February 11, 2020

Project Location



2

Project Scope/Justification
Provide security modifications to prevent unauthorized access
to the Rental Car Facility (RCF)
Anti-climb architectural barriers installed on floors 1-3 that are
accessible from the ground level.
Scope increased to include all ground floors
Egress only security doors with audible alarms installed in all eight
external stair towers on floors 1-4.
Scope increased to allow open stair towers to comply with building codes.

3

Cost Estimate Uncertainty vs. Level of Design
Costs Including Contingency %   90
70

50

30

10    Upper Range
Growth from Estimated  -10    Lower Range
-30

-50
0           10           20           30           40           50           60           70           80           90          100
Project Scope Definition %
5                  Class 3                                            Class 1
Class 4                                         Class 2

4

Project Drawings


Before                                                After

5

Project Schedule & Estimated Cost
Description               Year Quarter                     Description              Estimated Cost
Design Complete              2020 Q3                     Design Phase              $1,115,000
Construction Start               2020 Q4                    Construction Phase             $4,885,000
In-Use Date                 2021 Q4                          Total                   $6,000,000





6

Lessons Learned
U00266  Bird Nests
Make sure building is cleared of any nesting birds prior to installation
U103640  Panel Layout
Panel layout required more than necessary custom panels
Design as many standard panels as possible
U103640  Panel Tolerance
Panel tolerance was tighter then tolerance for structural steel
Match tolerances of product manufactured

7

Project Risks
Risk                Description                    Prob.   Impact  Mitigation Plan
Anchor Placement  Will placement interfere with     H      M    Design a suitable anchor to avoid rebar or
existing structural steel.                              map rebar in the concrete prior to anchor
placement.
Custom Panels     Limit the number of custom       H       L     Review design to ensure the maximum
panels designed.                                 number of standard panel widths.
Steel Tariffs          Steel tariffs increase cost of         M        H      Talk to CPO about escalation or address
materials.                                          through specifications.
Open Parking      Proposed materials may not       L       M    During design ensure the specified product
Garage           meet code requirements.                      meets code requirements.


8

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.