8e. Memo - SSAT Domestic Hot Water
COMMISSION AGENDA MEMORANDUM Item No. 8e ACTION ITEM Date of Meeting October 12, 2021 DATE: September 20, 2021 TO: Stephen P. Metruck, Executive Director FROM: Eileen Francisco, Interim Director, Facilities and Capital Programs Wayne Grotheer, Director, Aviation Project Management Group SUBJECT: Ratification of Critical Work for South Satellite Hot Water (C801271) Amount of this request: $1,100,000 Total estimated project cost: $1,100,000 ACTION REQUESTED Request Commission ratification of critical work authorization in the amount of $302,537 for the hot water at Seattle-Tacoma International Airport's South Satellite and additional authorization for the Executive Director to complete construction of the project using a Job Order Contract in the amount of $600,000, for a total authorization in the amount of $1,100,000, and a total estimated project cost of $1,100,000. EXECUTIVE SUMMARY Domestic hot water is required for both, restrooms and for airport dining and retail at the Seattle- Tacoma International Airport (Airport). Currently, two hot water tanks provide domestic hot water to the South Satellite facility (SSAT) - one for Airport Dining and Retail (ADR) locations and one for restrooms. One of the hot water tanks failed at the end of 2020 and is not repairable because of a leak in the shell of the tank. The redundancy in the system continues to provide hot water to the SSAT from the remaining tank. This project will replace the two existing hot water tanks with a new hot water system to ensure continued operations at the SSAT. This project was originally anticipated to be completed under a small works authorization; however, upon completion of design, it became clear that due to project complexity and materials cost the estimated project cost exceeded the small works threshold. Critical work was acknowledged by the Executive Director on September 7, 2021, to allow staff to move forward with a job order contract to procure long-lead items and start work to limit the risk of a disruption at the SSAT. Template revised January 10, 2019. COMMISSION AGENDA Action Item No. __8e__ Page 2 of 4 Meeting Date: October 12, 2021 JUSTIFICATION Both hot water tanks were installed in 2005. One hot water tank developed pinhole size leaks due to material failure from corrosion. As both tanks were installed at the same time, the second tank is at risk of failure. If the second tank fails, the SSAT will be without hot water for restrooms or ADR spaces until a temporary unit is provided. At a minimum the ADR spaces will be required to close; worst case the facility would need to be shut down until temporary hand washing units are provided for the restrooms. This project will ensure the domestic hot water system for the SSAT is returned to normal operations. In addition, the new system uses technology that is more energy efficient. This project started in early 2021 as a small works project to replace the two hot water tanks with identical tanks. Staff determined that a replacement in kind was not possible because of multiple factors, with space constraints being the biggest impact. Engineering started the design in March 2021. Upon completion of the design, it was determined that using small works contracts to install was no longer feasible as thresholds would be exceeded. Given the complex site conditions, estimated costs increased. The removal of the failing tanks will need to be cut up into smaller pieces. The installation of the newer tanks will require the tanks to be lowered into the mechanical room from a 20 ft high ramp access hatch. Material price increases and higher soft costs due to the complexity have also contributed to the higher estimated cost. Additionally, this project includes the amount of $100,000 in contingency to install a temporary natural gas boiler as a mitigation should the remaining hot water tank show an indication of failure, which could render the SSAT inoperable. Diversity in Contracting The construction for this project will be completed using an existing Job Order Contract (JOC) contractor that has a Women/Minority Business Enterprise goal of 5%. DETAILS This project will replace the existing domestic hot water tanks with two new hot water tanks. Scope of Work Work will include the replacement of both domestic hot water tanks with new energy efficient semi-instantaneous hot water tanks. The new tanks are smaller than the existing tanks, which will require less modification to fit into the space and meet current code. Other work will include: (1) Updating electrical wiring and connections (2) Programming and connecting direct digital controls (3) Modifying water and steam piping to fit new tanks (4) Commissioning and testing of new tanks and piping Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA Action Item No. __8e__ Page 3 of 4 Meeting Date: October 12, 2021 Schedule Port of Seattle Engineering completed the design for the replacement of the hot water tanks when the project was initially proposed as a small works project. Once it was determined that the cost would be over the amount of $300,000, a critical work memo was drafted in order for staff to continue moving the project forward without delaying the in-use date of Q1 2022. Activity Commission design authorization N/A Design start 2021 Quarter 1 Commission construction authorization 2021 Quarter 3 Construction start 2021 Quarter 4 In-use date 2022 Quarter 1 Cost Breakdown This Request Total Project Design $10,000 $60,000 Construction $590,000 $1,040,000 Total $600,000 $1,100,000 FINANCIAL IMPLICATIONS Cost Estimate/Authorization Summary Capital Expense Total COST ESTIMATE Original estimate $1,100,000 $0 $1,100,000 AUTHORIZATION Previous authorizations $197,463 $0 $197,463 Critical Work Declaration $302,537 $0 $500,000 Authorization Increase $600,000 $0 $1,100,000 Total authorizations, including this request $1,100,000 $0 $1,100,000 Remaining amount to be authorized $0 $0 $0 Annual Budget Status and Source of Funds This project, CIP C801271, was not included in the 2021-2025 capital budget and plan of finance. A budget transfer in the amount of $1,100,000 was transferred from the Aeronautical Reserve CIP (C800753) resulting in zero net change to the Aviation capital budget. The funding source will be Airport Development Fund. Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA Action Item No. __8e__ Page 4 of 4 Meeting Date: October 12, 2021 Financial Analysis and Summary Project cost for analysis $1,100,000 Business Unit (BU) Terminal Building Effect on business performance (NOI after NOI after depreciation will increase due to depreciation) inclusion of capital (and operating) costs in airline rate base. IRR/NPV (if relevant) N/A CPE Impact Less than $.01 in 2023 Future Revenues and Expenses (Total cost of ownership) ATTACHMENTS TO THIS REQUEST (1) Presentation slides (2) Critical work authorization memo dated September 7, 2021 PREVIOUS COMMISSION ACTIONS OR BRIEFINGS None Template revised June 27, 2019 (Diversity in Contracting).
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.