5f Memo

PORT OF SEATTLE 
MEMORANDUM 

COMMISSION AGENDA                   Item No.         5f 
Date of Meeting      April 14, 2009 
DATE:      April 6, 2009 
TO:         Tay Yoshitani, Chief Executive Officer 
FROM:     Dakota Chamberlain, Director, Seaport Project Management 
SUBJECT: Request authorization for construction and for approval to advertise a major works
bid package based on the design prepared and completed for Bird Control systems
at Smith Cove Cruise Terminal. 
SYNOPSIS 
Smith Cove cruise terminal is situated in a prime area for Seagull and other pest bird activity. 
Due to the seasonal nesting activity of these birds, it is important for the terminal to have systems
in place to prevent nesting and to discourage birds from roosting above areas which will
experience heavy cruise customer traffic.
BACKGROUND
In January of 2009, the Port of Seattle, using an existing open order contract, executed a service
directive for a design that identified and proposed solutions for pest bird activity. Using the 
Port's drawings, the designer created a comprehensive plan to address the locations most
vulnerable to bird activity. 4 distinct areas were identified and appropriate systems/materials
specified for each section.
PROJECT DESCRIPTION/SCOPE OF WORK 
The scope of work developed includes the following: 
BUILDING ROOF 
Bird netting will be installed upon the air handling units and the skylights to prevent gulls from
getting close enough to the units to be out of the wind. Uprights will be installed upon the
corners of the skylights and air handling units that extend upward and outward from the
structures. These uprights will support an installation of bird netting that will protect the
skylights and units, while allowing easy access for maintenance. A bird shock track system, a
standard and harmless device used to prevent Gulls from landing on the edge of the roof, will run
around the perimeter of the roof.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
April 6, 2009 
Page 2 of 3 
BUILDING CANOPIES 
To prevent perching, roosting, or nesting by any species of bird above the walkways or other
areas that will be occupied by passengers,  inch polyethylene bird netting, supported by a
stainless steel cable/bracket system will be mounted under the North Entrance Canopy, and both
the East and West Balcony Canopies. Tension wire, which prevents birds from perching, will be
installed upon any surfaces that will be below the plane of the netting. The bird netting is
uncomplicated to remove and replace, allowing for future maintenance needs. 
ACCESS / EGRESS STAIRWAYS 
There are four separate stairways to be treated. The deterrent in these locations will be bird
netting installed across the underside of the ceiling in the same manner as that used under the
adjacent canopies of the exterior passenger balconies. The netting will prevent entry into the
areas behind the support beams near the corners and along the top edges .There are some flanges
that are too low to be protected by the netting and these will be protected by installing a bird
slide on them. A bird slide is a product which creates an angle at which birds are unable to perch.
There are beam tops that will be protected by installing tension wire (bird wire) upon them. 
SOUTH EXTERIOR BEAMS (SUNSCREENS) 
Tension wire and bird slide will be installed on the exposed beams in this area to prevent birds 
from perching and roosting. 
ALTERNATIVES CONSIDERED/RECOMMENDED ACTION 
1.  Do nothing. Without action, not only will nesting and roosting be an issue, but the associated
droppings will become a problem. Bird droppings can be extremely toxic and disease laden
and could easily be tracked in to the cruise terminal. This is not the recommended alternative. 
2.  Install a comprehensive bird control system to discourage and prevent birds from nesting at
the Smith Cove Cruise Terminal. This is the recommended alternative. 

FINANCIAL IMPLICATIONS 
Cost Estimate 
The cost estimate for this work is $185,677. However, with the addition of sales tax, the estimate
becomes $203,316.31. 
Source of Funds 
The capital costs incurred will be allocated to the work project budget of the existing 
CIP 800085. No additional funds are requested.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
April 6, 2009 
Page 3 of 3 
Financial Analysis 
The costs associated with this authorization request are included in the overall budget of the
existing cruise terminal project. 
PROJECT SCHEDULE 
The scope of work associated with this request is anticipated to be completed within 60 days of
contract award. Special care has been taken to specify allowable working days based on the
cruise call schedule.
PREVIOUS COMMISSION ACTION 
On February 14th, 2006, the Commission authorized $10,850,000 for staff to proceed with
environmental reviews, design, and permitting of the T25/30 container terminal and the relocated
T91 Cruise Terminal. 
On April 11th, 2006, the Port Commission authorized the Chief Executive Officer to execute
lease amendments with SSA Terminals for T18, 25, 30, and with Cruise Terminals of America
for Cruise facilities. 
On February 16, 2007, the Commission authorized an additional $107,489,000 for staff to
proceed with final design and construction of the T91 cruise terminal and restoration of container
cargo facilities at T25/30. 
On July 22, 2008 Commission authorization changes to the Terminal 30/91 Program due to
foundation changes required by the City of Seattle: Change Order #20 for a cumulative time
extension of 78 days; Change Order #32 exceeding $200,000; and Additional funds in the
amount of $3,186,000 for a total authorization of $121,525,000.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.