8d. Memo
Access Controls in Communication Rooms
COMMISSION AGENDA MEMORANDUM Item No. 8d ACTION ITEM Date of Meeting December 13, 2022 DATE: December 2, 2022 TO: Stephen P. Metruck, Executive Director FROM: Keri Stephens, Director, Aviation Facilities and Capital Programs Eileen Francisco, Director, Aviation Project Management SUBJECT: Access Control in Communication Rooms (CIP# C800935) – Design Authorization Amount of this request: $ 2,000,000 Total estimated project cost: $ 8,100,000 ACTION REQUESTED Request Commission authorization for the Executive Director to (1) increase the project budget by $5,207,000 for a revised total budget of $8,100,000; (2) prepare design and construction bid documents for the Access Control in Communication Rooms project; (3) Utilize Port of Seattle crews and small works contracts for pre-construction work; (4) procurement of long-lead owner furnished equipment to include network switches, interface terminal boxes (ITB), and main headend gear. The amount of this request is $2,000,000 for an estimated total project cost not to exceed $8,100,000. EXECUTIVE SUMMARY Communication rooms at Seattle-Tacoma International Airport (STIA) house telecommunications and data processing equipment that are critical for airport operations. The Port of Seattle updated the security requirements for communications rooms and a subsequent security audit identified deficiencies in communications rooms in need of correction. This project will bring all STIA terminal communications rooms up to the latest Port of Seattle security standards by installing (details intentionally omitted) enhanced security measures. When developing the preliminary budget for this project it was assumed core security infrastructure capacity was available and that the project could be completed at a relatively low cost. Through preliminary design and field investigation completed this year, it was determined that substantial additional security infrastructure (local power supplies, new head end equipment and interface terminal boxes) would be required at each communications room. As a result of the additional scope, project delays due to the Coronavirus disruption, rising material costs, increased labor rates, and escalation the project team is requesting an additional $5,207,000 for a total revised budget of $8,100,000. Template revised January 10, 2019. COMMISSION AGENDA – Action Item No. 8d Page 2 of 4 Meeting Date: December 13, 2022 JUSTIFICATION This project is designed to comply with findings from an internal audit of the communication rooms at STIA. The locations were identified in the audit, several have since been updated as part of other projects, the remaining rooms will be addressed with this project. These sensitive rooms contain vital communication equipment and cable interconnection infrastructure. The findings from the audit revealed the requirement for increased security and access control for these rooms. Existing key or cipher lock access does not meet the latest heightened security requirements and access controls. The scope of this project will increase security measures to meet current Port standards. Diversity in Contracting The design services will be completed using an existing IDIQ contract that was established in 2022 which has a 17% WMBE participation utilization goal. DETAILS Scope of Work For security purposes, key details of the Access Control in Communication Room project have been intentionally omitted: (1) Design services will evaluate the internal audit-identified Communication rooms needing access control devices, associated wiring, and infrastructure equipment. (2) Design services will provide communication and electrical drawings required for installing new access control devices, wiring, associated infrastructure equipment and connection to existing STIA networks. (3) Construction services: a. Modify room walls to accommodate infrastructure equipment b. Modify walls around door to accommodate access control devices c. Modify doors as required d. Install associated wiring and interconnections for access control devices e. Installation of infrastructure equipment, access control devices, and surveillance equipment. f. Connection to current STIA Access Control System and surveillance system g. Set-up and removal of barricades for securing the rooms during construction Cost Breakdown This Request Total Project Design $2,000,000 $2,968,000 Construction 5,132,000 Total $2,000,000 $8,100,000 Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA – Action Item No. 8d Page 3 of 4 Meeting Date: December 13, 2022 ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1 –Status Quo. Do not proceed with project. Cost Implications: Expense approximately $75,000 for notebook development costs. Pros: (1) Delays or defers capital investment. Cons: (1) Audit findings remain unaddressed. (2) Security of the communication rooms remain at current levels with no reduction in risk of unauthorized access. (3) Change in software/hardware may happen during deferment. (4) Potential for additional increase in costs for materials, labor, and/or inflation. This is not the recommended alternative. Alternative 2 – Comply with Audit and secure STIA communication rooms. Cost Implications: $8,100,000 in capital cost. Pros: (1) Complies with the Audit and brings the security access of these sensitive rooms to current Port standards. (2) Reduces the potential risk for unauthorized access onto critical STIA networks. (3) Provides the owners of these rooms the ability to remotely monitor room and door status. (4) Provides better flexibility to control who has access to these highly sensitive rooms. Cons: (1) Capital Cost This is the recommended alternative. Template revised June 27, 2019 (Diversity in Contracting). COMMISSION AGENDA – Action Item No. 8d Page 4 of 4 Meeting Date: December 13, 2022 FINANCIAL IMPLICATIONS Cost Estimate/Authorization Summary Capital Expense Total COST ESTIMATE Original estimate $2,893,000 $0 $2,893,000 Current change 5,207,000 0 5,207,000 Revised estimate 8,100,000 0 8,100,000 AUTHORIZATION Previous authorizations 100,000 0 100,000 Current request for authorization 2,000,000 0 2,000,000 Total authorizations, including this request 2,100,000 0 2,100,000 Remaining amount to be authorized $6,000,000 $0 $6,000,000 Annual Budget Status and Source of Funds This project C800935 is included in the 2023-2027 capital budget and plan of finance with a budget of $8,100,000. The funding sources will be the Airport Development Fund and future revenue bonds. Financial Analysis and Summary Project cost for analysis $8,100,000 Business Unit (BU) Terminal Building Effect on business performance NOI after depreciation will increase due to inclusion of (NOI after depreciation) capital (and operating) costs in airline rate base. IRR/NPV (if relevant) N/A CPE Impact $0.02 in 2026 Future Revenues and Expenses (Total cost of ownership) As a result of this project, Aviation Maintenance may see a small increase in preventative maintenance support. ATTACHMENTS TO THIS REQUEST None PREVIOUS COMMISSION ACTIONS OR BRIEFINGS None Template revised June 27, 2019 (Diversity in Contracting).
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.