5. Port of Seattle Presentation

Financial Stewardship                    Accountability                       Transparency
Port of Seattle Audit Committee
Internal Audit Update
Glenn Fernandes - Director, Internal Audit
September 9, 2021
Remote Meeting
2:30 PM  4:30 PM

Operational Excellence                    Governance

Internal Audit Budget - Key Elements
Staffing (Payroll Costs)
Outside Services  Some required by RCW 39.10.385 (11)
Staff Training
2022 Principles:
Follow Port guidelines
Leverage independent resources for RCW 39.10.385 (11)
required audits
Invest in staff training and development
2

RCW 39.10.385 (11)
Applies to general contractor/construction manager (GC/CM) projects.
When in the best interest of the public, a GC/CM may select one or more
subcontractors using alternative methods.
When above $3 Million, "An independent audit, paid for by the public
body, must be conducted to confirm the proper accrual of costs."
The Port is initiating more projects using the GC/CM method.
Internal Audit will lead management of these independent audits in 2022.
Independent audit costs are viewed as part of the cost of the project and
are capitalized with the project.

3

Internal Audit Organization Structure



[Note: Two vacant positions need to be filled. One will be filled in 2022 and the other one will be deferred to the 2023 budget.]
4

Department Overview
Internal Audit, through an annual audit plan, provides
assurance that the Port's controls are effective and efficient
to mitigate business risks. The department provides the
material for and facilitates quarterly public and non-public
Audit Committee meetings each year.
The department also provides advisory services to the Port,
to the extent that it does not compromise its independence.
The department maintains its independence and objectivity
by reporting administratively to the Executive Director and
functionally to the Audit Committee.
5

New Budget Requests - Overview
Item                                                Priority     One-Time     Request for       Amount
No.               High-level Description              (H/M/L)       (Y/N)          FTEs         Requested
1     External Peer Review                            H           Y            N/A              $15,000
2     GC/CM Independent Audit - Main Terminal Low       H           Y             0                60,000
Voltage System Upgrade Project*
3     GC/CM Independent Audit - Airline Realignment      H           Y             0               120,000
Project*
4     International Arrivals Facility - External Audit         H           Y             0               100,000
Resources
Total               0                  $295,000
*Required by RCW 39.10.385 (11)



6

New Budget Requests - Details
Item 1 - External Peer Review
Description: This is an estimated cost for a Peer Review with the Association of Local
Government Auditors (ALGA), as required every three years.
Justification: Internal Audit has been certified by ALGA since 2012 and has passed every
Peer Review. This verifies that Internal Audit is consistently following Government Auditing
Standards and the International Standards for the Professional Practice of Internal Auditing.
Items 2 & 3  GC/CM Independent Audits
Description: GC/CM Independent Audits per RCW 39.10.385 (11) - Main Terminal Low
Voltage System Upgrade Project & Airline Realignment Project.
Justification: RCW requires an independent auditor to perform an audit of subcontractor
charges to the Port on GC/CM projects, where the subcontractor was selected through an
alternative selection process and their contract exceeds $3 Million.
7

New Budget Requests - Details
Item 4  External Audit Resources
Description: Capital Audit Expert Consulting Services for International Arrivals Facility
(IAF) Project.
Justification: The Audit Committee has requested a detailed review of costs related to
the IAF project to identify any potential overbillings. Additionally, this project would
identify process improvements, which the Port may utilize in future projects.



