6f Environmental Remediation Liability Memo

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6f 
ACTION ITEM                            Date of Meeting     November 13, 2018 
DATE:     October 26, 2018 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Kathy Bahnick, Sr. Mgr., Environmental Programs 
Don Robbins, Sr. Environmental Program Mgr. 
SUBJECT:  2019  2023 Environmental Remediation Liability (ERL) Program 
Amount of this request:             $ 17,025,000 
ACTION REQUESTED 
Request Commission authorization  for  (1) the Executive Director  to  spend environmental 
remediation funds for 2019  in the amount of $17,025,000 and (2) approving a five-year
spending plan for $116,026,000 for the environmental remediation liability (ERL) program for
2019-2023, of which an amount estimated not to exceed $30,000,000 will be obligated during
2019 to be spent in future years. 
EXECUTIVE SUMMARY 
As a major industrial and commercial landowner, the  Port has significant environmental
cleanup liabilities due to historic contamination of its properties. The $17,025,000 requested
spending  authorization  for  2019  will  allow  continuation  of  ongoing  environmental
investigations, testing, analysis, design, cleanup, and monitoring for active sites and will initiate
similar activities for new sites to be noted in the Commission memorandum.  The spending
authorization and five-year plan will allow the Port to enter into contracts for work spanning
multiple years. Prior to actual spending of these future obligated funds, Commission budget
approval will be needed, likely through future annual ERL authorizations. The approval of the
five-year  plan  gives  greater  visibility  to  our  projected  upcoming  environmental  liability
spending. 
Environmental remediation projects define and minimize, to acceptable levels, threats to the
environment caused by the effects of historic industrial activity on properties acquired by the
Port, prior Port operations, and prior tenant operations. Generally, the results of these efforts,
as well as the attendant compliance with regulatory mandates, management of Port liabilities,
and support of the local community, align with the goals and objectives of the Century Agenda,
Long Range Plan, and Maritime, Aviation, Economic Development Division and Storm Water
Utility Business Plans. 

Template revised April 12, 2018.

COMMISSION AGENDA  Action Item No.  6f                               Page 2 of 12 
Meeting Date: November 13, 2018 

JUSTIFICATION 
Consistent with past practices, the duration of the authorization continues to be an annual
spending authorization.  Since 2011, the authorization requests have also provided a rolling
five-year spending plan to reflect the level of resources expected to be required over the next
five years.  Executing contract obligations for a longer duration minimizes the need to rework
all  contract  amendments  and  service  directives  that  are  aligned  with  the  end-of-year
authorization. It also provides greater visibility of the environmental liability costs. 
The environmental investigation and remediation actions described below are generally
required under federal and/or state law; exceptions are noted. Remedial actions continue to
focus on cost-effective study, analysis, and implementation of cleanup actions; coordination
with capital planning, design, and construction; and negotiation with agencies, tenants, other
Potentially Responsible Parties (PRPs) and insurance companies. 
Project Objectives: 
(1)      Perform the remediation work at the various sites in accordance with the various state
or federal requirements. 
(2)      Manage and perform the work, with project controls and contract systems in place. 
(3)      Identify and consider community values and concerns as part of the various public
participation plans. 
(4)      Perform remediation investigations, designs and implementations that will be carried
out in a manner that considers current and potential uses for the sites. 
(6)      Perform initial investigations and scoping work to identify future actions. 
(5)      Maximize cost recovery. 

