6h Memo Architecture and Engineering Services MT Infrastructure Upgrades

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6h 
ACTION ITEM                            Date of Meeting      October 13, 2020 
DATE:     October 5, 2020 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Eileen Francisco, Acting Director, Aviation Facilities and Capital Programs 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Main Terminal Infrastructure Upgrades Preliminary Design Funding (CIP# C801202) 
Amount of this request:           $4,850,000 
Total estimated project cost:       $300,000,000 to $400,000,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to (1) execute a contract for
Architecture and Engineering (A&E) services in the amount not-to-exceed $4,500,000. The
amount of this request is $4,850,000 for a total estimated project cost of $300M-$400M. The
Main Terminal Infrastructure Upgrades project was briefed to Commission on September 22,
2020. This is the first of multiple action requests as the project progresses in design and then
construction.
EXECUTIVE SUMMARY 
This project will update and upgrade the Main Terminal to ensure compliance with current life
safety and building codes. 
The existing Main Terminal was built in the 1970s, with an extension to the north added in the
1980s, and Gina Marie Lindsay Arrivals Hall added in the 2000s. Although some improvements
have been made in the Main Terminal, there has not been a comprehensive renovation. The
different sections of the Main Terminal met the building codes that were in place at the time they
were constructed. Over the last couple of decades, building codes have evolved to provide
additional safety measures. These new safety measures include fire sprinklers and smoke control.
Projects in the Main Terminal have installed fire sprinklers in the areas where the work was
completed; however, large areas in the Main Terminal are still deficient in multiple areas
including the following life safety systems: fire sprinklers, smoke control (including emergency
power upgrades), fire standpipes, and emergency exit signage. 
This project will bring the Main Terminal up to current code, which is required for future projects
in the Main Terminal to move forward, including a new restroom renovations project, replacing
aging bag claim devices, and the zones 6 & 7 renovation. This project will update life safety

Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. _6h___                              Page 2 of 6 
Meeting Date: October 13, 2020 
systems to current code. In addition, this project will include full asbestos removal from the
ceiling. 
Staff will return to the Commission following the completion of the preliminary design work. At
this time staff will provide an updated project cost estimate and request authorization to move
forward with the next phase of project delivery. Staff will also request authority to add significant
money into the design contract amending it to authorize the design team to complete full design
and be available to provide design support during construction. 
JUSTIFICATION 
For the Main Terminal building to meet current code, the entire building must have a sprinkler
system installed. This will involve removing the existing ceiling, abating asbestos in the area, and
putting in new ceiling and lighting on ticketing, baggage claim, and the skybridge level. New
lighting controls to improve efficiency will also be included. 
In addition to sprinklers, a fully-integrated smoke control system will need to be installed. The
smoke control system will include adding exhaust fans and connecting to an upgraded emergency
power system. The existing emergency power is not sufficient to meet the demand of the new
smoke control system and will require significant upgrades. 
The existing emergency power system supports the Main Terminal; Concourses B, C, and D; and
the South Satellite. The total future emergency power need of these spaces is currently unknown.
Therefore, the preliminary design will focus on designing the smoke control system for all areas
except the South Satellite and evaluate any other code-required emergency power needs to 
determine the total system requirement. The South Satellite will get its own dedicated
emergency power and smoke control systems when it is renovated. The future C1 building will
also be incorporated into the total emergency power needs. 
All of this must be completed in a facility that is operational 24 hours a day, every day of the year.
Although currently passenger traffic is reduced, it is anticipated that traffic numbers will have
returned to 2019 levels by the time of construction and the project will need to be able to limit
impacts when that occurs. This is a complex project and the preliminary design is an important
first step to help mitigate some of the unknown risks to be able to provide a better cost estimate
and schedule. As part of the preliminary design we will conduct an operational impact analysis. 
In addition to the design of smoke control and emergency power, the preliminary design will
include an updated cost estimate. The $4,500,000 not-to-exceed amount represents 50% above
the initial estimate, that is $3,000,000 for the preliminary design. Full design is estimated at
$40,000,000. 
Project Scope and Budget Controls 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. _6h___                              Page 3 of 6 
Meeting Date: October 13, 2020 
The total program budget for the 'Main Terminal Infrastructure Upgrades Preliminary Design' is
estimated at $300M to $400M. At this early stage of the project, planning and budgeting is of the
most importance for a successful initiative. The team will have project controls in place to ensure
project scope, costs, and schedule are successfully managed. The project team has implemented
several strategies similar to other successful design projects. Those strategies are as follows:
1.  The original cost estimate was prepared by the Aviation Project Management estimating
manager. A second independent estimate will be performed by a cost estimating firm
under a different contract to the Port.
2.  Project  designer  will  be  directed  to  design  to  budget  and  produce  an  updated
construction estimate at all major design milestones. 
3.  Subject to further authorization by the Port Commission, the Port intends to procure a 
General Contractor, Construction Manager (GC/CM) firm. The same firm would be used
for the entire project to maintain predictability, budget, and scope. 
4.  Design review comments will be limited to identified key individuals representing the
different stakeholders. This will provide additional controls on scope creep. 
Aviation Capital Programs and Aviation Project Management have implemented a formal change
management system (applicable to all projects) that will require budget and schedule impact 
analysis and formal approval for any discretionary scope increases beyond the scope established
in the Project Definition Document. 
Diversity in Contracting 
The project team with the Diversity in Contracting Department determined a Women and
Minority Business Enterprise (WMBE) participation aspirational goal of fifteen percent (15%) for
the design contract. 
DETAILS 
This project will update the Main Terminal to ensure life safety and building code requirements
are met to ensure passenger safety. Asbestos removal will occur in all areas that the project is
conducting work. The preliminary design will focus on the emergency power system and smoke
control system. 
Scope of Work 
The following life safety issues will be addressed: 
(1)   Fire sprinklers throughout all levels of the Main Terminal; 
(2)   Fire sprinklers above both arrivals and departures drives; 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. _6h___                              Page 4 of 6 
Meeting Date: October 13, 2020 
(3)   New emergency power system for the main terminal and new feeders for Concourses
B, C, and D; 
(4)   Smoke control system added to the main terminal; 
(5)   Fire doors on the terminal side of the skybridges to ensure proper operation of the
smoke control system; 
(6)   New fire standpipes throughout the main terminal to meet NFPA requirements; 
(7)   Replacing and adding emergency exit signage to meet current codes; and 
(8)   Asbestos abatement in all areas under construction. 
Schedule 
Activity 
Preliminary design start                           2021 Quarter 1 
Commission full design authorization            2022 Quarter 1 
Full design start                                     2022 Quarter 2 
Commission construction authorization          2025 Quarter 2 
Construction start                                2025 Quarter 2 
In-use date                                       2030 Quarter 2 
Cost Breakdown                                      This Request           Total Project 
Design                                                  $4,850,000            $40,000,000 
Construction                                                     $0          $321,206,000 
Total                                                          $4,850,000           $361,206,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Initiate full design for the project. 
Cost Implications: $40,000,000 
Pros: 
(1)   Potentially shorten the schedule. 
Cons: 
(1)   Several unknowns exist within the Main Terminal which will likely cause increased costs
during design without adequate planning. 
(2)   Total emergency power loading is unknown. 
(3)   Does not provide information for stakeholder buy-in on operational impact analysis. 
(4)   Does not provide third-party estimate for construction. 
This is not the recommended alternative. 



Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. _6h___                              Page 5 of 6 
Meeting Date: October 13, 2020 
Alternative 2  Conduct preliminary design to determine options for the emergency power
system and smoke control of the Main Terminal. 
Cost Implications: $5,000,000 
Pros: 
(1)   Will develop initial smoke control design for the Main Terminal and Concourses B, C,
and D which helps provide total emergency power requirements for the project. 
(2)   Evaluates  existing  emergency  power  system  and  will  provide  alternatives  for
replacement. 
(3)   Provides alternatives to operational impacts. 
(4)   Will allow sufficient information for stakeholder buy-in. 
(5)   Provides comprehensive existing conditions for full project design. 
(6)   Will provide third-party estimate for construction cost. 
Cons: 
(1)   Potentially increases design schedule. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Following a third-party cost estimate, as part of the preliminary design, the project will update
the revised estimate for total project cost. 
Cost Estimate/Authorization Summary               Capital        Expense           Total 
COST ESTIMATE 
Original estimate                               $350,000,000     $11,206,000   $361,206,000 
AUTHORIZATION 
Previous authorizations                            $150,000               $0        $150,000 
Current request for authorization                $4,850,000               $0      $4,850,000 
Total authorizations, including this request       $5,000,000               $0      $5,000,000 
Remaining amount to be authorized          $345,000,000    $11,206,000   $356,206,000 
Annual Budget Status and Source of Funds 
This project, CIP C801202, was open with a new CIP that has a new scope and is estimated at
$350M which was included in the 2021-2025 capital budget and plan of finance. The remediation
liability would be budgeted in the operating budget. 
Financial Analysis and Summary 
Project cost for analysis              $356,206,000 
Business Unit (BU)                  Terminal Building 

Template revised June 27, 2019 (Diversity in Contracting).

COMMISSION AGENDA  Action Item No. _6h___                              Page 6 of 6 
Meeting Date: October 13, 2020 
Effect on business performance     NOI after depreciation will increase due to inclusion of
(NOI after depreciation)             capital (and operating) costs in airline rate base. 
IRR/NPV (if relevant)                N/A 
CPE Impact                       $1.24 in 2030 
Future Revenues and Expenses (Total cost of ownership) 
The addition of a new emergency power system and smoke control system will increase
maintenance costs as additional assets come online; h owever, the removal of asbestos in the
ceiling will make maintenance easier and faster as asbestos control will no longer be required for
ceiling entry. 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
September 22, 2020  The Commission was briefed on the overall project and intended use
for the preliminary design funding request. 











Template revised June 27, 2019 (Diversity in Contracting).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.