule and is at risk if their delays cause the Port
InitialChange OrdersSpent
of Seattle any claims. Additionally, the Regulated Materials
Management costs are higher than originally estimated.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 3Q 2010 Report  35

THIRD QUARTER REPORT, 2010
Fire Piping Upgrades - Main Terminal
Project:    C800239         This project will upgrade the Main     Status Snapshot  Prior Report
Budget: $1,450,000        Terminal fire piping to restore       Ahead of Schedule      4Q 09
Phase: Close Out          system reliability and provide full     Under Budget     4Q 09
Start: 09/23/2008             monitoring capability with the fire      1 Change Orders
Completion: 03/24/2010     alarm system.                   Total Change Orders Amount:
($10,000)
Significant Developments                              Budget/Costs Incurred
Project is complete and in close out. Substantial completion was
issued on March 24, 2010. This will be the last quarterly report for           2
this project.
1.5
Millions
Schedule                                            1
The construction was completed ahead of schedule. The fire piping       Dollars in 0.5
contractor identified efficiencies and performed the work accordingly.
0
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
None                                                     0.3
0.2
Risks                                                Millions 0.1
Dollars in 
None identified at this time.
0
Budget Transfers                                            Initial Change Orders Spent
0.1
None this quarter



AIRPORT

36  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
2nd Floor HVAC Upgrades
Project:    C800249         Construct a new Heating             Status Snapshot
Budget: $1,700,000        Ventilating and Air-Conditioning      On Schedule
Phase: Close Out          (HVAC) air supply duct system to    On Budget
Start: 03/25/2008             the north side of the second floor of   15 Change Orders
Completion: 04/09/2010     the central main terminal           Total Change Orders Amount:
administration building and the         $114,331
concessions located directly below
on the ticketing level.                  Budget/Costs Incurred
Significant Developments                               1.72
1.7
Construction was completed on April 9, 2010. This will be the last
1.68
quarterly report for this project.                                                Millions
1.66
Schedule                                          1.64
1.62   Dollars in 
The project is in close-out phase.
1.6
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
None this quarter                                                           1
0.8
Risks                                                Millions 0.6
None identified at this time.                                                    0.4
Dollars in   0.2
Budget Transfers
0
None this quarter                                                               Initial  Change Orders  Spent
Cost of Construction Growth
The project scope required the installation of supply and return air
ducts for the 2nd floor offices in the Old Administration Building at
STIA. Change orders were required to correct varying design and
site conditions discovered during the contract submittal, demolition
and installation processes. Change orders were negotiated and
issued covering time and scope to redesign the supports for the
ductwork, address the changed site conditions for the return air duct
and add temporary HVAC to the Host offices.
AIRPORT

Port of Seattle 3Q 2010 Report  37

THIRD QUARTER REPORT, 2010
Parking System Replacement
Project:    C800253         This project replaces the current      Status Snapshot
Budget: $9,777,000        Parking Revenue Control System,    Delayed Schedule
Phase: Design            which manages parking access      On Budget
Start: April 6, 2010           and revenue collection in the          0 Change Orders
Completion: 2/15/2012      Airport's Main Parking Garage.      Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Consultant contract has been executed and design is underway.
The schedule is being revised to complete design and bid in first           12
quarter of 2011 and construct the system during 2011 and early           10
2012.                                                             Millions 8
6
Schedule
4
The project is approximately one month behind schedule due to          Dollars in   2
protracted consultant scope and fee negotiations. The project team
0
is working on a recovery schedule to reduce this delay.
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of     Construction Costs
construction funding and authority to advertise for construction will      None this quarter
be requested when the design and bid documents are completed.
Photo
Change Order
No change orders were issued this quarter.
Risks
This project schedule is aggressive.
Budget Transfers
None this quarter


AIRPORT

38  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Aircraft RON Parking USPS Site
Status Snapshot
On Schedule
Project: C800254           This project will prepare the site for
On Budget
Budget: $43,900,000       the construction of Hardstands for
0 Change Orders
Phase: Design            use as Remain Overnight (RON)
Total Change Orders Amount:
Start: 04/05/2009             parking of aircraft at the Air Mail
$0
Center site.
Completion: 06/30/2013
Significant Developments                             Budget/Costs Incurred
Completed the lease buyout negotiation with the United States            50
Postal Service (USPS) and lease termination in February 2010. A
40
temporary lease with Customs and Border Protection extended the
lease to August 2010. Design efforts for the demolition of the Air          Millions 30
Mail Center including the design for minimal site improvements            20
allowing for temporary uses and amenities, and 15% hardstand          Dollars in  10
design started in Summer 2010.
0
Authorized   Forecasted  Costs Incurred
Schedule
Abatement and demolition of the USPS Building is scheduled to
start second quarter of 2011. Proposed construction of a permanent   Construction Costs
hardstand is scheduled to begin the second quarter of 2012.           Not Applicable
Budget                                         Photo
The project forecast is within the approved budget. Authorization of
construction funding and authority to award for construction will be
requested following the review of the proposal documents.
Change Order
None
Risks
Extent of asbestos in the USPS Building may affect the project cost.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 3Q 2010 Report  39

THIRD QUARTER REPORT, 2010
8th Floor Weatherproofing
Status Snapshot
Project:    C800274         This project includes removal and     On Schedule
Budget: $13,000,000       replacement of the floor covering     On Budget
Phase: Design            system on the 8th floor of the STIA   0 Change Orders
Start: 03/23/2010             parking garage and repair or          Total Change Orders Amount:
Completion: 03/31/2013     replacement of expansion joints      $0
and flashings.
Budget/Costs Incurred
Significant Developments                                14
12
Consultant contract negotiations are complete and contract
Millions 10
execution is planned for mid-October. Design will begin immediately.
8
6
Schedule
Dollars in   4
The current plan is to complete the design in the first quarter of 2011,       2
to advertise in the second quarter of 2011, and to construct during          0
the spring/summer of 2011 and 2012.                                       Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of     Construction Costs
construction funding and authority to advertise for construction will      Not Applicable
be requested when the design and bid documents are completed.
Photo
Change Order
None
Risks
This is a weather-dependent project.
Budget Transfers
None this quarter



AIRPORT
40  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Common Use Equipment Expansion (CUSE)
Project:    C800276         This project installs flexible           Status Snapshot
Budget: $3,090,000        common use facilities at some       On Schedule
Phase: Design            South Satellite and Concourse A     On Budget
Start: 09/01/2009             gates, as well as at Delta's former     0 Change Orders
Completion: 12/31/2011     (pre-NWA merger) ticket counters.    Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Procurement of the design consultant continues.
3.5
3
Schedule
2.5
The project is on schedule.                                               Millions  2
1.5
Budget                                           Dollars in  1
0.5
The project forecast is within the approved budget. Authorization of
0
construction funding and authority to advertise for construction will
Authorized   Forecasted  Costs Incurred
be requested when the design and bid documents are completed.
Change Order                                     Construction Costs
None                                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2010 Report  41

THIRD QUARTER REPORT, 2010
South Satellite Delta Sky Club Expansion
Project:    C800336       Construction of a new 6,800 square     Status Snapshot
Budget: $5,440,000      foot Sky Club lounge on the roof of     On Schedule
Phase: Design          the South Satellite for Delta Air Lines.   On Budget
Start: 06/01/2010                                                  0 Change Orders
Completion: 04/30/2011                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port of Seattle and Delta Air Lines have negotiated tenant
reimbursement amounts for the shell scope. The tenant is finalizing         6
the sizing requirements of the club before proceeding.                      5
Millions  4
Schedule
3
Construction work has not yet begun. Substantial completion is             2
scheduled for late spring 2011.                                            Dollars in   1
0
Budget
Authorized   Forecasted  Costs Incurred
The project forecast for the current scope is within the approved
budget and authorization.
Construction Costs
Change Order                                     Not Applicable
None
Risks
If the tenant decides to increase the size of the club, the Port's scope
and costs may increase beyond current authorization.
Budget Transfers
None this quarter



