9b Baggage Optimization Presentation

Item No. 9b_supp 
Meeting Date: October 23, 2018 
Baggage Optimization 
Third Quarter Briefing and
Project Update

AGENDA 
Project Overview 
2018 Quarter 3 Update 
Budget 
Schedule 
Challenges 
Accomplishments 
Progress 
Sustainability 
Baggage Optimization Project                                                                            2

PROJECT OVERVIEW 
Replaces six individual baggage screening
systems with a centralized system that
optimizes the operation and functionality
of the checked baggage system 
Key elements: 
60 Million Annual Passengers (MAP) 
Reliability 
Redundancy 
Security 

Complete Overhaul of Outbound System                                                              3

2018 Q3 Update 
Schedule 
Contractor Falling Behind on Submittals and Fabrication 
Phase 1: 
Contractor Maintaining Two Work Shifts (Mon. through Fri.) 
Conveyor Installation is ongoing (Critical Path) 
Phase 2: 
100% Design Documents 
Reviewing Phase 2 estimates 
Developing Phase 2 Bid Documents 
Phase 1 Schedule Concerns                                                                            4

FINANCIAL PROGRESS REPORT 
Authorization Summary                 Capital       Expense         Total 
$450
Millions                                                                                                                       Current Budget                             $444.90 M         $0.15 M     $445.05 M 
$400                                                                                       Current Authorization                 $136.16 M       $0.15 M    $136.31 M 
$350                                                                                       Amount Remaining to be             $308.74 M          $0 M    $308.74 M 
Authorized 
$300
$250
$200                                                                                                         Total Project (Capital + Expense) 
Budget      Spent to    Forecast at    Variance 
$150
Date    Completion 
$100
Soft Cost                 $64.99 M      $23.01 M       $64.99 M         $0 M 
$50                                                                                       Construction           $359.43 M      $35.55 M     $359.43 M         $0 M 
$-                                                                                                            Management             $20.63 M            $0 M       $20.63 M          $0 M 
Management Reserve Remaining     Construction Remaining           Reserve 
Construction Spent                   Soft Cost Remaining
$445.05 M     $58.56 M     $445.05 M        $0 M 
Soft Cost Spent

Financial Breakdown  Project Tracking Within Authorized Budget                                          5

FUNDING CONTRIBUTION 
(Port Contribution to Date
$31.7M) 

Port 
$351M 
79%                                     (TSA Contribution to Date
$27.0M) 
TSA 
$94M 
21% 
Total Project Budget                          $445,050,000 
Total TSA Contribution                         $94,043,296 
Total Port Contribution                        $351,006,704 
Amount Spent to Date                      $58,566,741 
TSA Reimbursement to Date                 $27,005,449 

TSA OTA/LOI Reimbursement                                                                      6

SCHEDULE 




Contractor Delay Extends Overall Completion Date                                                        7

SMALL BUSINESS/APPRENTICESHIP UTILIZATION 
SCS/SBE                                                APPRENTICESHIP 

Overall
SBE Const                                                              (15%)
(15%)
Women
(10%)
SCS Const
(5.0%)                                                                Minority
(15%)

0.0%   50.0%  100.0%  150.0%  200.0%  250.0%                0.0%         50.0%        100.0%       150.0%
Goal   Actual                                                     Goal   Actual

Tracking Close to or Exceeding Goals                                                                         8

CHALLENGES 
Phase 1 Construction Schedule
Baggage Handling/Steel Market Conditions for Phase 2 Bid 
Operational Impacts Through Construction 
IAF Coordination  IAF must be operational prior to Phase 2 SSAT construction 
Project Coordination  Have coordinated with 48+ projects so far 

Overcoming Challenges                                                                               9

ACCOMPLISHMENTS 
Continuous delivery and installation of new conveyors. 
100% Phase 2 Design Documents reviewed. 
New CT Ramp Construction complete. 
Maintenance breakroom in Concourse B complete. 
Conveyor Factory Acceptance Test (FAT) conducted, retest scheduled Q4 
Continued construction on utilities and infrastructure. 

Baggage Optimization Construction Progress                                                             10

SUSTAINABILITY 
Energy Conservation                          Water Conservation 
Optimized system is projected to result          No opportunity 
in up to 30% energy savings 
Working Environment 
Improved ergonomics 
Waste Reduction 
Contractual requirement to recycle
demolished material when possible 

Opportunity in Energy Conservation                                                                     11

New Conveyor Sections                                                                              12

North EDS Screening Matrix                                                                             13

CTE Bump Out  Steel Installation                                                                          14

Factory Acceptance Testing  Detroit, MI                                                                   15

Drive In A Box Network Testing  Louisville, KY                                                                16

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.