8

Employee Training & Development Related
Travel & Other Employee Expenses         2021 Budget            2022 Budget                   Notes
Air Fare                                                           $0                   $2,905 Travel for training
Lodging & Other Travel                                         0                   3,580
Employee Food & Beverage                                 0                 1,200
Local Transportation                                          360                      770 Travel to audit sites & training
Registration/Seminar Fees                               14,735                 13,510 Training costs
Membership Dues & Fees                              5,637                 5,610 Professional memberships
Management Education Expense                            0                     0
Subscriptions                                                  0                     120 Puget Sound Business Journal
Employee Recognition                                      0                      0
Retiree Recognition - HR Only                                   0                        0
Tuition Reimbursement - HR Only                             0                       0
Total                                    $20,732                  $27,695

9

Budget Overview
2019           2020           2021           2022           Change from 2021 Budget
Expense Category           Actuals           Actuals           Budget           Budget              $                %
Salaries & Benefits                 $1,291,372        $1,510,454        $1,605,524        $1,706,357          $100,833              6.3%
Equipment                          6,925             275             170            2,749            2,579         1517.1%
Supplies & Stock                          649                 70               351              1,000               649            184.9%
Outside Services                      111,531              1313              1,558           297,090           295,532         18968.7%
Travel & Employee                    30,858            19967            20,732            27,695             6,963             33.6%
Promotional                              0                0                0                0                0             0.0%
Genera l                                 2,680               -545               320              3,893              3,573           1116.6%
Telecom/ Workman's Comp            6,199            7974            7,911            8,890             979            12.4%
Total Charges to Capital                     0                  0                  0          -180,000          -180,000
Total O&M Expenses           $1,450,214       $1,539,509       $1,636,566       $1,867,674         $231,108            14.1%
Changes in certain Port-wide assumptions that drive entity-wide allocations, might cause small changes for certain
line items.
10

Approved 2021 Audit Plan
Limited Contract Compliance                 Operational                      Information Technology
Lenlyn Limited                               Rent and Concession Deferral Recovery             T2 Airport Garage Parking System
Seattle-Tacoma International              Capitalization of Assets                                Replacement1
Limousine Association (STILA)            Art Program                                     Malware Defenses  Aviation
Dilettante Chocolate, Inc.                   Noise Monitor Data Accuracy                         Maintenance
Fruit & Flower, LLC d/b/a Floret            South King County Fund                              Continuous Vulnerability Management
Lyft, Inc.3                                               Biometrics
Rasier, LLC3                                             Payment Card Industry (PCI) - Internal
Security Assessor
Capital                                               Data Recovery Capabilities2
Central Terminal Infrastructure Upgrade
(Construction and Closeout Phases)
North Terminals Utilities Upgrade 
Phase 1
Baggage Optimization - Phase 2
Restroom Renovations Phase 3 Prototype

1: Due to implementation delays, this audit will be deferred to the 2022 Audit Plan.             3: Reclassified from Limited Contract Compliance to Operational.
2: This is a contingency audit that was approved by the Audit Committee in December 2020.
11

2021 AUDIT PLAN STATUS
Audit Title                                             Type                Jan   Feb   Mar   Apr   May   Jun    Jul    Aug   Sep   Oct   Nov   Dec
Noise Monitor Data Accuracy                                                   Operational
South King County Fund                                                      Operational
Central Terminal Infrastructure Upgrade (Construction and Closeout Phases)                      Operational - Capital
Malware Defenses - Aviation Maintenance                                           IT
Seattle-Tacoma International Limousine Association (STILA)                                 Contract Compliance
Biometrics                                                              IT
Art Program                                                             Operational
Restroom Renovations Phase 3 Prototype                                            Operational - Capital
Lenlyn Limited                                                            Contract Compliance
Rasier, LLC3                                                              Operational
Lyft, Inc.3                                                               Operational
Fruit & Flower, LLC d/b/a Floret                                                  Contract Compliance
Baggage Optimization - Phase 2                                                  Operational - Capital
Payment Card Industry (PCI) - Internal Security Assessor                                   IT
Rent and Concession Deferral Recovery                                             Operational
Continuous Vulnerability Management                                             IT
Data Recovery Capabilities2                                                    IT
North Terminals Utilities Upgrade - Phase 1                                          Operational - Capital
Capitalization of Assets                                                       Operational
Dilettante Chocolate, Inc.                                                     Contract Compliance
T2 Airport Garage Parking System Replacement 1                                       IT