AIRPORT

42  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Roof Replacement Program
Project:    C800360         Remove and replace the roofing      Status Snapshot
Budget: $2,640,000        systems on the south and central    On Schedule
Phase: Design            sections of the Main Terminal. The   On Budget
Start: 4/25/2010              new roofing systems will achieve      0 Change Orders
Completion: 12/20/2010     LEED credits and are Energy Star    Total Change Orders Amount:
rated. This project is part of a         $0
multi-phased program.
Budget/Costs Incurred
Significant Developments
3
Design and bid document preparation is underway.                      2.5
Millions  2
Schedule
1.5
The project is on schedule.                                                 1
Dollars in 0.5
Budget
0
The project forecast is within the approved budget. Authorization of             Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                                     Not Applicable
None
Risks
None at this time
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 3Q 2010 Report  43

THIRD QUARTER REPORT, 2010
RW16C/34C Reconstruction Design
Project:    C800406         This project will produce the 60%     Status Snapshot
Budget: $669,000          design for the runway 16C/34C      On Schedule
Phase: Design            reconstruction. The design will      On Budget
Start: 05/04/2010             include utilities, runway status         0 Change Orders
Completion: 12/31/2010     lights, and other scope items        Total Change Orders Amount:
related to the project.                   $0
Significant Developments                              Budget/Costs Incurred
The 30% design was issued in September 2010.
0.8
Schedule                                           0.6
The 60% design will be completed in December 2010. Staff will           Millions
0.4
return to Commission for authorization of the remaining design funds
in late 2014 or early 2015.                                                  Dollars in 0.2
0
Budget
Authorized   Forecasted  Costs Incurred
The Port Commission authorized $669,000 on May 4, 2010. The
current forecast for 60% design is within the approved budget and
authorization. The forecast will be reassessed when staff returns to     Construction Costs
the Commission for authorization of the final design funds.              Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
None



AIRPORT

44  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Fire Vehicles
Project:    C102396         Purchase of fire vehicles according    Status Snapshot
Budget: $1,369,000        to the Fire Department Vehicle      On Schedule
Phase: Implementation     Replacement Master Plan. Includes   On Budget
Start: 11/16/2008             purchase of an ARFF vehicle and     0 Change Orders
Completion: 7/31/2009      medical aid unit vehicle.            Total Change Orders Amount:
$0
Significant Developments
The ARFF vehicle contract has been executed.                       Budget/Costs Incurred
The Medical Aid Unit contract has been executed; the Aid vehicle will      1.5
be in service beginning July 2010.
1
Schedule                                            Millions
The project is on schedule.                                                0.5
Dollars in
Budget                                            0
The project forecast is within the approved budget.                             Authorized  Forecasted Costs Incurred
Change Order
Construction Costs
None                                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2010 Report  45

THIRD QUARTER REPORT, 2010
Highline School Noise Insulation
Project:    C200007         Highline School Insulation           Status Snapshot  Prior Report
Budget: $101,797,000      Agreement will provide funding for    Delayed Schedule  3Q 09
Phase: Construction       sound mitigation for 15 schools that   On Budget
Start: 03/23/1999             are impacted by aircraft noise from    0 Change Orders
Completion: 11/30/2021     Sea-Tac Airport.                 Total Change Orders Amount:
$0
Significant Developments
The insulation of seven schools has been completed and no more      Budget/Costs Incurred
are scheduled until 2012.
120
100
Schedule
80
Port funding is authorized and will be available when the matching
60
funds are provided by the state and school district. The schedule for        Millions
40
state funding is not known. The district's schedule is also dependent      Dollars in 20
on obtaining general election bonds at various intervals.
0
Budget                                              Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not applicable
Not applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

46  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
3rd Runway Residential Acquisition
Project:    C200015         Acquire single/multi-family           Status Snapshot  Prior Report
Budget: $34,340,000       residences located in the noise-      Delayed Schedule  1Q 10
Phase: Close Out          impacted 3rd Runway flight path in    On Budget
Start: 05/27/1999             the City of Burien to comply with      0 Change Orders
Completion: TBD          FAA noise exposure and safety      Total Change Orders Amount:
regulations.                            $0
Significant Developments                              Budget/Costs Incurred
The final of three phases is complete. 58 of 59 properties have been       60
acquired and the residents relocated to quieter neighborhoods. The
apartment building property settled in mediation. The remaining           Millions 40
single property was determined by the court to be compatible land
20
use and will not be acquired.
Dollars in   0
Schedule                                              Authorized  Forecasted Costs Incurred
Currently on schedule
Budget                                         Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Photo
Change Order
Not Applicable
Risks
No significant risks identified.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 3Q 2010 Report  47

THIRD QUARTER REPORT, 2010
FAR Part 150 Mobile Home Park Acquisition
Project:    C200037       Acquisition of mobile and              Status Snapshot  Prior Report
Budget: $52,306,110      manufactured home parks, and       Ahead of Schedule      2Q 10
Phase: Close Out        reloaction of tenants, to reduce the     On Budget
Start: 02/12/2002           number of people living in mobile        0 Change Orders
homes within high noise areas.
Completion: 06/17/2010                                   Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
All mobile home units have been purchased. Demolition and site
restoration is 100% complete. This will be the last quarterly report        52.4
for this project.                                                                    52.2
Millions 52
Schedule
51.8
All tenants have been successfully relocated to quieter
neighborhoods.                                                     51.6  Dollars in 
51.4
Budget                                              Authorized Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                                     Construction Costs
Not Applicable
Not Applicable
Risks                                              Photo
None foreseen at this time.
Budget Transfers
None this quarter




AIRPORT

48  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Highline Community College Noise Insulation
Project:    C200042         Highline Community College         Status Snapshot  Prior Report
Budget: $10,822,000       Insulation Agreement will provide    Delayed Schedule  1Q 08
Phase: Construction       funding for up to 22 eligible         On Budget
Start: 01/11/2005             buildings that are impacted by        0 Change Orders
Completion: 10/01/2011     aircraft noise from Sea-Tac Airport.   Total Change Orders Amount:
$0
Significant Developments
Twelve of the 22 eligible buildings have been sound insulated by the    Budget/Costs Incurred
college.
12
Schedule                                           10
Building #9 is under construction and is anticipated to be complete          8
the first quarter of 2011. The schedules for the remaining buildings          6
in Millions
are dependent on state funding.                                           4
Dollars   2
Budget                                            0
The project forecast is within the approved budget. We will complete           Authorized  Forecasted Costs Incurred
noise audits on each of the remaining buildings that have not been
reconstructed to see if in the future any will be eligible for FAA grant
funds. Authorization of the remaining project budget will be              Construction Costs
requested for one building at a time from the Commission in the        Not Applicable
future when schedule is determined.
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. The Port is working with the College to determine
estimates for the remaining college buildings that have not been
completed.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 3Q 2010 Report  49

