9b North Satellite Modernization Budget Increase Briefing Presentation

NSAT Budget Increase Briefing            Item No.  9b_supp
Date of Meeting      February 25, 2020

NSAT Budget Increase Request
$800
Budget Growth: $40M
$700
$712         5.9% over previous approval
$672  $672     +5.9%
$600                                                         Expended to Date
$500
Millions
Authorized by Commission
$411
$400                                                         Revised Budget (Commission
approved)
$300
$200
$100          Expended to Date      Authorized      Commission Approved 2017                   Forecast                Forecast
$0
NSAT Budget

NSAT Budget Increase Request
5.9%
$40M     Construction Potential
Risk                 Scope Added by Port/Airlines
(Pending)
Changes in Process

Added Support Cost


Management
Reserve
Differing Site Conditions

3

Factors Driving Increase
Capital:                                              Capital (cont'd):
Design development allowance, now complete        Reconstructing vertical circulation
Code changes                                   core while passengers moving
Differing site conditions discovered during               through area
construction                                     Scope Additions
Market Conditions / Contractor Availability
Lack of Subcontractor availability, labor        Expense:
shortages, lack of qualified labor                Additional contaminated & unsuitable
Ability to "pick and choose" projects             soils
Customer service provision changes
Schedule/Phasing Complexity:
Incorporating a more rigorous activation
Maintaining 'prior to construction' levels of      effort
operational & customer service
4

Continued Risks Requiring Mitigation
Contaminated & unsuitable soils
Maintaining old systems until Phase 2 opening
Resource availability (labor vs schedule/acceleration)
Complications related to Art piece "Boundary" installation
Gate closure coordination
Removal of temporary systems after Phase 2 opening


5

Lessons Learned
Design
Ensure completion stage of design documents and timing of subcontract bids are fully evaluated and balanced
Ensure complexities of phased construction are fully vetted

Code Compliance
Early (Design Development) and ongoing Building and Fire Department engagement and bi-weekly check-ins
continue during construction
Cost
Thoroughly review project complexity and risks when estimating contingencies
Delivery Method
Leverage experience and capability of GCCM for maximum control of construction work; limit work performed by
other means and account for risks of doing so
Capital vs Expense
Increase focus on budgeting for maintaining customer experience during construction

6
10/30/2019

Small Business on Track
SCS Participation                                     SBE Participation                                     WMBE Participation
SCS Participation   $ Requirement   $ Committed   $ Paid                      SBE Participation   $ Requirement   $ Committed   $ Paid                        WMBE     $ Requirement     $ Committed     $ Paid
$25                                                                 $90                                                                  $18
Millions                           $22.5          $22.7                             Millions                                           $78.1
$80                                                                 Millions $16                                    $15.4
$14.7
$20
$70                    $65.4                                          $14
$11.9
$60                                                $54.5              $12
$14.6
$15
$50                                                                  $10
$40                                                                   $8
$10
$30                                                                   $6
$20                                                                   $4
$5                        Requirement             Committed             Paid               $10                         Requirement             Committed             Paid                $2                          Requirement             Committed               Paid

$0                                                                  $0                                                                   $0
SCS Total                                                                  SBE Total                                                                    WMBE Total

PAID TO DATE
SCS:    $14.5M Paid / $22.5M Required = 64.7%
SBE:    $54.5M Paid / $65.4M Required = 83.2%
WMBE: $11.9M Paid / $14.7M Required = 80.8%

7

Apprenticeship exceeding Goals
Women Apprenticeship                             Minority Apprenticeship                            TOTAL Apprenticeship
% Goal          % Utilization                                                % Required         % Utilization
Women Apprenticeship   % Goal  % Utilization
12%                                                           35%                                      32.9%                20%                                      18.6%
10.0%               10.0%                                                                                    18%
10%                                                           30%
16%            15.0%
25%                                                           14%
8%
12%
20%
6%                                                                      15.0%                                        10%
Utilization          15%
8%
4%
10%                                                            6%
2%                            Goal                                                                                       4%
5%                Goal                       Utilization                 2%               Goal                          Utilization
0%                                                        0%                                                        0%
Women Total                                                     Minority Total                                                    Apprenticeship Total

UTILIZATION
Women:  10.0% Goal / 10.0% Utilization = 100.0%
Minority:  15.0% Goal / 32.9% Utilization = 219.3%
Total:       15.0% Goal / 18.6% Utilization = 124.0%

8

Program on Schedule
2019                Today                          2020                                               2021
Start      Finish     ID           Task Name
J    F    M   A    M    J    J    A    S    O    N    D    J    F    M   A    M    J    J    A    S    O    N    D    J    F    M   A    M    J    J    A    S    O    N    D
1   NSAT PHASE 1                A                      B
1/31/2019  11/20/2019   2   CONCOURSE C STS STATION
3   PHASE 2 - BASE BLDG
NSAT Wedge                                                       Criti cal P ath                                                           BA SELIN E
1/27/2019  12/17/2019             Lateral & Roof Structure
12/18/2019  5/26/2020           Interior Roughin / Finishes
NSAT South Building                                                                                                                                                      FO  RECA  ST
7/1/2019   6/18/2020                      South Building
NSAT Central Core                                                                                                                                  C ritic al Pa th
2/4/2019   7/23/2019                     NSA/NSB Demo
7/1/2019   8/22/2019                        ST3.4 Install
2/20/2020   8/6/2020             Demo Roof/Topping Slab
8/10/2020  9/15/2020                  Infill Elevator Core
9/16/2020  10/1/2020                     Buildout Level 3
10/5/2020  3/31/2021                   Escalator NS5/NS6
4/1/2021   6/29/2021          Concourse TI West Buildout
7/1/2021   7/28/2021                     Commissioning                                                                                                                                                                 NS AT TURN  OV ER
4   NSAT PHASE 2 ACTIVATION                                                                                                                                                  NS AT O  PEN  ING
7/1/2021  10/27/2021                           Closeout

Critical Path

9

NSAT Phase 1 Complete



10

June 2, 1972
11

Original North Satellite


North Satellite Today





North Satellite Future

12

Concourse Level  Gate Lobby







Today

13

Marketplace Area







Today

14

i      ll|     |

]     [
iE
era SRR]
IIB

H  
Ui    RT Ts                        rae
8
I






15

16

John Grade
Boundary

Krista Birnbaum

Deborah Butterfield
Blackleaf
17

18

March, 1973
19

North Satellite Today




20

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.