8g. Presentation

FT ADA Compliance Phase 2

Item No.: 8g_Supp
Date: April 16, 2024
Fishermen’s Terminal ADA Compliance Phase 2:
Additional Funding and Construction
Authorization Request
Commission Meeting | April 16, 2024
Jennifer Maietta – Director, Real Estate Asset Management
Julie Yun – Waterfront Capital Project Manager

                Action Requested
Request Commission Authorization from the Executive Director to:
Request Commission authorization for the Executive Director to 1.
Approve additional funding, and 2. Advertise and execute a major public
works  construction  contract  for  the  completion  of  the  U00721
Fishermen’s Terminal ADA Compliance Phase 2 Project (CIP# C801198).
This request is in the amount of $1,100,000 for a total estimated project
cost of $2,890,000.

2

                Project Background
•  Litigation Settlement Agreement (10/5/2020):
– Port committed to address alleged Americans with Disabilities Act (ADA) code violations
within the Fishermen’s Terminal parking areas by 10/5/2022.
•  Phase 1 FT ADA Compliance (C801198/U00658)
– Construction completed by Port Construction Services (PCS): 1/8/2023
– Third-party post-construction survey reported remaining areas out of compliance with
2010 ADA design standards (e.g., ramps were too short and steep).
•  Phase 2 FT ADA Compliance (C801198/U00721):
– Scope: Correct ramps, sidewalks and parking areas that are out of compliance
(demolition, regrading, paving/pavement overlay, pavement marking, landscaping)
– Construction will be performed by an external general contractor procured via major
public works construction contract.
3

                    Risk Mitigation
• Construction resource will be procured via Major Public Works
Construction contract to establish contractual accountability
and not-to-exceed cost limit for full delivery of design.
• Engagement of the new Port Facilities Access Program
Manager specializing in ADA requirements for review and
guidance through duration of project.

4

              Tenant Impact Mitigation
• Tenant impact will be minimized through the following
coordination:
– External relations outreach and coordination.
– Additional tenant-specific communication by on-site Real Estate and
Maritime Operations staff.
– Construction contract terms to include access and phasing
accommodation
– Timing of work to commence October 2024 after busy season.
– Internal coordination to limit conflict with other projects occurring at
Fishermen’s Terminal.
5

                 Funding Request
•  Additional Funding Request: $1,100,000
•  Justification:
1. Tenant Impact: Minimize tenant impact through construction phasing and
outreach.
2. Compliance: Phase 1 original construction did not meet ADA compliance
requirements per project design. Phase 2 re-work will be required to meet full ADA
compliance via external construction contract.
3. Litigation: The conditions of the Litigation Settlement Agreement have not been
met, as Phase 1 construction did not meet ADA compliance requirements per
project design.
4. Funding: Current project funding has been exhausted as of Phase 1 original project
completion. Additional funding required to proceed with Phase 2 re-work scope.
6

                     Timeline
Milestone                                                         Date
Commission – Additional Funding and Construction Authorization        Apr 2024
Advertisement                                                    Jun 2024
Phase 2 Construction start                                               Oct 2024
Phase 2 Substantial Completion                                        Dec 2024


7

                      Questions


8



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.