THIRD QUARTER REPORT, 2010
Home Insulation Retrofit
Project:    C200048         This CIP includes two projects that    Status Snapshot  Prior Report
Budget: $5,344,000        provide either re-insulation or repair   Delayed Schedule  4Q 09
Phase: Construction       of previously insulated homes due    On Budget
Start: 01/11/2005             to safety issues.                     0 Change Orders
Completion: 12/31/2011                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The Port is researching remaining eligible homes to continue with
insulation retrofit.                                                                    6
5
Schedule                                            4
The project will commence upon review of remaining homes.              Millions 3
2
Budget                                           Dollars in 1
The project forecast is within the approved budget and authorization.       0
Authorized   Forecasted  Costs Incurred
Change Order
Not Applicable
Construction Costs
Risks                                              Not Applicable
There is potential liability associated with egress safety issues.
Budget Transfers
None




AIRPORT
50  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Single Family Home Sound Insulation
Project:    C200093         Sound insulate remaining homes     Status Snapshot
Budget: $2,450,000        that are within the 1998 65 decibel    On Schedule
Phase: Construction       day night level (DNL) noise         On Budget
Start: 03/27/2007             contour.                             0 Change Orders
Completion: 12/31/2011                                   Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Five homes are in process and there are 30 on the waiting list for the
3
next group.
2.5
Schedule                                           Millions 2
Dollars in 
1.5
This project is on schedule.
1
0.5
Budget
0
The project forecast is within approved budget and authorization.
Authorized   Forecasted  Costs Incurred
Change Order
Not Applicable                                                       Construction Costs
Not Applicable
Risks
The ability to accomplish the insulation is dependent on
homeowner's schedules, willingness to sign an aviation easement,
and structural integrity of the home.
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 3Q 2010 Report  51

THIRD QUARTER REPORT, 2010
Street Vacations - Des Moines Creek 1
Project:    C800046     Purchase the City of Des Moines-        Status Snapshot  Prior Report
Budget: $3,850,000     owned streets in the Des Moines Creek   Delayed Schedule  1Q 10
Phase: Implementation  Business Park site that are surrounded   On Budget
Start: 10/01/2008         by Port-owned property. This             0 Change Orders
Completion: 12/31/2010 acquisition will enable the Port to        Total Change Orders Amount:
develop the business park site.            $0
Significant Developments                              Budget/Costs Incurred
Per the Port's agreement with the City of Des Moines, the amount
3.86
owed the City has been deposited into an escrow account pending
3.84
satisfaction of all the conditions required for closing.
3.82   Millions
Schedule                                           3.8
Acquisition is expected to be completed by December 31, 2010. The     3.78  Dollars in 
Port is still negotiating the agreement with the City of Des Moines,
3.76
which we expect to complete before the end of the year.
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.   Construction Costs
Not Applicable
Change Order
Not applicable
Risks
The original conditions required for closing--most notably, the Des
Moines City Council's approval of the developer's master plan--
cannot be met now that the developer selected for the project
withdrew from ground lease negotiations. The Port anticipates
revising its existing agreement with the City to reflect a new
approach to developing the site.
Budget Transfers
None this quarter

AIRPORT

52  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Burien Commercial Property Acquisition
Project:    C800150         Acquire commercial properties        Status Snapshot  Prior Report
Budget: $3,000,000        along Des Moines Memorial Drive,   Delayed Schedule       2Q 10
Phase: Implementation     and vacate one street, in the City of   On Budget
Start: 05/31/2007             Burien that is surrounded by Port-     0 Change Orders
Completion: 12/31/2011     owned properties.                Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
The Burien Seventh Day Adventists Church and School were
3.5
acquired December 31, 2008. Next acquisitions are for the
3
Sunnydale Substation and a street vacation in Burien.
Millions 2.52
Schedule                                           1.5
Properties are purchased as Commission authorization is received.       Dollars in   1
The program is now expected to be complete in 2011. The last            0.5
0
parcel to be acquired is tied to the North East Redevelopment Area
Authorized   Forecasted  Costs Incurred
(NERA) project which is a joint effort with the city of Burien. They will
not be ready to vacate the street until next year.
Budget                                         Construction
Not Applicable
The project forecast is within the approved budget.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 3Q 2010 Report  53

THIRD QUARTER REPORT, 2010
Tenant Reimbursement
Project:    C800154       Build out of spaces for new and         Status Snapshot
Budget: $4,709,577      existing tenants. If more than a "basic   On Schedule
finish" condition space is built for the      On Budget
Phase: Construction
tenant, the tenant is required to           0 Change Orders
Start: 08/14/2007
reimburse the Port for the cost of the     Total Change Orders Amount:
Completion: 03/31/2012
work beyond this "basic finish". These    $0
reimbursements are allowed under
the guidelines described in the          Budget/Costs Incurred
"Tenant Reimbursement Policy".
5
Significant Developments                                 4
Execution of Delta's South Satellite Tenant Reimbursement              Millions  3
Agreement for $190,000 was completed during the third quarter of
2
2010. This reimbursement is for ramp office improvements related to      Dollars in   1
their consolidation of operations on the South Satellite.
0
Schedule                                              Authorized  Forecasted Costs Incurred
Schedules vary to meet the tenant's needs.
Budget                                         Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

54  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
28th Ave Property Acquisition
Project:    C800381         Acquire by purchase two King        Status Snapshot
Budget: $1,455,000        County Parcels 042204-9218 &      Ahead of Schedule
Phase: Implementation     042204-9139. Demolish the        On Budget
Start: 5/4/2010                improvements on the Property and    0 Change Orders
Completion: 11/31/2010     restore it in accordance with the     Total Change Orders Amount:
Interlocal Agreement.                 $0
Budget/Costs Incurred
Significant Developments
1.46
The 28th Ave property has been acquired and demolition is complete.
1.44
Final removal of the concrete remains and should be completed in
1.42
November 2010.                                                Millions
1.4
Schedule
1.38   Dollars in 
The project will be completed ahead of schedule.                         1.36
Authorized   Forecasted  Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                                     Not Applicable
None
Risks
None identified at this time
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 3Q 2010 Report  55

THIRD QUARTER REPORT, 2010
T-115 Dock Reconstruction
Status Snapshot  Prior Report
Project:    C102451         Upgrade three areas of existing       Delayed Schedule  4Q 08
Budget: 31,541,577        1200 ft dock, upgrade Berth 1 and    Forecast Overrun  1Q 08
Phase: Construction       improve 15 acres of uplands for      29 Change Orders
Start: 7/03                    tug/barge cargo operations.           Total Change Orders Amount:
Completion: 12/31/09                                     $1,748,865
Significant Developments                              Budget/Costs Incurred
Construction was completed in 2Q 2010. The Tenant began using        32
Berth 1 at the end of April 2010. Final contract negotiations will
31.5
extend into 4Q 2010.                                                   Millions 31
Schedule
30.5
Project finalization is expected to move from 4Q 2010 to 1Q 2011.        Dollars in 
30
Authorized   Forecasted Costs Incurred
Budget
No change this quarter.
Construction Costs
Change Order
30
A change order was approved for unexpected difficulties in driving
25
pipe and sheet pile caused by unanticipated underwater
obstructions. However, project is expected to stay within the               Millions  20
15
approved budget.
10
Risks                                                Dollars in   5
0
None
InitialChange OrdersSpent
Budget Transfers
Photo
None
Cost Growth of Construction
No change form lat report Cost growth remains at 17.4 percent.