DETAILS 
Scope of Work 
Maritime, Economic Development and NWSA Homeport Sites/Projects 
Lower Duwamish Waterway Superfund Site  The Lower Duwamish Waterway (LDW) is a
federal Superfund site under the Comprehensive Environmental Response, Compensation, and
Liability Act (CERCLA).  The Lower Duwamish Waterway Group (LDWG), consisting of the Port,
the City of Seattle, King County and Boeing has completed a Remedial Investigation and
Feasibility Study (RI/FS) of the LDW under order with the Environmental Protection Agency
(EPA) and the state Department of Ecology (Ecology). In November 2014, after seeking
concurrence from Ecology, EPA issued the Record of Decision for the LDW Site. Also in 2014, as
part of the ongoing studies, LDWG initiated a Fisher Study to determine who is using the river
for fishing and to aid EPA in development of appropriate institutional controls during and after

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                               Page 3 of 12 
Meeting Date: November 13, 2018 
cleanup. This work was completed in 2016. LDWG also began a carbon amendment pilot study
at the end of 2014, which is anticipated to be completed in 2020 and in 2016 began performing
pre-design activities including a baseline monitoring program and a waterway user study.
LDWG began pre-design work in 2017, which will be completed in early 2019. The LDWG
parties signed an order amendment in 2018 to begin cleanup design work of the upper third of
the river. The joint procurement process for the design consultant has begun and is expected
to be complete in January 2019 when the design work will begin. Design of the upper third is
expected to be complete in 3-4 years. The Port shares costs with the other LDWG parties for
the current work being performed on this site. In addition to the in-water investigations, the
Port is monitoring, tracking and working on source control aimed at reducing recontamination
after the in-water cleanup is performed.  The Department of Ecology is the lead agency for
source control work. 
Terminal 117 Sediments, Bank and Uplands  As part of the LDW Superfund Site effort, EPA
identified the Port's Terminal 117 (T-117)in South Park as an Early Action Area (EAA).  This
work was performed by the Port with a cost sharing agreement with the City. EPA issued an
Action Memorandum in 2010 that included the EPA-selected cleanup plan. The Port completed
the T-117 upland soil and sediment cleanup in 2014. The Port constructed the final stormwater
controls at the site and is beginning long-term monitoring and maintenance, to verify the
continued performance of the cleanup. 
South Park Marina  As part of the effort to control sources of contamination to the LDW,
Ecology has identified potential source sites that could require early cleanup action. One such
site is South Park Marina, which is adjacent to and north of Terminal 117.   Ecology has
identified the Port as a Potential Liable Party (PLP) for the cleanup of this site under the state
Model Toxics Control Act (MTCA), and has requested the Port participate as a signatory to an
order along with two other PLPs, the City of Seattle and South Park Marina. The request for
authorization to sign the order will be presented to Commission after Ecology completes a 45-
day public comment period.
Terminal 108  Ecology has also identified Terminal 108 as a potential source control site. In
2006 and 2007, at Ecology's request, the Port investigated groundwater at the site  and 
determined that the groundwater is not a source of contaminants to the Lower Duwamish.
However, additional upland contamination was discovered on the site that generated future
investigation requirements. As part of an Interagency Agreement (IAA) with Ecology, in 2015
the Port completed a bank stabilization project along 350 feet of shoreline and cleanout of
stormwater conveyance lines. In 2017, Ecology requested that EPA handle oversight of the
Terminal 108 site due to limited resources at Ecology  and historic federal government
involvement at the site. The Port  signed an EPA Order in 2017 to perform a preliminary
assessment (PA) and data gaps analysis for the site.  The PA report will be finalized later this
year.  Additional assessment, cleanup and source control work is likely to be required in the
future. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                               Page 4 of 12 
Meeting Date: November 13, 2018 
Terminal 115 South  The Port, along with Boeing, has been named by Ecology as a PLP under
MTCA at Terminal 115 South, which is the location of the former Boeing Plant 1 facility. Boeing
and the Port are negotiating an Ecology MTCA order to perform a remedial investigation and
feasibility study. Once the order is negotiated, the request for authorization to sign the order
will be presented to Commission after Ecology completes a 45-day public comment period,
which is expected to occur in the first quarter of 2019. 
Terminal 115 North  In 2009, Ecology identified the Port as a PLP under MTCA for Terminal
115 North, located adjacent and to the south of Glacier Bay, one of the high priority sediment
sites within the LDW Superfund Site. The Port entered into an order with Ecology in 2010. Since
then, the fieldwork for the remedial investigation has been completed and the Port submitted
the draft Remedial Investigation report to Ecology in October 2017. 
