10a. Memo

C Concourse Expansion Program

COMMISSION 
AGENDA MEMORANDUM                        Item No.          10a 
ACTION ITEM                            Date of Meeting        July 25, 2023 

DATE:     July 13, 2023 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Eileen Francisco, Director Aviation Project Management 
Richard Duncan, Director Aviation Business and Properties 
SUBJECT:  C Concourse Expansion Program Update and Long Lead Equipment and Materials 
(CIP# C800845) 
Amount of this request:           $20,000,000 
Total   estimated   project     $405,000,000-$420,000,000 
budget range: 

ACTION REQUESTED 
Request Commission authorization for the Executive Director to authorize $20,000,000 of the
program budget for long lead electrical, mechanical, and curtain wall equipment and other long
lead materials.

EXECUTIVE SUMMARY 
The C Concourse Building Expansion (CCE) program was created to address shortfalls in Airport
Dining and Retail (ADR) capacity, office space, and premium lounge space. The project is located
at the intersection of Concourses C and D and will add four floors to the existing three floor
structure.
The project is also programmed to provide  public amenities including  new restrooms, a
meditation room, a sensory room, a nursing room, and an “outdoor” public lookout. 
The C Concourse Expansion Program is working to accelerate delivery of the project to 2026. To
support this effort the project team would like to procure long lead materials and equipment 
now, ahead of authorization for the final Maximum Allowable Construction Cost (MACC) and the
rest of the program budget.  Ordering the equipment and materials now would supplement 
previous authorizations and efforts that allowed the project to accelerate the design and
relocation of current tenants, accelerate the design and procurement of structural steel, and to
accelerate the design and procurement of vertical circulation. 

Template revised January 10, 2019.

             COMMISSION AGENDA – Action Item No. 10a                                 Page 2 of 5 
Meeting Date: July 25, 2023 

Program Budget Update 
The design is 100% complete and the GCCM contractor is soliciting subcontractor bids. After bids
are received, the contractor will submit the final MACC proposal.   Port staff will review the
proposal, negotiate the final number, and then return to the Commission in September or
October of 2023 for authorization to execute the final contract.
The current authorization request amount was developed by the Exterior Wall, Electrical, and
Mechanical subcontractors already under contract.  Pricing for the long lead equipment and
material was quoted by suppliers to the subcontractors. 
Below is an overview of the C Concourse Expansion program’s current budget: 
MII Approved Budget                        $340,000,000 
Transfers: Bag Ops, RMM, TRA                 ($16,200,000) 
Trends 
Discretionary Scope Changes                 $ 225,000 
Non-Discretionary Scope Changes              $ 17,200,000 
(ex: emergency power requirements) 
Escalation and Design Development            $ 53,800,000 
(ex: lighting requirements, final detailing) 
Risk Contingency                               $ 10,000,000 
July 2022 Range   $340,000,000 - $420,000,000 
Current Range   $405,000,000 - $420,000,000 
JUSTIFICATION 
Early work packages allow the project to accelerate specific scopes of work that will benefit the
project schedule. Staff worked with the design team and the General Contractor Construction
Manager (GCCM) to identify scopes of work that could be accelerated without causing excessive
risk to the project.
This authorization will allow the project to procure the following long lead items: 
-Air Handling units 
-Electrical equipment (switchgear, panels, sub stations)
-Curtain wall materials 
-Other miscellaneous long lead items 
All these materials and equipment are experiencing industry wide impacts. The project team
would like to order these now or obtain production slots so that we can deliver the full project
on our accelerated delivery timeline of 2026. 

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10a                                 Page 3 of 5 
Meeting Date: July 25, 2023 
Diversity in Contracting 
WMBE outreach efforts through local community organizations and publications have begun in
support of CCE construction efforts. This includes targeted WMBE and small business pre-bid job
walkthroughs for better understanding of project efforts, prior to upcoming bids.
Current WMBE contractual commitment: 
(1) Designer: 12% 
(2) GCCM: 12% 
(3) Program Management and Construction Management: 20% 
(4) Commissioning Agent: 15% 
The project is anticipated to provide approximately 28% in Airport Construction Disadvantage
Business Enterprise (ACDBE) post-construction ADR opportunities. 
DETAILS 
The project will order: 
(1)   Air Handling Units 
(2)   Electrical Gear / Equipment 
(3)   Curtain Wall Materials 
(4)   Other materials identified by GCCM as the project progresses. 
Schedule 
Commission design authorization               2020 Quarter 2 
Design start                                       2021 Quarter 1 
Commission construction authorization early    2021 Quarter 2 
work packages 
Construction start early work packages           2022 Quarter 3 
Commission construction authorization         2022 Quarter 4 
Commission MACC authorization               2023 Quarter 4 
In-use date                                       2027 Quarter 2 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1 – Procure Long Lead Equipment and Materials with the final MACC contract. 
Cost Implications: $20,000,000 plus potential escalation 
Pros: 
(1)   Additional funds are not committed prior to having a final contract amount. 