SEAPORT

56  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Terminal 30/Terminal 91 Program
Project:    C800085         Redevelop Terminals 25/28/30 into    Status Snapshot
Budget: $121,525,000      one combined container facility.      On Schedule
Phase: Construction       Relocation of the existing T-30      On Budget
Start: 10/02/07                Cruise operations into a new facility   129 Change Orders
Completion: 04/30/11       at T-91, and related facility          Total Change Orders Amount:
improvements and berth dredging.    $6,581,000
Significant Developments                              Budget/Costs Incurred
T-91: Installed protective bollards, signs, cable safety barriers for the
125
new canopies and canopy extension. New queuing/crowd control
barrier systems and benches were ordered and are in use.               120
Art Oversight Committee agreed to proceed with advertisement of
the Carving Contract for the Welcome Figures and the Carving           115
Millions
Contract has now been executed. The Graphic Artist Art Call has
Dollars in 110
been advertised.
105
Authorized   Forecasted  Costs Incurred
Schedule
T-91: Fencing and electrical works for the canopy are the remaining
work elements to be completed under the December 2009            Construction Costs
Commission authorization. The remaining work is scheduled to be
100
completed in 4th Quarter. Terminal's public arts component is
scheduled to be completed in 2011.                                       80
Millions   60
Dollars in 
T-30: T-30 components of the Program are in closeout and will no
40
longer be included in quarterly reports as previously reported.
20
Budget                                             0
The budget remains stable. Current program budget is $121,500,000            InitialChange OrdersSpent
and the forecast is $115,900,000.
Change Order                                     Photo
There were no change orders this quarter. Major construction
contracts are in closeout.
Risks
T-91: None. Facility is in operation.
T-30: None. Facility is in operation.

Port of Seattle 3Q 2010 Report  57

Budget Transfers
There were no budget transfers in or out of the program.
Cost Growth of Construction
T-91 Cruise Terminal Upgrade  MC-0314783  The major
construction contract is in closeout. Cost growth of construction
remains the same as reported previously in 4Q 09.
T-30 Upgrade  MC-103326  The major construction contract is in
closeout. The cost growth of construction remains as reported in
4Q 09










SEAPORT
58  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
P66 Bag. Corridor & Pass. Screening
Project:    C800114         Provide baggage and passenger      Status Snapshot  Prior Report
Budget: $2,087,000        screening improvements at P66 to    Delayed Schedule  3Q 09
Phase: Construction       accommodate larger cruise vessels   On Budget
Start: 1/1/2008                with 300-400 more passengers per    0 Change Orders
Completion: 3/31/2011      sailing.                         Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
The construction contract has been awarded for the last project in
2.5
this CIP, an elevator upgrade.
2
Schedule                                           Millions 1.5
Construction is scheduled to begin in January with a completion date       1
of March 2011.                                                       Dollars in 0.5
0
Budget
Authorized   Forecasted  Costs Incurred
None
Change Order                                     Construction Costs
None                                                 Not Applicable
Risks
The biggest risk is that there may be unforeseen conditions that
could possibly delay the project and conflict with the cruise schedule.
Budget Transfers
None




SEAPORT
Port of Seattle 3Q 2010 Report  59

THIRD QUARTER REPORT, 2010
Terminal 18 South Fender Improvements
Status Snapshot  Prior Report
Project: C800121           Replace 800' of deteriorated fender
Delayed Schedule  4Q 09
Budget: $3,300,000        system at the south end of
On Budget
Phase: Design            Terminal 18.
0 Change Orders
Start: 3/26/08                                                     Total Change Orders Amount:
Completion: 3/31/11                                      $0
Budget/Costs Incurred
Significant Developments
3.5
Bid advertisement and opening for construction of 800' of the fender        3
system. Apparent low bid is Manson Construction within 5% of the        Millions 2.52
engineer's estimate.
1.5
Dollars in   1
Schedule                                           0.5
0
No change from last report. Construction is scheduled to start in               Authorized  Forecasted Costs Incurred
December 2010, with berth available for use in March 2011.
Budget
Construction Costs
Project within approved budget.                                       None at this time
Change Order
Photo
None this quarter
Risks
None this quarter
Budget Transfers
None



SEAPORT
60  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
T-5 Crane Spreader Replacement                Status Snapshot  Prior Report
Delayed Schedule  1Q 10
Project:    C800123         To replace two crane cargo          On Budget
Budget: $525,000          spreader beams that are beyond     0 Change Orders
Phase: Construction       their useful life. Spreader beams     Total Change Orders Amount:
Start: 10/24/06                are terminal equipment used to       $0
Completion: 3/31/09        move containers to and from ships
and trucks.                           Budget/Costs Incurred
0.6
Significant Developments                               Millions 0.4
Spreader Beams were delivered 3Q 2010.
0.2
Schedule                                           Dollars in 
0
Project closeout is scheduled for 4Q 2010.
Authorized   Forecasted  Costs Incurred
Budget
On budget                                                    Construction Costs
0.5
Change Order
0.4
None
Millions  0.3
Risks                                                 0.2
None                                                   Dollars in  0.1
0
Budget Transfers                                            Initial Change Orders Spent
None
Photo



SEAPORT

Port of Seattle 3Q 2010 Report  61

THIRD QUARTER REPORT, 2010
North Harbor Island Mooring Dolphins (4)
Project:    C800182         Replace four barge mooring          Status Snapshot
Budget: $2,350,000        dolphins at the north end of Harbor   On Schedule
Phase: Design            Island.                        On Budget
Start: 07/05/09                                                    0 Change Orders
Completion: 3/31/11                                      Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Commission has approved construction funding for this project.
2.5
Design completed and construction work advertised.
2
Schedule                                           Millions 1.5
Project is still on schedule to be completed within the 2010-11 permit       1
fish window. Bid advertisement delayed approximately one month to      Dollars in 0.5
resolve lease obligation issue with Crowley Maritime for submerged
0
lands. Bid opening and award expected 4Q 2010.
Authorized   Forecasted  Costs Incurred
Budget
No change                                                  Construction Costs
None
Change Order
None                                                 Location
North Harbor Island
Risks
Scheduled completion date extended based on renewed project       Photo
analysis, longer lead time for steel materials and design completion.
Contractor schedule remains very tight.
Budget Transfers
None



SEAPORT
62  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
T-10 Interim Redevelopment
Status Snapshot  Prior Report
Project:    C800264         Funding is to develop full project
Budget: $980,000          scope and design of utilities to       Delayed Schedule  2Q 10
Phase: Design            support terminal related activities.    On Budget
Start: 03/22/08                Primary focus is the design of the     0 Change Orders
Completion: 11/30/2009     storm water drainage system and    Total Change Orders Amount:
the paving, lighting and fencing.        0
Significant Developments
Budget/Costs Incurred
As noted previously, revised design and permit documents were
submitted to the City, State and Federal Agencies. Staff continues to       8
work on addressing permit requirements with the Department of
6
Natural Resources. We expect to receive the permit in 4Q 2010          Millions 4
Schedule                                           2
The scheduled completion remains at 3Q 2011.                         Dollars in 0
Authorized  Forecasted     Costs 
Budget                                                          Incurred
As noted last quarter, staff will return to Commission for additional
construction authorization 4Q 2010.                                    Construction Costs
Not Applicable
Change Order
None                                                 Photo
Risks
Schedule delays
Budget Transfers
None