Terminal 5 Ecology State Cleanup Sites  In the past, as part of the Terminal 5 Southwest
Harbor redevelopment, the Port completed remediation at four sites under Consent Decrees
with Ecology. Current obligations related to those cleanups include on-going cap inspection and
maintenance of the cap areas. As part of the T-5 redevelopment, the Port purchased the old
West Seattle Landfill and installed an environmental cap and a methane collection system.
These systems require long-term operation and maintenance, inspection, and reporting, which
are continuing. The Port is currently evaluating the potential of converting the active methane
collection system to a passive system. 
Terminal 5 Pacific Sound Resources (PSR) Superfund Site  This site was cleaned up under an
order with EPA as part of the Terminal 5 Southwest Harbor redevelopment project. Ongoing
obligations include continuing to perform required cap inspection and cap maintenance,
product recovery activities, and monitoring EPA activities related to the groundwater and the
off-shore sediments.
Lockheed West - As part of the South West Harbor Redevelopment Project, the Port purchased
aquatic and upland property on the north end of the current Terminal 5 from Lockheed Martin.
The upland portion of the property is part of the Terminal 5 Ecology State Cleanup Sites
described above. The adjacent submerged portion is a Superfund cleanup site known as the
Lockheed West Seattle Site, and includes submerged land owned by both the Port and the state
Department of Natural Resources. Under its purchase and sale agreement with the Port,
Lockheed is obligated to investigate and cleanup the sediment within the site. On August 28,
2013, EPA issued the record of decision for the site. Lockheed Martin is the sole PRP
responsible to perform the cleanup work.  Cleanup fieldwork started in October.  The Port is
coordinating cleanup activities, reviewing sediment cleanup documents by Lockheed Martin,
and providing comments to EPA. 
Harbor Island Superfund Site Soil and Groundwater Operable Unit  Cleanup of this Superfund
site was performed under a Consent Decree with EPA, and the PRP group consultant is
performing long-term groundwater monitoring under a PRP agreement.   Long-term cap

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                               Page 5 of 12 
Meeting Date: November 13, 2018 
maintenance and inspections are ongoing as required under EPA's Record of Decision. Terminal
18 is located within this Superfund site.
Harbor Island Superfund Site East Waterway Sediments Operable Unit  In 2006, the Port
signed an order with EPA to conduct a final Supplemental Remedial Investigation and Feasibility
Study (SRI/FS), and a Memorandum of Agreement with the City of Seattle and King County to
share costs and cooperate in the SRI/FS process. The PRPs have conducted the SRI/FS tasks
identified in the EPA order and subsequent work plans. EPA approved the final RI in January
2014. The final Feasibility Study was submitted to EPA in November 2017. EPA had some
additional comments and we are in the process of finalizing the Feasibility Report, which is
expected to be complete later this year. 
Terminal 30 Cleanup   Terminal 30 is a former Chevron bulk storage site that is being
remediated under MTCA. Since the 1990s, the Port has removed significant amounts of free
product and conducted an extensive groundwater-monitoring program. The required public
comment period for the draft consent decree and cleanup action plan was completed and the
Port signed a final consent decree in early 2017. The Port has begun design of the selected
remedy for the site. Implementation (cleanup construction) will begin in 2019, followed by long
term monitoring. 
Terminal 10 Lockheed  Lockheed Martin previously performed the upland and sediment
cleanup required at this Superfund site. The Port has a continuing obligation to maintain the
upland cap and the habitat restoration area, manage any contaminated soil and groundwater
encountered or removed during redevelopment or maintenance activities, and protect
Lockheed's groundwater monitoring wells. Under the Terminal 10 Uplands capital project, the
Port completed stormwater drainage and upland cap improvements in early 2012.  As a
condition of EPA approval, the Port initiated long-term stormwater solids sampling after the
capital project.
Terminals 103/104/105/107  These sites have been identified by Ecology as having source
control data gaps related to the Lower Duwamish Waterway Superfund Site, and will likely
require future investigation and possibly remediation.