Complete
KEY                                              In Process
Deferred to 2022
1: Due to implementation delays, this audit will be deferred to the 2022 Audit Plan.
2: This is a contingency audit that was approved by the Audit Committee in December 2020.
3: Reclassified from Limited Contract Compliance to Operational.
12

Open Issue Follow-Up Status  Aging Report as of September 9, 2021



*1 Fifteen issues outstanding for more than two years consist of:
One issue - Fishing & Commercial Operations - Manual Billing Process at Risk of Error  To be built in house / Commission approved $410,000 additional
funding / implementation date, Q4 2021.
Two issues  Marine Maintenance Shop - One issue related to keys/badges tracking and the other issue related to fleet and fuel internal controls.
Twelve issues - IT Audits (Security Sensitive) - Exempt from Public Disclosure per RCW 42.56.420  Issues Not Discussed in Public Session.
They are: Disaster Recovery Capability (1), AV/M Facilities & Infrastructure Data Centers (3), and Security of Personal Identifiable Information (2),
HIPAA Security (4), and Closed Network System Security (2).
*2 Four IT issues do not have Target Dates and are not included in this chart. These issues are in the process of being addressed, however, they are more than two
years past the Report Date.
See Appendix A for a detailed listing of outstanding issues aging as of September 9, 2021.
13

Audits Completed:
1) Baggage Optimization Project  Phase 2
2) TNC (Lyft, Inc. & Rasier, LLC)
3) Fruit & Flower, LLC d/b/a Floret



14

Baggage Optimization Project - Phase 2
The Baggage Optimization Project replaces six individual baggage screening
systems and centralizes operations.
Key Elements of Phase 2 will:
Replace conveyor systems to the north portion of the bag well.
Construct the final baggage sortation matrix (make system more efficient).
Move concession storage to their final locations.
Move maintenance shop to its permanent location.
Add screening capacity with more Explosive Detective System machines.


15

Baggage Optimization Project - Phase 2 (continued)
Engineer's Estimate was $179,157,000.
Winning bidder, Hensel Phelps, submitted a bid for $293,937,000, 64%
over the Engineer's Estimate.
Due to the bids coming in high, the project received a negative vote on the
Majority in Interest ballot from the Managing Airline partners at Seattle-
Tacoma International Airport.
After the expiration of a required 180-day period, the Port awarded the
contract to Hensel Phelps.
The Port reduced the time of the project by six months, by making various
efficiency changes, but only received a $2.6 Million deduct change order
from Hensel Phelps.

16

Estimator's (BNP Associates, Inc.) Explanation for High Bids
Port's Project Labor Agreement with Unions was not factored into BNP's
Estimate.
Both bidders requested a one-year project extension during the bid process,
which resulted in approximately 33% additional overhead costs. This additional
year was not included in the estimate.
Unproductive hours required by the Port (requirement for Contractor to move
material in and out daily).
Decrease in eligible contractors because of prequalification statements made by
the Port.
Cost of steel increase between Phase 1 and Phase 2.

17

1) Rating: Low
The audit identified a discrepancy of $29,156 had occurred
because Hensel Phelps submitted a change order cost
proposal to the Port for one of its subcontractors, that
differed from the documented agreed-upon amount
between Hensel and the subcontractor.
According to Hensel, they did not keep adequate
supporting documentation to justify the discrepancy.
Hensel addressed the discrepancy during the course of the
audit by initiating a change order with the subcontractor.
18

Management Action Plan
No Action Plan is necessary. During the audit, Hensel Phelps
remedied the discrepancy by initiating another change order
with the subcontractor.
DUE DATE: Completed




19

TNC (Lyft, Inc. & Rasier, LLC)
Internal Audit (IA) completed an audit of Lyft, Inc. and Rasier LLC, referred to
as Transportation Network Company (TNC), for the period April 2017 through
March 2021.
The Port entered into agreements with Lyft, Inc. and Rasier, LLC d/b/a Uber
(TNCs) for the pick-up and drop-off of passengers from Seattle-Tacoma
International Airport.
TNCs connect passengers through a mobile application, which, among other
things, provides information about the pick-up time and trip duration, and
manages the payment process.
TNCs' trip activities are captured through the interaction of the Port's geo-
fence, the General Positioning System (GPS) and the TNC Apps.
20