SEAPORT

Port of Seattle 3Q 2010 Report  63

THIRD QUARTER REPORT, 2010
T-91 Mobile Gangway
Status Snapshot
Project:    C800273         Construct two mobile gangways
Budget: $6,460,000        and the associated support         On Schedule
Phase: Construction       infrastructures for the new T-91      On Budget
Start: 6/24/2008              Smith Cove Cruise Terminal          6 Change Orders
Completion: 4/30/2009                                    Total Change Orders Amount:
$565,395
Significant Developments                              Budget/Costs Incurred
Mobile gangways performed well through the record breaking 2010       6.5
cruise season. Warranty will expire in October. This will be the last
6.45
report for the mobile gangways project.                                   Millions 6.4
Schedule                                          6.35
Dollars in 6.3                                                                                                      Project is in the close-out phase with an 18 month warranty period
expiring in October.                                                        6.25
Authorized   Forecasted  Costs Incurred
Budget
Project is on budget.                                                    Construction Costs
Change Order                                         8
One change order issued to reconcile performance bond.                   6
4
Risks
Millions
None                                                      2
Dollars in 
0
Budget Transfers
InitialChange OrdersSpent
None
Photo



SEAPORT

64  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
T-91 Roadway Pavement Project
Project:    C800343                                           Status Snapshot  Prior Report
Budget: $895,000        Repave two main roadway           Delayed Schedule  2Q 10
Phase: Design          intersections and the adjacent areas    On Budget
Start: 12/18/09             west of the east guard shack.            0 Change Orders
Completion: 5/1/2011                                     Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Completed the coordinated design effort with the T-91 Watermain
1
Replacement and Security project teams to minimize future impacts
to the proposed pavement work. Commission authorized staff to          0.8
proceed with the construction phase of the project on September         Millions 0.6
28th. Port Construction Services is mobilizing for construction.
0.4
Dollars in 0.2
Schedule
0
Construction is scheduled to begin in October and the completion
Authorized   Forecasted  Costs Incurred
date remains unchanged.
Budget
Construction Costs
Project is currently on budget.                                           Not Applicable
Change Order                                     Photo
None
Risks
Paving work is weather dependent and staff anticipates additional
challenges from the dynamic terminal operations. Also, the
conditions of existing underground vaults and utilities cannot be
accurately assessed until they are fully exposed after construction
starts.
Budget Transfers
None

SEAPORT

Port of Seattle 3Q 2010 Report  65

THIRD QUARTER REPORT, 2010
T46 Upgrade Yard Lighting
Status Snapshot
Project:    C800347         Purchase and Engineering support    On Schedule
Budget: $680,000          for installation of energy saving      On Budget
Phase: Design            yard lighting and equipment, as      0 Change Orders
Start: 08/25/09                part of T46 lease negotiation.         Total Change Orders Amount:
$0
Completion: 12/31/2010
Budget/Costs Incurred
Significant Developments
0.8
Re-advertisement resulted in multiple bids and contract for lighting
purchase was awarded to Stusser Electric Co. The Port will               0.6
purchase the equipment as needed for tenant installation.                 Millions
0.4
Schedule                                           Dollars in 0.2
On schedule
0
Authorized   Forecasted  Costs Incurred
Budget
No change
Construction Costs
Change Order                                     Not Applicable
None
Photo
Risks
None
Budget Transfers
None




SEAPORT

66  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
T-5 Crane Cable Reels
Status Snapshot
Project:    C800349         Purchase Cable Reels for tenant.
Budget: $3,500,000                                      On Schedule
Phase: Design                                         On Budget
Start: 05/04/10                                                    0 Change Orders
Completion: 03/31/11                                     Total Change Orders Amount:
0
Significant Developments
Budget/Costs Incurred
Commission approved funding for the Project on May 4, 2010. The
Consultant preparing the specifications also supports issues
5
impacting crane operation. During the 3Q 2010 most of the
4
Consultant's technical resource was focused on issue to maintain
operations. Consequently the performance specification was not          Millions  3
finalized.                                                                           2
Dollars in   1
Schedule
0
Not applicable
Authorized   Forecasted  Costs Incurred
Budget
None                                                 Construction Costs
Not Applicable
Change Order
None                                                 Photo
Risks
Schedule
Budget Transfers
None



SEAPORT

Port of Seattle 3Q 2010 Report  67

THIRD QUARTER REPORT, 2010
East Marginal Way Grade Separation
Project:    E 102007         FAST Corridor funded project;        Status Snapshot  Prior Report
Budget: $49,000,000       FHWA, State, City with Port         On Schedule 3Q 10
Phase: Construction       commitment of $18,800,000. Scope   On Budget  3Q 10
Start: 5/2006                 is to construct grade separation in     10 Change Orders
Completion: Q3 2011       vicinity of T5 and T18 to minimize    Total Change Orders Amount:
truck traffic/rail conflicts.                  $411,876
Budget/Costs Incurred
Significant Developments
60
Bridge substructure complete and pre-casting of span girders has          50
commenced. Utility installation includes large stormwater quality           40
vault.
Millions
30
20
Schedule                                           Dollars in  10
Construction is 50% complete and scheduled completion remains          0
September 1, 2011. The overall program schedule remains as was            Authorized  Forecasted Costs Incurred
reported in 4Q 09. The Schedule status snapshot is On Schedule
reflecting the current construction schedule.
Construction Costs
Budget
The overall program budget remains the same as reported in 4Q 09.        25
On future reports the budget that will be tracked will be the current           20
construction costs. The Budget status snapshot is On Budget
15
reflecting the active construction budget.
Millions
10
Change Order                                       Dollars in   5
Ten change orders have been executed for a total net amount of             0
$411,876.                                                                InitialChange OrdersSpent
Risks
Construction change orders could occur, which could increase cost     Photo
of construction.
Budget Transfers
New source of funds indicates that no budget transfers will be
required.

SEAPORT

68  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Terminal 46 ZPMC Gearboxes
Project:    Expense         Implementation of contingency       Status Snapshot
103705,103706,103707      plans to keep the three port owned   On Schedule
Budget: $1,227,000        ZPMC cranes located at Terminal    On Budget
Phase: Construction       46 operating while               0 Change Orders
Start: 8/22/2007              cause of the failing gearboxes is      Total Change Orders Amount:
investigated                           $0
Completion: 12/31/09*
Budget/Costs Incurred
Significant Developments
1.4
ZPMC sent letter to manufacturer of gearbox to replace all
1.2
gearboxes with new redesigned gearboxes. Continued efforts to
Millions  1
work with manufacturer to resolve will be managed as an operating        0.8
expense, as such the gear boxes will no longer appear in quarterly        0.6
reports.                                                                      Dollars in 0.4
0.2
Schedule                                            0
Authorized   Forecasted  Costs Incurred
Contingency plans were implemented through December 2008 as
spare parts were received and stored for future use when another
failure occurs. Monitoring of gearbox vibrations and oil quality occurs
Construction Costs
on a quarterly basis.
No Major Construction
Contracts
Budget
Budget remains unchanged from the 2Q 10 Report. Annual operating
expenses are $25,000 for quarterly monitoring and $90,000 for         Photo
potential gearbox replacement labor.
Change Order
None this quarter
Risks
Additional gearbox failures would result in further disruptions to
operations.
Budget Transfers
None

SEAPORT
Port of Seattle 3Q 2010 Report  69

THIRD QUARTER REPORT, 2010
T5 Maintenance Dredging
Project:    Expense     Mechanically dredge up to 3,000 cy of     Status Snapshot
103835                sediment at T5 and dispose of dredged   On Schedule
Budget: $1,980,000     material at approved upland disposal     On Budget
Phase: Construction    sites; conduct environmental testing,     0 Change Orders
Start: Feb 2008           permitting, and design work for T5         Total Change Orders Amount:
maintenance dredging                   $0
Completion: Feb 2011
Budget/Costs Incurred
Significant Developments                                2.5
Maintenance Dredging received Commission authorization for             2
construction on July 13, 2010. Project went out to bid, and received       Millions 1.5
bids well within authorized budget. Port has received all permits and
has completed contract award.                                           1
Dollars in 0.5
Schedule
0
Project is on schedule and construction is expected to start in                   Authorized  Forecasted Costs Incurred
December.
Budget                                         Construction Costs
Commission approved funding of $1,300,000 in July for construction    Not Applicable
phase.
Photo
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT

