8c. Memo - North Terminal Utilities Upgrade Project Phase 1 Change Order
COMMISSION AGENDA MEMORANDUM Item No. 8c ACTION ITEM Date of Meeting October 26, 2021 DATE: October 1, 2021 TO: Stephen P. Metruck, Executive Director FROM: Tina Soike, Director Engineering Services Janice Zahn, Assistant Engineering Director, Construction Services Jeffrey Brown, Aviation Chief Operating Officer SUBJECT: North Terminal Utilities Upgrade Project Phase 1 (#C800717) ACTION REQUESTED Request Commission authorization for the Executive Director to execute a Change Order to Contract MC-0319240 North Terminal Utilities Upgrade Project Phase 1 (NTUUP) to replace an existing roll up door at Seattle-Tacoma International Airport in the amount of $12,490.97 and a contract time extension of 89 calendar days. EXECUTIVE SUMMARY This change order requires the addition of eighty-nine (89) calendar days to the Contract Duration. Commission action is required under the General Delegation of Authority because the Change Order includes a time extension of more than sixty days (60). No additional project funding is included with this request. Description of Change Order This change order authorizes installation of a new roll up door in lieu of reinstallation of the existing 20+ year-old roll up door. It also revises the contract completion date to match the actual completion date and settles all claims due to Port and Contractor impacts to the project schedule. Background This project was authorized for construction by the Commission on October 14, 2019. The project installed the first phase of the north utility loop which replaces and extends the existing 50-yearold undersized steam, condensate and chilled water supply and return piping from the Central Mechanical Plant. The project will create a redundant interconnected piping loop when Phase 2 is completed. Phase 1 reached substantial completion on August 17, 2021 and is currently in project close out. The project provided a new valve room and upsized piping from the Central Mechanical Plant to the Concourse D Annex and North Satellite. Template revised September 22, 2016. COMMISSION AGENDA Item No. __8c__ Page 2 of 2 Meeting Date: October 26,2021 During construction, the contract scope included the removal and reinstallation of an existing roll up door to excavate and install new piping to the room. Prior to reinstallation, it was discovered the existing door would leave a 7" gap at the bottom. It was determined the existing door could not be modified to close the gap and a new door is required. While preparing the price proposal, the Port was notified by the contractor the lead time for the new door was uncertain due to supply chain issues. Subsequently the contractor has obtained a November delivery date. In lieu of extending the contract for over 180 days and compensating the contractor for extended overhead due to the Port caused delay, the Port and Contractor reached agreement for an 89 calendar day extension without any indirect time impact costs. The Port would pay for only the direct cost of procuring and installing the new door. FINANCIAL IMPLICATIONS There is no additional funding being requested in this memo. ATTACHMENTS None. PREVIOUS COMMISSION ACTIONS OR BRIEFINGS October 22, 2019 The Commission authorized the Executive Director to (1) advertise and award a construction contract for Phase 1 of the North Terminals Utility Upgrade project at Seattle-Tacoma International Airport: (2) employ a project labor agreement (PLA); and increase authorization by $12,064,000 to total estimated cost of $40,000,000. September 12, 2017 - The Commission authorized the Executive Director to extend the North Terminals Utilities Upgrade Project Early Work Mechanical Contract by adding 250 calendar days to the contract duration. June 28, 2016 - The Commission authorized the Chief Executive Officer to increase the North Terminals Utilities Upgrade Project scope, budget, authorization, utilize Port crew advertise and award a major construction contract for the Early Work Mechanical Contract for an additional $7,271,000. April 28, 2015 - The Commission authorized the Chief Executive Officer to execute service agreements and conduct studies, cost estimates, design and prepare construction documents for the North Terminals Utilities Upgrade Project in the amount of $2,000,000. Template revised September 22, 2016; format updates October 19, 2016.
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.