8b Attachment, HIM Dock-E sustainable design approach

P.O. Box 1209 
P.O. Box 1209 
Seattle, WA 98111-1209 
Seattle, WA 98111-1209 
Tel: 787-3000 
Tel: 787-3000 
www.portseattle.org 
www.portseattle.org 
SUSTAINABLE DESIGN APPROACH 
HARBOR ISLAND MARINA DOCK-E FLOATS AND NORTH PIER IMPROVEMENTS 
PURPOSE 
This serves as a summary document for the sustainable design coordination for the Harbor Island
Marina (HIM) Dock-E Floats and North Pier Improvements project. Additional information can be
found in Project Management's Notebook. 

SUSTAINABLE DESIGN APPROACH 
The HIM Dock-E Floats and North Pier Improvements projects has been identified as a Tier 2 project
under the Sustainable Evaluation Framework Policy Directive (SEF Policy Directive) adopted by the
Port of Seattle Commission in January 2020. Tier 2 projects are described as: 
Tier 2: Medium-sized, or more complex, projects that have opportunities for sustainability benefit
would be subject to targeted sustainability analyses and strategies. Tier 2 projects may receive a
cost per ton of carbon calculation. 
The HIM Dock-E Floats and North Pier Improvements project consists of the following elements (see
Figure 1): 
Complete replacement of 23 (out of 78 total) of Dock-E's existing float sections with new
heavier duty floats, steel piles, and appurtenances designed for larger vessel berthing and
higher load mooring capability. 
Refurbishment of 55 (out of 78 total) of Dock-E's existing float sections consisting of replacing
all remaining timber guide piles with higher load capacity steel piles; replacement of damaged
walers and cleats; nominal leveling; and concrete surface crack repairs and sealing. 
Demolition and replacement of Dock-E's existing North Pier to restore vehicle access to it.





Page 1 of 4

Figure 1. HIM Dock-E Floats and North Pier Improvements 

Following the project kickoff meeting, the Project Manager and Sustainability Coordinator assembled
a Sustainable Project Assessment and Review Collaboration (SPARC) team The SPARC team
leverages port expertise and knowledge of existing and emerging sustainability practices to: 
(1) Identify, review, brainstorm, and recommend sustainability concepts and ideas for project and
operational teams to consider and evaluate during the development and design stage of port projects. 
(2) Encourage project and operational teams to evaluate and consider innovative strategies to reduce
emissions and energy use beyond traditional approaches. 
(3) Select and apply the relevant Sustainable Evaluation Framework criteria to highlight tradeoffs
and benefits during development of the Sustainable Design Approach (SDA).
PROJECT GOALS 
The SPARC team met in January 2020 to solidify project goals which will be shared with the designer
to identify potential design alternatives/strategies moving into the 30% design process. 
Sustainable Asset Management 
o  Upgrade structural integrity and load capacities to meet existing uses 
Restore vehicle access to North Pier 
Avoid future structural damage to dock 
Habitat 
o  Look for cost effective opportunities to enhance habitat, such as 
Including light transmissivity elements such as "open grating" 

Page 2 of 4

Removing angular rock from bankline to increase potential for shoreline
vegetation 
Removing debris from the bankline and seabed 
o  Consider use of Reinhall piles to reduce underwater noise during pile driving 
Materials 
o  Consider alternative design materials for replaced structures 
Low-embodied carbon concrete 
Alternatives to concrete 
Alternative floatation materials 
Water Quality 
o  Look into options to address spill containment where feasible 
Financial Sustainability 
o  Balance project cost and function against environmental benefits 
SUSTAINABLE EVALUATION FRAMEWORK CRITERIA 
The goals identified by the SPARC team support three of the seven criteria articulated in the SEF
Policy Directive: 
Reduce GHG Emissions. The design acknowledges the need for shore power and will
accommodate the existing system during float replacement. 
Increase Resilience. The proposed improvements will upgrade the existing system to provide
necessary structural support, limiting future damage to the existing structures and allowing for
the docks to meet current and future intended function. 
Protect Health and the Environment. This project focuses on the replacement and upgrade of
existing infrastructure while limiting environmental impacts. Goals focus on materials, habitat,
and water quality. 

THIRD PARTY CERTIFICATION 
The SDA is required to include a recommendation as to whether a project should pursue an applicable
third-party sustainability certification (such as LEED or Envision.) Staff does not recommend
pursuing certification for this project, but may apply principles from the American Society of Civil
Engineers "Envision" rating system to help inform the design as appropriate. 

NEXT STEPS 
SPARC recommendations within this SDA will be presented to commission along with the request for
authorization for design funds. The Project Manager and Sustainability Coordinator will continue to
work with the SPARC team to develop a Draft Sustainable Design Strategy (SDS) that defines
alternatives to meet the goals that are included herein. The Draft SDS will be presented to the Energy
and Sustainability (E&S) Committee to present sustainable design elements that are incorporated in 30
percent design. 
The SEF Policy Directive requires that the project team evaluate and quantify the sustainability costs
and benefits of the SDA. This will be completed iteratively as the design progresses, making sure to

Page 3 of 4

coordinate with the project sponsor as appropriate. The SDS and analyses will be finalized as design
progresses. Any significant changes to design will be brought to the attention of the E&S Committee. 
The Final SDS will be included in the Commission authorization request for construction funding for
the project. 

















Page 4 of 4

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.