70  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Water/Sewer Meter Upgrade                    Status Snapshot  Prior Report
Delayed Schedule
Project:    E104206-14,     Upgrade existing water and sewer    On Budget
E104216, E104304-06       meter to meet current Seattle        0 Change Orders
Budget: $373,000          Public Utilities standards.          Total Change Orders Amount:
Phase: Planning                                        $0
Start: 09/13/09
Budget/Costs Incurred
Completion: 12/23/10
0.4
Significant Developments
0.3
This project has been transferred to Seaport Maintenance to oversee     Millions 0.2
and finalize. As such this will be the last report on this project.
Dollars in 0.1
Schedule
0
Project is on schedule.                                                         Authorized  Forecasted Costs Incurred
Budget
Construction Costs
Of the $373,000, approximately $123,000 is tenant reimbursable.
None at this time
Change Order
Photo
None
Risks
POS and tenant will pay higher commercial sewer rates on meters
without upgraded technology.
Budget Transfers
None


SEAPORT


Port of Seattle 3Q 2010 Report  71

THIRD QUARTER REPORT, 2010
Street Vacations T5,18,105
Status Snapshot
Project: Expense        Street vacation related real estate        On Schedule
104362, 104364, 104366  negotiations and agreements --T5,       On Budget
Budget: $1,500,000     T18, and T105.                     0 Change Orders
Total Change Orders Amount:
Phase: Permitting
$0
Start: June 2010
Budget/Costs Incurred
Completion: Feb 2012
2
Significant Developments                                1.5
Millions
Numerous real estate issues with the City were resolved. Final             1
agreements are in drafting stage.
Dollars in 0.5
Schedule
0
On Schedule                                                        Authorized  Forecasted Costs Incurred
Budget
On Budget                                                   Construction Costs
Not Applicable
Change Order
Photo
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable



SEAPORT

72  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
SBM Renewal and Replacement
Project:    C001706,        Redevelopment Shilshole Bay        Status Snapshot  Prior Report
C001769, C001716          Marina docks, landside facilities,     On Schedule
Budget: $80,000,000       infrastructure and buildings.         On Budget
Phase: Construction                                    149 Change Orders
Start: 1997                                                        Total Change Orders Amount:
$6,299,064
Completion: 4/30/2010
Budget/Costs Incurred
Significant Developments
81
The construction of interim flatwork and landscaping were completed
during the reporting period. This will be the final report.                      80
Millions 79
Dollars in 
Schedule
78
Interim Pad Site improvements and landscaping work completed.
Site is open for public access.                                               77
Authorized   Forecasted  Costs Incurred
Budget
No change this quarter.                                               Construction Costs
Change Order                                        100
None this quarter                                                          80
Millions   60
Risks
40
None
Dollars in    20
0
Budget Transfers
InitialChange OrdersSpent
None
Location
Shilshole Bay Marina
Photo

REAL ESTATE

Port of Seattle 3Q 2010 Report  73

THIRD QUARTER REPORT, 2010
T 102 HVAC Renewal/Replacement
Project:    C800070         Replace HVAC System at all four     Status Snapshot  Prior Report
Budget: $1,300,000        buildings at the Harbor Marina       Delayed Schedule  4Q 08
Phase: Construction       Conference Center               On Budget
Start: 10/2/2005                                                   0 Change Orders
Completion: 3/1/2011                                     Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Six of the remaining seven HVAC units have been installed and
1.32
booked.                                                          1.3
1.28
Schedule                                          1.26  Millions
1.24
The last unit is scheduled to be installed in late December 2010 or        1.22
early January 2011 above the Anchor tenant space.                     Dollars in 1.2
1.18
1.16
Budget
Authorized   Forecasted  Costs Incurred
Funding has been authorized to complete the project during this
quarter and the budget has been rest.
Construction Costs
Change Order
None                                                     0.4
0.3
Risks                                                Millions
Anchor tenant may not allow contractor to work in their space until           0.2
August 2011.
Dollars in   0.1
Budget Transfers                                         0
Initial Change Orders Spent
None



REAL ESTATE

74  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
T-86 Grain Facility Modernization                 Status Snapshot  Prior Report
On Schedule
Modernize and replace aging grain    On Budget
Project:    C800133         facility equipment/controls for $5M    1 Change Orders
by 12/31/2011 to maximize           Total Change Orders Amount:
Budget: $2,500,000
operational efficiencies and allow      $40,000.00
Phase: Construction       continuation of uninterrupted grain
Start: 2/21/2010              terminal operations.                 Budget/Costs Incurred
Completion: 11/30/2011
1
0.8
0.6
Significant Developments
0.4
Millions
Phase-1 portion of the project is complete. Final close out                 0.2
procedures are in process.                                              Dollars in  0
Authorized   Forecasted     Costs 
Phase-2 portion of the project is currently in design and will prepare                               Incurred
to advertise and bid in Q4.
Construction Costs
Schedule
Not Applicable
None
Photo
Budget
None
Change Order
None
Risks
None
Budget Transfers
None


REAL ESTATE

Port of Seattle 3Q 2010 Report  75

THIRD QUARTER REPORT, 2010
FT South Wall Reconstruction Phase IV
Project:    C800136         Completion of Fishermen's           Status Snapshot
Budget: $5,535,000        Terminal South Wall              On Schedule
Phase: Construction       Reconstruction. Phase IV is located  On Budget
Start: 6/2009                 along parcel currently leased by       0 Change Orders
Completion: 6/2011        FVO.                          Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Design completed and permits approved. Construction funding
6
approved and construction bids received. IMCO was low bidder at
5
approximately $2,149,000 (engineer's estimate was $2,696,000).
Millions  4
3
Schedule
2
No changes this quarter.                                                Dollars in   1
0
Budget
Authorized   Forecasted  Costs Incurred
Budget has been updated to reflect authorized construction funding.
Change Order                                     Construction Costs
None this quarter                                                     None at this time
Risks                                              Photo
None this quarter
Budget Transfers
None




REAL ESTATE

76  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
MIC Central Seawall Replacement
Project:    C800175         Replacement of steel sheet pile       Status Snapshot
Budget: $2,650,000        seawall between West Pier and      On Schedule
Phase: Construction       Central Pier at Maritime Industrial    On Budget
Start: 9/2008                 Center.                              0 Change Orders
Completion: 6/2011                                      Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Design completed and permits approved. Construction funding
3
approved and construction bids received. IMCO was low bidder at
2.5
approximately $1,099,000 (engineer's estimate was approximately
Millions  2
$1,177,000).
1.5
Schedule                                            1
Dollars in 0.5
No changes this quarter.
0
Authorized   Forecasted  Costs Incurred
Budget
Budget has been updated to reflect authorized construction funding.
Construction Costs
Change Order                                     None at this time
None
Photo
Risks
None
Budget Transfers
None