TNC (Lyft, Inc. & Rasier, LLC) (continued)
TNCs' combined revenues for the audit period were as shown below:
2017 (Apr-Dec)          2018               2019               2020           2021 (Jan-Jul)
$914,987        $4,031,466       $12,973,434      $10,280,640       $8,079,650
Internal Audit conducted an independent match rate by collecting a
sample of 126 pick-up trips on three different dates and tracing these
observations to the TNCs' monthly reports.
Five out of the 126 observations did not have an exact match. The
match rate was between 96% to 98%.

21

1) Rating: Low
Internal Audit identified an opportunity for the
enhancement of internal controls to assess the accuracy
of the TNCs' reported trip data.
While management has implemented a control of
performing a match rate between the Port's own
observation of the TNCs' activities and the TNCs' self
reported activities, no additional work was conducted to
determine the root cause of the resulting variances and
whether corrective measures were necessary.
22

Recommendation
Management should:
Understand the reasons for the variances and adapt
processes to minimize them.
Establish a tolerance threshold that would trigger when
additional research is needed.

23

Management Response
Aviation Commercial Management staff agreed with
the key elements of the audit recommendation, and a
threshold and process will be developed with a
targeted completion date of the end of October 2021.

DUE DATE: 10/31/2021       Management will discuss in detail. (Full response in Audit Report No. 2021-10 & 11)


24

Fruit & Flower, LLC d/b/a Floret
Lease Agreement established in 2016
Gross revenue about $7.5 million annually (prior to
COVID-19)
Concession fees paid about $600,000 annually (prior to
COVID-19)

25

No Issues
Internal Audit concluded that Fruit & Flower, LLC d/b/a
Floret materially complied with the significant terms of
the Agreement.