Terminal 106 (West and Warehouse parcels)  These sites have been identified by Ecology as
having source control data gaps related to the Lower Duwamish Waterway Superfund Site, and
will likely require future investigation and possibly remediation.
Natural Resource Damages (NRD) Habitat Restoration  The Port's Superfund liability for LDW
and Harbor Island sediments includes injury to natural resources from contamination. The Port
is negotiating with the Elliott Bay Trustee Council (Trustees) for a settlement of this liability.
Terminal 91 Cleanup  Investigation and cleanup of this site is being administered by Ecology
under a State Dangerous Waste Permit and a MTCA order. The bulk of the uplands cleanup
work was completed in mid-2015 and long-term groundwater monitoring and maintenance has 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                               Page 6 of 12 
Meeting Date: November 13, 2018 
begun. Investigation and cleanup of discrete units is ongoing as they are discovered. In 2016, 
pursuant to an amendment to the order the Port regraded a small shoal along the east side of
Pier 91 with oversight by Ecology. Ecology also  required the Port to begin a preliminary
investigation into the site sediments, which was completed in 2018. The Port and Ecology are
working to determine the next steps for the sediment portion of this site. The site is particularly
complicated due to the existence of discarded military munitions (DMM) from the Navy's use of
the site during the World War II era. Ecology will most likely require a MTCA order to conduct a 
remedial investigation and feasibility study in 2019. 
Fishermen's Terminal  The Port has removed some contaminated soils in the uplands, capped
a portion of the uplands, and has performed some investigation of groundwater monitoring at
and near the Fishing Vessel Owners (FVO) tenant site.  Some dredging of contaminated
sediments occurred as part of the Docks 5-10 renewal and replacement and berth dredging
project.
Aviation Sites/Projects 
Aircraft Fuel Farms and Fueling Systems  Five underground aircraft fueling systems were
constructed and operated by individual airlines beginning in the early 1960s. As of January
2007, each of these systems has been decommissioned.  Appropriate environmental cleanup
has been achieved for three of the systems and is in progress for two others. Remediation of an
area impacted by operations of the former United Airlines and Continental Airlines fuel farms is
complete as of 2017. Confirmation monitoring, closure negotiations with the Department of 
Ecology, and decommissioning of the remediation system remain. The Port is a member of the
PLP group for this multiple-source site. 
Lora Lake Apartments  In 2009, the Port and Ecology executed a MTCA order that required the
Port to conduct a remedial investigation and feasibility study (RI/FS) for the cleanup of the Lora
Lake Apartment Property. The RI/FS was finalized in 2013. A Consent Decree, along with the
Cleanup Action Plan, was finalized in 2015. Remedial design, including extensive field sampling
and analysis, occurred in 2015 and 2016, and Commission authorized a major works contract to
implement the remediation in  September 2016. Remediation of the former Lora Lake
Apartment site has been completed. Remaining work for year two of the cleanup consists of
final capping of the lake sediments with additional fill to restore the site to historic wetland
conditions. This work was scheduled to occur during the dry season of 2018 but was postponed
to 2019 due to a labor strike that prevented the work from occurring during dry weather.
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
The following alternatives were considered for accomplishing the work described above: 
Alternative 1  Do not complete the work. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                               Page 7 of 12 
Meeting Date: November 13, 2018 
Cost Implications: Projects must be completed eventually; potential short-term cost savings by
not doing work now, followed by significant cost increases due to enforcement actions by
regulators, litigation by other parties, and general costs of delay. 
Pros: 
(1) Staff could not identify positive aspects for this alternative. 
Cons: 
(1) Could  result  in  the  regulators,  including  Department  of  Ecology  or  EPA,  taking
enforcement action that could lead to Ecology or EPA implementing the remedy and the
Port liable for three times the costs incurred by the regulator. 
(2) The Port would lose the  opportunity to employ the flexibility contained in the
controlling regulations, to define and direct the work, and to manage costs. 
