8o. Memo - Sites 23/25 Habitat Restoration Change Order

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8o 
ACTION ITEM                            Date of Meeting     December 14, 2021 
DATE:     November 22, 2021 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Tina Soike, Director Engineering Services 
Janice Zahn, Assistant Engineering Director, Construction Services 
SUBJECT:  Sites 23/25 Habitat Restoration Change Order Over $300K 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to execute a change order to
Contract MC-032036 Sites 23/25 Habitat Restoration (Heavy Civil GC/CM) in the amount of
$1,941,446.60 due to costs related to the unanticipated Subtitle D disposal of soils on Site 23. 
EXECUTIVE SUMMARY 
This change order adjusts the Contract Value by the amount of $1,941,446.60 for a new value of
$15,942,343.38. This action is required under the General Delegation of Authority because the
Change Order includes a cost impact greater than $300K and is greater than 10% of the Contract
value. No additional project funding is included with this request. 
Description of Change Order 
This change order compensates the Contractor for the additional soil handling and management 
and disposal costs related to Subtitle D disposal requirements associated with potentially
contaminated material found during the excavation of the Terminal 117 site. 
Background 
The project will convert degraded shoreline areas and marginal uplands to high-functioning
estuarine habitat critical to migratory juvenile and adult salmon, as well as other resident and
migratory fish and wildlife that use the Duwamish Waterway. The Terminal 117 project restores
14 acres of estuarine habitat, including sub-tidal aquatic area, inter-tidal sediment slopes,
intertidal marsh, and native riparian/forested buffer. Estuarine habitat, once abundant in the
Duwamish estuary, is now very rare. The project is strategically located in the estuarine transition
zone in the Duwamish Waterway, where out-migrating juvenile salmon acclimate into saltwater
environments further downstream. Their survival will be significantly improved by the highquality
transition zone habitat provided by the project. 
On August 12, 2020 the Port executed a construction contract with Scarsella Brothers, Inc. in the
amount of $14,211,077. On May 17, 2021 while excavating below the site's finished clean-up
elevation, "suspect" soil was identified in 2 locations and the Contractor was directed to move

Template revised September 22, 2016.

COMMISSION AGENDA  Item 8o                                          Page 2 of 3 
Meeting Date: December 14, 2021 
elsewhere while the Port chemically profiled the soil. Two days later, two more locations were 
identified as "suspect". While three of the four locations had soil profiles consistent with the soil
profiles for the site, one sample contained elevated levels of contamination. Discovery of the
contamination was unexpected as this material was found below the elevation grade of the EPA
approved  clean-up.  Port Staff  from Environmental,  Legal, and Construction Management
engaged the Environmental Protection Agency  (EPA) to advise them of this  discovery.
Meanwhile, the Port issued Change Order #007 for the not-to-exceed amount of $273,750 to
begin removal and disposal of the contaminated material in suspect locations. Negotiations with
the EPA concluded with their decision to over-excavate beyond the design, finished habitat grade 
and dispose all generated soil at an EPA Subtitle D regulated landfill. The over excavated, finished
grades were backfilled with clean, imported sand creating an increased fill layer thereby capping
or separating the lower, native soil layer from the finished habitat surface. Factors contributing
to this decision was the presence of elevated contamination in some but not all "suspect"
locations.  The decision to do this allowed the Contractor to quickly progress with their work 
minimizing the impact to the progress of the project, which is weather and tide dependent,
however it would incur considerably higher than expected soil disposal costs.  As this was
determined to be a "Differing Site Condition" (i.e., the final T-117 upland soil cleanup was
deemed complete by EPA, confirmed with final surface soil sampling results) the Port is
responsible for these additional costs. The execution of this Change Order will result in a new
Contract Value of $15,942,343.38. Most of the work is now completed, there is no expectation
of further cost growth. 
FINANCIAL IMPLICATIONS 
There is no additional funding being requested with this action. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  Do not authorize the issuance of the Change Order. 
Pros: 
(1) Properly disposes potentially contaminated material 
Cons: 
(1)   Creates a risk potential for litigation. 
(2)   Additional staff soft costs, potential legal expenses. 
This is not the recommended alternative. 
Alternative 2  Authorize the issuance of the Change Order in the amount of $1,941,446.60.
Pro: 
(1)   Properly compensates the Contractor for the additional expense related to Subtitle D
disposal of potentially contaminated soil. 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Item 8o                                          Page 3 of 3 
Meeting Date: December 14, 2021 
Cons: 
(1) 
This is the recommended alternative. 
ATTACHMENTS TO THIS REQUEST 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
July 25, 2006  the Commission received public testimony regarding future uses for Terminal 117. 
May 13, 2008  the Commission approved entering into a memorandum of agreement (MOA)
with the Trustees for crediting habitat restoration projects in and near the Lower Duwamish
Waterway relating to future settlement of NRD claims; for execution of a professional
services agreement for environmental review and application of permit authorizations; and
to prepare plans and specifications for design and permitting of a fish and wildlife habitat
restoration project at Terminal 117 under the MOA, for a total authorized expenditure of
$210,000. 
October 27, 2008  the Commission approved entering into a settlement agreement regarding
the Terminal 117 Site and Lower Duwamish Site cleanup costs and NRD liability. 
July 7, 2009  the Commission adopted the Lower Duwamish River Habitat Restoration Plan, an
inventory of Port of Seattle properties eligible for habitat restoration. 
June 7, 2011  the Commission approved 1) permitting and design of an expanded fish and
wildlife habitat restoration project at Terminal 117 for an estimated cost of approximately
$3,021,000; and 2) execution of a contract for outside professional services to complete the
permitting and design of the habitat restoration project at Terminal 117. 
March 26, 2013  the Commission approved (1) purchase of the southern portion of the South
Park Marina float structure to accommodate habitat restoration at Terminal 117 and (2)
completing permitting and design for a public access viewpoint pier at Terminal 117. 
July 23, 2019  the Commission authorized advertising and executing a contract with a General
Contractor/Construction Manager (GC/CM) "Heavy Civil," to assist with completion of design
and permitting work associated with the Terminal 117 Habitat Restoration and Duwamish
Shoreline Access Project (the "Project"). 
April 28, 2020  the Commission authorized the execution of the GC/CM Construction Contract 
to complete the restoration of the Terminal 117 Habitat Restoration and Duwamish Shoreline
Access Project, which includes fish and wildlife habitat restoration and public shoreline access
improvements (Sites 23/25 Habitat Restoration Project). 



Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.