26

Appendix
A  Aging of Outstanding Issues as of September 9, 2021


27

Appendix A  Aging of Outstanding Issues as of September 9, 2021
Operational, Capital, Information Technology, and Limited Contract Compliance Audits
Months/Years                  Months/Years
Days Outstanding  Outstanding      Days Outstanding  Outstanding
Type               Audit                                      Description                  Rating    Report Date   Target Date     (from Report Date) (from Report Date)  (from Target Date)  (from Target Date)
Operational Audit       Fishing & Commercial Operations Maritime                Manual Billing Process at risk of error      High       2/23/2018      12/31/2021         1,294   More than 2 years           -113        Not Due
IT Audit             AV/M Facility & Infrastructure Data Centers                Security Sensitive                 High       12/4/2018  No date supplied         1,010   More than 2 years           N/A           N/A
IT Audit             AV/M Facility & Infrastructure Data Centers                Security Sensitive                 High       12/4/2018  No date supplied         1,010   More than 2 years           N/A           N/A
Operational Audit       Marine Maintenance Shop                          Keys and badges tracking             High       6/14/2019      12/31/2023          818   More than 2 years           -843        Not Due
Operational Audit       Marine Maintenance Shop                          Fleet and fuel internal controls          High       6/14/2019      12/31/2023          818   More than 2 years           -843        Not Due
IT Audit             HIPAA Security Audit                             Security Sensitive                 High        9/4/2019      7/31/2020          736   More than 2 years           405        1-2 years
IT Audit             HIPAA Security Audit                             Security Sensitive                 High        9/4/2019      7/31/2020          736   More than 2 years           405        1-2 years
Operational Audit       Architecture & Engineering                          Determine fair and reasonable          High       12/9/2019      6/30/2020          640        1-2 years           436        1-2 years
Operational Audit       Architecture & Engineering                          Management review over max rates       High       12/9/2019      6/30/2020          640        1-2 years           436        1-2 years
Operational Audit       Architecture & Engineering                          Contract accuracy                  High       12/9/2019      6/30/2020          640        1-2 years           436        1-2 years
Operational Audit       Ground Transportation - Taxicabs                      Reconciliation process               High       12/1/2020      12/31/2021          282      6-12 months          -113        Not Due
IT Audit             Disaster Recovery Capabilities                        Security Sensitive                Medium      11/29/2017  No date supplied         1,380   More than 2 years           N/A           N/A
IT Audit             AV/M Facility & Infrastructure Data Centers                Security Sensitive                Medium      12/4/2018  No date supplied         1,010   More than 2 years           N/A           N/A
IT Audit             Security of Personal Identifiable Information               Security Sensitive                Medium      2/26/2019      12/31/2019          926   More than 2 years           618        1-2 years
IT Audit             Security of Personal Identifiable Information               Security Sensitive                Medium      2/26/2019      3/31/2020          926   More than 2 years           527        1-2 years
IT Audit             HIPAA Security                                 Security Sensitive                Medium       9/4/2019      7/31/2020          736   More than 2 years           405        1-2 years
IT Audit             HIPAA Security                                 Security Sensitive                Medium       9/4/2019      7/31/2020          736   More than 2 years           405        1-2 years
IT Audit             Closed Network Systems Security                      Security Sensitive                Medium       9/5/2019      3/31/2020          735   More than 2 years           527        1-2 years
IT Audit             Closed Network Systems Security                      Security Sensitive                Medium       9/5/2019      6/30/2020          735   More than 2 years           436        1-2 years
IT Audit             Inventory and Control of Hardware Assets                 Security Sensitive                Medium      11/12/2019      6/30/2023          667        1-2 years          -659        Not Due
Operational Audit       Architecture & Engineering                          Governance                    Medium      12/9/2019      6/30/2020          640        1-2 years           436        1-2 years
IT Audit             Network Password Management                      Security Sensitive                Medium      3/20/2020      12/31/2022          538        1-2 years          -478        Not Due
IT Audit             Network Password Management                      Security Sensitive                Medium      3/20/2020      9/30/2020          538        1-2 years           344      6-12 months
IT Audit             Network Password Management                      Security Sensitive                Medium      3/20/2020      12/31/2020          538        1-2 years           252      6-12 months
IT Audit             Secure Configuration for Hardware and Software on Mobile Devices,  Security Sensitive                Medium      8/21/2020      12/31/2021          384        1-2 years          -113        Not Due
Laptops, Workstations and Servers
IT Audit             Secure Configuration for Hardware and Software on Mobile Devices,  Security Sensitive                Medium      8/21/2020      12/31/2021          384        1-2 years          -113        Not Due
Laptops, Workstations and Servers
Lease and Concession Audit  Concourse Concessions, LLC                         RE-2 policy review                Medium      9/10/2020      12/31/2020          364      6-12 months           252      6-12 months
IT Audit             Inventory and Control of Software Assets                  Security Sensitive                Medium      11/24/2020      12/31/2021          289      6-12 months          -113        Not Due
IT Audit             Inventory and Control of Software Assets                  Security Sensitive                Medium      11/24/2020      12/31/2021          289      6-12 months          -113        Not Due
IT Audit             Inventory and Control of Software Assets                  Security Sensitive                Medium      11/24/2020      12/31/2021          289      6-12 months          -113        Not Due
IT Audit             Malware Defenses - Aviation Maintenance                 Security Sensitive                Medium      3/17/2021      12/31/2022          176       0-6 months          -478        Not Due
Lease and Concession Audit  Lenlyn Limited                                 Underreported Revenue             Medium      5/28/2021      6/30/2021          104       0-6 months            71      0-6 months
Operational Audit       Art Program                                  Governance, Funding, Staffing/Resources   Medium       6/4/2021      12/31/2021           97       0-6 months          -113        Not Due
Operational Audit       TNCs (Lyft, Inc. & Rasier, LLC)                         Additional research on variances         Low       8/26/2021      10/31/2021           14       0-6 months           -52        Not Due
28

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.