(3) Would not comply with Port's obligation to remediate the sites. 
(4) Would not honor our cost sharing agreements for multiple sites. 
(5) Would delay work previously agreed to under existing regulatory orders or under
voluntary programs. 
This is not the recommended alternative. 
Alternative 2  Complete the work using Port staff only. Port staff is already heavily involved in
project direction, legal analysis, and project management, and will continue to perform these
services. The nature and extent of the technical and legal work required to complete this work
is substantial, and would require a large number of additional staff with additional expertise in
a number of highly technical specialty areas. Contracts would still be required for such work as
laboratory analysis. This is not the recommended alternative. 
Cost Implications: Increased costs due to need for new employees with advanced technical
expertise on project-specific basis, under-utilization of specialized staff, and purchase of
specialized equipment. 
Pros: 
(1) Reduces staff costs for contract administration. 
(2) Additional hired employees would provide flexible work force. 
(3) Provides trained Port workforce with specific technical expertise. 
(4) Provides consistent reporting and documentation. 
Cons: 
(1) Servicing peak seasonal demand would require hiring additional full-time employees
resulting in un-utilized labor throughout the majority of the year. 
(2) Would require additional Port staff. 
(3) Would require purchase of substantial amount of specialized sampling equipment. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                               Page 8 of 12 
Meeting Date: November 13, 2018 
(4) Would still require some contracting for tasks staff would not be able to perform such as 
laboratory analysis. 
(5) Many of the sites are joint sites with multiple partners who may not agree to the Port
performing the work. 
This is not the recommended alternative. 
Alternative 3  Complete the work using outside consultants and contractors only (Port or
other partners as contracting agent or outside support). Outside consultants and contractors
have sufficient numbers and types of specialists necessary for timely and cost-effective
completion of this work; however, the work would be more costly than if some Port staff were
also involved. This is not the recommended alternative. 
Cost Implications: Reduced Port staff costs where Port staff only have oversight role, but
increase in overall costs. 
Pros: 
(1) Provides  for  a  competitive  procurement  process  and  encourage  small  business
participation. 
(2) Provides full service support and expertise. 
(3) Provides staff with the tools to respond in a timely manner to new requests from EPA or
Ecology. 
Cons: 
(1) Increases staff time to track, compile and manage contractor reports. 
(2) Prime contractor would charge to manage these services. 
(3) Reduces technical development opportunities for Port staff. 
(4) This approach would result in the loss of in-house historical knowledge of Port-owned
sites. 
This is not the recommended alternative. 
Alternative 4  Complete the work using a combination of Port staff (Alternative 2) and outside
consultants and contractors (Alternative 3) that maximizes the ability for the Port to direct
cleanup efforts and maximize the effectiveness of staff. This is the recommended alternative. 
Cost Implications: Balances the Port's oversight role for managing the remediation project and
accessing technical consultants for adjusting service levels to effectively respond to regulator's
demands. 
Pros: 
(1) Provides contracted and Port work force that can increase or decrease service level of
effort as needed. 

Template revised September 22, 2016; format updates October 19, 2016.


COMMISSION AGENDA  Action Item No.  6f                               Page 9 of 12 
Meeting Date: November 13, 2018 
(2) Provides trained workforce with specific technical expertise. 
(3) Provides consistent reporting and documentation. 
(4) Provides opportunities for businesses, including small businesses, to participate in Port
work. 
(5) Provides staff with the tools to respond in a timely manner to new requests from the
regulator. 
(6) Does not require a large expenditure for field equipment or the long-term maintenance
of the equipment. 
(7) Allows for technical development of Port staff. 
(8) Keeps in-house historical knowledge of Port-owned sites. 
Cons: 
(1) Requires more staff time than alternative 3. 
(2) Coordination is required between Port Environmental Program Manager and consultant. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
The following table summarizes 2019 through 2023 forecasted spending for environmental
remediation projects. Forecasted spending reflects projects described in the Scope of Work.