REAL ESTATE

Port of Seattle 3Q 2010 Report  77

THIRD QUARTER REPORT, 2010
P91 Fender System Upgrade
Project:    C800183         Upgrades to the vessel berths of      Status Snapshot
Budget: $2,125,000        P91 to better accommodate cruise    On Schedule
Phase: Design            ships and also serve the other       On Budget
Start: 01/31/10                industrial customers who utilize the    0 Change Orders
Completion: 04/30/2012     berths and adjacent dock/apron      Total Change Orders Amount:
areas on P91 for less than $5.5M      $0
by spring 2011.
Budget/Costs Incurred
Significant Developments
Commission approval for design of complete system, construction of      2.5
Phase I improvements, and purchase of replacement camel barges.        2
Phase I construction consists of the replacement of 15 piles to            Millions 1.5
strengthen the facility for the 2011-12 cruise season.
1
Schedule                                           Dollars in 0.5
Phase I construction is scheduled to start in January 2011, complete        0
by April 2011. Full replacement is to be completed by April 2012.               Authorized  Forecasted Costs Incurred
Budget
Project is within approved budget.                                      Construction Costs
None at this time
Change Order
None this quarter
Risks
None this quarter
Budget Transfers
None



SEAPORT

78  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
T-91 Watermain Replacement
Project:    C800298         Replace water main in the vicinity     Status Snapshot  Prior Report
Budget: $700,000          of Magnolia Bridge and City         On Schedule
Phase: Design            Ice/Trident including various        On Budget
Start: 9/20/2009              buildings at T91                      0 Change Orders
Completion: 12/30/2011                                   Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Design is completed. Comission will approve construction funding to
5
move the project forward in Q4 2010.
4
Schedule                                           Millions 3
Dollars in 
On schedule                                                       2
1
Budget
0
On budget
Authorized   Forecasted  Costs Incurred
Change Order
None                                                 Construction Costs
Not Applicable
Risks
Contaminated material may be encountered throughout the            Photo
excavation process.
Budget Transfers
None



SEAPORT

Port of Seattle 3Q 2010 Report  79

THIRD QUARTER REPORT, 2010
FT NW Dock East Fender System Replacement
Project:    C800386         Replace existing timber fender       Status Snapshot
Budget: $3,750,000        system for the east section of the    On Schedule
Phase: Construction       NW Dock at Fishermen's Terminal    On Budget
Start: January 2010          including all new steel piling and      0 Change Orders
Completion: April 2011     associated fender system.          Total Change Orders Amount:
$0
Significant Developments                              Budget/Costs Incurred
Construction plans and specifications were completed. Request for
4
construction bids was advertised and the contract will be executed in
October.                                                              3
Millions
2
Schedule
Site construction work will start in mid January 2011 and will be           Dollars in   1
completed by the end of April 2011.
0
Authorized   Forecasted  Costs Incurred
Budget
Total project budget is $3,750,000.
Construction Costs
Change Order                                     Not Applicable
No construction change orders to date; construction contract has
been executed, but work has not commenced.
Risks
In-water pile replacement work must be completed by April 15, 2011
to comply with anticipated permit requirements.
Budget Transfers
None

REAL ESTATE



80  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
T18 Fender Replacement
Project:    C800416         Replacement of 200 timber fender    Status Snapshot
Budget: $5,465,000        piles and their supporting members   On Schedule
Phase: Construction       along the face of the SSA crane     On Budget
Start: 02/07/2010             terminal.                             0 Change Orders
Completion: 03/15/2012                                   Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Design documents completed, Commission authorization for
construction of both phases of work.                                        7
6
Schedule
Millions  5
4
Construction scheduled in two phases to accommodate permit
3
windows and tenant operations. First phase scheduled to start in
January 2011, second phase to be completed by March 2012.           Dollars in   2
1
0
Budget
Authorized   Forecasted  Costs Incurred
Project is within the approved budget.
Change Order                                     Construction Costs
None this quarter                                                     None at this time
Risks
None this quarter
Budget Transfers
None



SEAPORT

Port of Seattle 3Q 2010 Report  81

THIRD QUARTER REPORT, 2010
Flight Information System (FIMS) II
Project: C101117           Procure, develop, and implement a   Status Snapshot
Budget: $5,400,000         FIMS system that includes          On Schedule
Phase:Design             replacement monitors, an airport     On Budget
Start: 5/4/2010                resource management system, and   0 Change Orders
Completion: 12/30/2012     a flexible digital signage system      Total Change Orders Amount:
capable of displaying flight             $0
information, visual paging, and
notifications.
Budget/Costs Incurred
Significant Developments
6
Evaluating vendor proposals for a replacement resource
5
management system and for the monitor casework design. Planning
4
and architecture design in progress.
3
in Millions
Schedule                                            2
Dollars   1
On Schedule
0
Authorized   Forecasted  Costs Incurred
Budget
On Budget
Construction Costs
Change Order                                     Not Applicable in the phase
None
Risks
Aircraft activity feeds will be requested from every airline in the new
industry standard format. There is a risk that not all airlines will
initially agree to this request causing a schedule delay.
Budget Transfers
None


CORPORATE

82  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Maximo Enterprise Implementation
Project:    C800003         Implement latest version of           Status Snapshot
Budget: $3,680,000        Maximo, merge Aviation and Real    Delayed Schedule
Phase: Implementation     Estate applications onto one        On Budget
Start: 11/25/2007             platform, add service desk module    0 Change Orders
Completion: 12/30/2012     and wireless handheld capabilities.   Total Change Orders Amount:
$0
Significant Developments
Major components of the program have been delivered including the    Budget/Costs Incurred
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of             4
Marine Maintenance and Aviation Maintenance Maximo systems in
3
September 2010. The smaller components of mobility enhancements
and additional interfaces remain.                                           Millions 2
1
Schedule                                           Dollars in
Several of the proposed new interfaces link the Maximo system to          0
the Peoplesoft Financials Procurement module. Because of planned           Authorized  Forecasted Costs Incurred
changes in the procurement process with the Peoplesoft Financials
Upgrade project, the delivery of these interfaces may be delayed
until after the completion of the upgrade project. Due to resource       Construction Costs
constraints, the delivery of the mobility enhancements will be           Not Applicable
completed in June 2011.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None

CORPORATE

Port of Seattle 3Q 2010 Report  83

THIRD QUARTER REPORT, 2010
Ground Transportation Management System
Project: C800227           Procure and implement a Ground     Status Snapshot
Budget: $840,000           Transportation Management        On Schedule
Phase: Planning            System for tracking and billing       On Budget
Start: 4/27/2010               ground transportation operators at    0 Change Orders
Completion: 6/30/2011      the airport.                       Total Change Orders Amount:
$0
Significant Developments
Vendor selected through competitive procurement. Project kickoff      Budget/Costs Incurred
scheduled for mid-November.
1
Schedule                                           0.8
On Schedule                                                    Millions 0.6
0.4
Budget
Dollars in 0.2
On Budget
0
Change Order                                          Authorized  Forecasted Costs Incurred
None
Construction Costs
Risks
Not Applicable
No significant risks
Budget Transfers
None




CORPORATE

84  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Port of Seattle Internet Redesign
Project: C800319           Create a new Internet web site, and   Status Snapshot  Prior Report
Budget: $500,000           underlying infrastructure, with        Delayed Schedule       2Q 10
Phase:Planning            dynamic content and interactive      On Budget
Start: 1/6/2009                communication tools such as blogs,   0 Change Orders
Completion: 6/30/2011      video, podcasts, discussion forums   Total Change Orders Amount:
and interactive maps.                 $0
Significant Developments                              Budget/Costs Incurred
Procurement evaluations in progress for website design vendor.
0.6
Schedule                                           0.5
0.4
Prior Report - The delay caused by the need to re-advertise the RFP
0.3
for an implementation vendor will delay the estimated completion to        Millions
0.2
2nd quarter 2011.                                                       Dollars in 0.1
Budget                                            0
Authorized   Forecasted  Costs Incurred
On Budget
Change Order
Construction Costs
None                                                 Not Applicable
Risks
No significant risks identified
Budget Transfers
None