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10a                                 Page 4 of 5 
Meeting Date: July 25, 2023 
Cons: 
(1)   The ordering of long lead equipment will be deferred and could impact the completion
date of the project. 
This is not the recommended alternative. 
Alternative 2 – Procure Long Lead Equipment and Materials 
Cost Implications: $20,000,000 of authorization of approved budget 
Pros: 
(1)   Allows project to order long lead equipment needed for the building. 
(2)   Allows the project to procure production slots for long lead equipment. 
(3)   Assists project in its goal of a 2026 project delivery. 
Cons: 
(1)   This action would commit additional funds to the project without a final project cost
being established. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Capital        Expense                  Total 
COST ESTIMATE 
Original estimate                               $331,776,000     $8,224,000           $340,000,000 
Transfer to Baggage Optimization Program    ($15,500,000)              $0          ($15,500,000) 
Revised Estimate Range                               TBD            TBD          $405,000,000 - 
$420,000,000 
AUTHORIZATION 
Previous authorizations                       $157,174,000     $7,926,000           $165,100,000 
Current request for authorization               $20,000,000              $0            $20,000,000 
(Concourse C Expansion) 
Total Auth, including this request              $177,174,000      $7,926,000           $185,100,000 
(Concourse C Expansion) 
Remaining amount to be authorized                   TBD           TBD         $219,900,000 - 
(Concourse C Expansion)                                                             $234,900,000 
Annual Budget Status and Source of Funds 
This project is included in the 2023-2027 capital budget and plan of finance with a budget of
$316,276,000. The expense budget would be included in the Aviation Division’s annual operating
expense budget. The funding sources will include the Airport Development Fund and future

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10a                                 Page 5 of 5 
Meeting Date: July 25, 2023 
revenue bonds. This project was approved by airlines through a Majority-In-Interest (MII) vote in
April 2021. 
Financial Analysis and Summary 
Project cost for analysis              $340,000,000* 
Business Unit (BU)                  Terminal Building 
Effect on business performance    NOI after depreciation will increase due to inclusion of
(NOI after depreciation)             capital (and operating) costs in airline rate base 
IRR/NPV (if relevant)                NPV (40 years) for non-aero $44.5 million* 
CPE Impact                       $0.68 in 2028 
* Financial implication for this project has not changed, but the $15.5 million was transferred to
the Baggage Optimization project for enabling work to relocate baggage handling system transfer
lines in conflict with the C Concourse Expansion project. Authorization and transfer for this work
was authorized by the Commission on April 26, 2022. 
Future Revenues and Expenses (Total cost of ownership) 
As presented on April 27, 2021, when completed the project will generate incremental nonairline
revenues of $12 million by 2028 and over $15 million by 2031. Aeronautical revenues will also
increase as the allocated operating and capital costs (debt service) are included in airline terminal
rate base. 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
•    July 26, 2022 – C Concourse Expansion Structural Steel Package 
•    April 26, 2022 – C concourse Expansion Budget Authorization and Transfer 
•    April 12, 2022 - C Concourse Expansion Briefing 
•    March 8, 2022 – Authorization to execute a Service Agreement for a third-party
Commissioning Agent 
•    April   27,   2021   –   C1   Building   Project   Additional   Design   and   General
Contractor/Construction Manager Early Work Authorization – Special Inspection and
Testing Authorization 
•    May 26, 2020 – C1 Building Project Design and General Contractor/Construction
Manager Authorization 
•    March 10, 2020 – C1 Building Project Briefing and Introduction 
•    June 26, 2018 – C1 Building Project Authorization for Planning Funds 


Template revised June 27, 2019 (Diversity in Contracting).



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.