Five-Year Spending Plan 
$s in Thousands       2019       2020         2021        2022      2023     2019-2023 
Project Spending       $17,025       $17,146       $28,842   $23,471    $35,280     $121,763 
Cash from 3rd
Parties*                ($1,318)       ($1,207)       ($1,072)    ($1,069)    ($1,071)       ($5,737) 
Net Port Share         $15,707      $15,939       $27,769   $22,402    $34,209     $116,026 
*Note: Forecasted amounts do not include estimates of possible recoveries. 
Budget/Authorization Summary 
$s in Thousands          Spent           Budget              Recovery 
2013 - 2017           $66,919           $91,763              $(40,992) 
2018 thru 9/30/2018      $3,864           $19,800              $(8,539) 
*Note: Budget does not carry over. Recovery includes money from prior years. The difference
between budgeted and spending for 2018 is due to the labor strike delaying projects, other
delays due to regulatory negotiations, carrying the contract for other partners who reimburse,
and recognition the year is not complete. 
Annual Budget Status and Source of Funds 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                              Page 10 of 12 
Meeting Date: November 13, 2018 
Airport  Airport Development Fund 
Maritime, Economic Development, and homeport liabilities on Northwest Seaport Alliance
managed property  Tax Levy 
Financial Analysis and Summary 
Environmental cleanup projects have multiple funding sources: (1) Maritime and Economic
Development non-operating projects are funded by the Port's Tax Levy; (2) Maritime and
Economic Development operating projects are funded by the General Fund; (3) Airport projects
are funded by the Airport Development Fund.  In addition, there are supplementary outside
sources of funding, including the following: 
Cash from third parties (payment from cost-sharing or contribution agreements with
other potentially liable parties (PLPs), where the Port functions as a funding conduit for
the other PLPs and the Port holds contracts on behalf of these other PLPs) 
Litigation settlements with other PLPs 
Allocation settlements with other PLPs 
Insurance recoveries from both the Port's insurers and other PLPs' insurers 
Department of Ecology grants 
ADDITIONAL BACKGROUND 
The Port has identified a number of contaminated sites on Maritime, Economic Development,
homeport liabilities on Northwest Seaport Alliance (NWSA) and Aviation properties that must
be investigated and remediated in compliance with federal and state environmental laws and
regulations.  In some cases, the Port has been designated by the federal government as a
"Potentially Responsible Party" (PRP), and/or by the state government as a "Potentially Liable
Party" (PLP) for the investigation and cleanup of properties owned by the Port or where the
Port may have contributed to site contamination. 
Although the Port may not bear ultimate liability for the contamination, under federal and state
law, the Port is presumptively liable as the property owner, and it is often practically and
financially beneficial for the Port to take initial responsibility to manage and pay for the
cleanup. 
In many cases, the Port has successfully recovered and/or will seek recovery from other
responsible parties for Port-incurred investigation and cleanup costs.  The Port also has been
successful in receiving Model Toxics Control Act (MTCA) grant funds to pay part of the cleanup
costs. The Port's goals are to cost-effectivelycomplete this environmentally responsible work
and to maximize work accomplished by or paid for by the parties responsible for the conditions
encountered (or others, such as insurance companies, who represent them).
To manage such environmental expenditures, the Port also encourages, coordinates with, and
oversees the investigation and cleanup of sites by other responsible parties, to assure that legal

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                              Page 11 of 12 
Meeting Date: November 13, 2018 
requirements are met and that Port liabilities are minimized. Regardless of whether the Port
conducts the investigation and remediation directly, or oversees the proper performance of
that work by other responsible parties, the Port provides a valuable public benefit by acting as a
catalyst in expediting appropriate environmental management of these sites. 
Accounting rules require that the Port "book" or establish a liability on its balance sheet for
environmental remediation when the Port's obligation meets specified definitions of certainty
and the liability amount can be reasonably estimated. When an environmental remediation
liability  is  booked,  an  expense  is  also  recorded  in  the  current  period  for  the  future
expenditures. The Port develops its environmental remediation liability forecasts in compliance
with Government Accounting Standards Board (GASB) Statement No. 49 "Accounting and
Financial Reporting for Pollution Remediation Obligations." 