CORPORATE

Port of Seattle 3Q 2010 Report  85

THIRD QUARTER REPORT, 2010
External Sharepoint
Project: C800320           Implement External Microsoft        Status Snapshot
Budget: $500,000           Sharepoint Services to support      Delayed Schedule       1Q 10
Phase:Implementation      application consolidation, customer   Under Budget
Start: 1/6/2009                collaboration, and system            0 Change Orders
Completion: 2/1/2011        integration opportunities.            Total Change Orders Amount:
$0
Significant Developments
Project was put on hold by ICT Management to evaluate security       Budget/Costs Incurred
issues and potential solutions identified during architecture                    Dollars [Thousands)
600
development. After evaluation, a lower-cost solution utilizing a
500
hosted sharepoint environment has been selected that will meet the
400
current needs for the Port Internet Redesign and other external
projects.                                                                      300
200
Schedule                                           100
Solution is in progress and will be ready for deployment in February         0
Authorized    Forecasted   Costs incurred
2011.
Budget                                         Construction Costs
This solution can be delivered at a lower-cost than the original          Not Applicable
proposed solution resulting in an estimated 50% under-run of
$250,000.
Change Order
None
Risks
No significant risks
Budget Transfers
None

CORPORATE

86  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Enterprise Project Cost Management
Project: C800321           Replace the current construction     Status Snapshot
Budget: $1,525,000         costing systems with a common      Delayed Schedule
Phase:Planning            enterprise project cost             On Budget
Start: 4/21/2008               management system.                0 Change Orders
Completion: 9/30/2011                                      Total Change Orders Amount:
$0
Significant Developments
Negotiations are in progress to update agreement and finalize          Budget/Costs Incurred
implementation plan.
2
Schedule
1.5
Vendor did not deliver software per original contract and project was
put on-hold to evaluate alternatives. A decision was made to               Millions 1
continue with Skire in July 2010. The estimated completion date at
Dollars in 0.5
this time is September 2011 although there may be interim deliveries
prior to completion.                                                           0
Authorized   Forecasted  Costs Incurred
Budget
None
Construction Costs
Change Order                                     Not Applicable
None
Risks
See Schedule
Budget Transfers
None



CORPORATE

Port of Seattle 3Q 2010 Report  87

THIRD QUARTER REPORT, 2010
Records and Document Management
Project:    C800322         Improve statutory compliance,        Status Snapshot  Prior Report
Budget: $800,000          increase functionality, and lower     Delayed Schedule       2Q 10
Phase: Implementation     operating costs by replacing        On Budget
Start: 6/23/2009              Hummingbird with SharePoint for      0 Change Orders
Completion: 5/30/2011      records and document             Total Change Orders Amount:
management.                    $0

Significant Developments                              Budget/Costs Incurred
Incorporating upgrade to Sharepoint 2010 because of significant
improvements in Records Management features.
1
Schedule                                           0.8
Prior Report - Sharepoint 2010 implementation is dependent on the       Millions 0.6
completion of several infrastructure projects currently in progress.          0.4
This will delay the implementation of Sharepoint Records Center and     Dollars in 0.2
full build out of department sites until Spring 2011.
0
Authorized   Forecasted  Costs Incurred
Budget
On Budget
Construction Costs
Change Order                                     Not Applicable
None
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None


CORPORATE

88  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Business Continuity
Project: C800326           Acquire new backup and storage     Status Snapshot  Prior Report
Budget: $1,760,000         software and hardware that will      Delayed Schedule
Phase:Implementation      facilitate business continuity in the    On Budget
Start: 6/23/2009               event of a disaster                   0 Change Orders
Completion: 4/30/2011                                      Total Change Orders Amount:
$0
Significant Developments
Installation of the High Capacity Storage Device is complete and        Budget/Costs Incurred
data migration scheduled to complete in November is going well.
2
Schedule
1.5
Previous Report - Insufficient power in the data center required
unplanned infrastructure upgrades for the new High Capacity               1
in Millions
Realtime Storage Device. The new device is estimated to be online
Dollars 0.5
in October 2010 and final project completion is estimated in April
2011, a six month delay from the original schedule.                         0
Authorized   Forecasted  Costs Incurred
Budget
On Budget
Construction Costs
Change Order                                     Not Applicable
None
Risks
No significant risks
Budget Transfers
None



CORPORATE

Port of Seattle 3Q 2010 Report  89

THIRD QUARTER REPORT, 2010
Time Clock System
Project:C800387            Procure and implement a Time      Status Snapshot
Budget:$840,000           Clock System to accurately capture   On Schedule
Phase:Planning            and track time and attendance for    On Budget
Start: 6/8/2010                approximately 230 employees in      0 Change Orders
Completion:7/30/2012       Aviation Security and Airport        Total Change Orders Amount:
Operations organizations.             $0

Significant Developments                              Budget/Costs Incurred
Negotiating contract with vendor selected through an RFP process.
0.4
Schedule                                           0.3
On Schedule
Millions 0.2
Budget                                           Dollars in 0.1
On Budget
0
Authorized   Forecasted  Costs Incurred
Change Order
None
Construction Costs
Risks                                              Not Applicable
Cost of selected time clock system is greater than business case
estimate. There is a risk that contingency is not sufficient to cover
additional cost.
Budget Transfers
None



CORPORATE

90  Port of Seattle 3Q 2010 Report

THIRD QUARTER REPORT, 2010
Peoplesoft Financials Upgrade
Project:C800392            Upgrade of Peoplesoft Financials     Status Snapshot
Budget:$5,000,000          hardware and software             On Schedule
Phase:Planning                                         On Budget
Start: 9/28/2010                                                  0 Change Orders
Completion:12/31/2012                                     Total Change Orders Amount:
$0
Significant Developments
Implementation vendor procurement in progress                      Budget/Costs Incurred
6
Schedule
5
On Schedule
4
Millions 3                                                                                                     Budget
2
On Budget                                                     Dollars in 1
0
Change Order
Authorized   Forecasted  Costs Incurred
None
Risks                                              Construction Costs
Significant resources will be required across multiple organizations     Not Applicable
which may delay other technology projects.
Budget Transfers
None




CORPORATE

Port of Seattle 3Q 2010 Report  91

THIRD QUARTER REPORT, 2010
Port Roster
Project: C800397         Develop and implement a single Port     Status Snapshot
Budget: $450,000        Roster & Bid System that replaces the   On Schedule
Phase: Design          functionality of three rosters, supports    On Budget
Start: 1/26/2010           new Central Procurement Office         0 Change Orders
Completion: 2/28/2011    processes , and simplifies the process    Total Change Orders Amount:
for Port vendors.                          $0
Significant Developments
Budget/Costs Incurred
In Development
0.5
Schedule                                           0.4
On Schedule                                                   Millions 0.3
0.2
Budget                                           Dollars in 0.1
On Budget                                                      0
Authorized   Forecasted  Costs Incurred
Change Order
None                                                 Construction Costs
Not Applicable
Risks
No significant risks
Budget Transfers
None




CORPORATE

92  Port of Seattle 3Q 2010 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.