Environmental liability expenditures are authorized in one of two ways: 
1.       If the environmental costs are incurred in the course of, or incidental to, a construction
project, the Commission authorization occurs as part of the authorization for the overall 
construction project.  Examples of this include asbestos removal, off-site soil disposal during
construction, or upland dredge material disposal. 
2.       If  the  environmental  cost  is  not  associated  with  a  capital  construction  project  or
maintenance (including asbestos and lead), but is a stand-alone pollution remediation project,
the expenditure is authorized through one annual action. 
Since 1993, the Commission has approved annual environmental expenditures.  In addition,
Commission  authorization  is  obtained  prior  to  entering  into  legal  commitments  for
investigation or cleanup actions, such as an Agreed Order, Administrative Order on Consent
(AOC), or Administrative Settlement Agreement and Order on Consent (ASAOC) (collectively
referred to as "Orders"). Under the Orders, the Port is required topay agency oversight costs.
Further, to the extent required by the General Delegation of Authority, Central Procurement
Office contract actions in support of approved environmental projects may require additional
Commission authorization. 
Since  1993,  the  Port  has  booked  liabilities  to  recognize  these  obligations.  While  Port
environmental cleanup projects typically span several years, more complex projects have been
active for over 15 years. 
ATTACHMENTS TO THIS REQUEST 
(1) Map of ERL Sites North Properties Maritime, Economic Development 
(2) Map of ERL Sites South Properties Maritime, Economic Development and NWSA 
(3) Map of ERL Sites Aviation 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No.  6f                              Page 12 of 12 
Meeting Date: November 13, 2018 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
November 6, 2017   the Commission approved the 2018  (1) spend environmental
remediation liabilities funds for 2018 in the amount of $19,800,000; (2) approving a fiveyear
spending plan of $88,800,000 for the Environmental Remediation Liability (ERL)
Program for 2018 to 2022 of which an amount estimated not to exceed $30,000,000 will
be obligated during 2018 to be spent in future years. 
November 8, 2016   the Commission approved the 2017 (1) spend environmental
remediation liabilities funds for 2017 in the amount of $17,700,000; (2) approving a fiveyear
spending plan of $85,800,000 for the Environmental Remediation Liability (ERL)
Program for 2017 to 2021 of which an amount estimated not to exceed $33,600,000 will
be obligated during 2017 to be spent in future years. 
December 8, 2015   the Commission approved the 2016 (1) spend environmental
remediation liabilities funds for 2016 in the amount of $13,900,000; (2) approving a fiveyear
spending plan of $71,700,000 for the Environmental Remediation Liability (ERL)
Program for the Seaport, Real Estate, and Aviation Divisions for 2016-2020. 
December 1, 2014  the Commission approved the 2015 project-wide authorization of (1) a
five-year spending plan of $36,804,000 for the Environmental Remediation Liability
(ERL) Program for the Seaport, Real Estate, and Aviation Divisions for 2015-2019; and (2)
environmental remediation liabilities funds for 2015 in the amount of $36,804,00, of
which (a) $16,804,000 is forecasted to be spent in 2015 and (b) an amount estimated
not to exceed $20,000,000 of the remaining funds approved in the five-year plan will be
obligated during 2015 to be spent in future years. 
December 3, 2013  the Commission approved the project-wide authorization of (1) a fiveyear
spending plan of $106,740,000 for the Environmental Remediation Liability (ERL)
Program for the Seaport, Real Estate, and Aviation Divisions for 2014-2018; and (2)
environmental remediation liabilities funds for 2014 in the amount of $42,180,000, of
which (a) $22,180,000 is forecasted to be spent in 2014 and (b) an amount estimated
not to exceed $20,000,000 of the remaining funds approved in the five-year plan will be
obligated during 2014 to be spent in future years. 





Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.