8g. Presentation
FT ADA Compliance Phase 2
Item No.: 8g_Supp Date: April 16, 2024 Fishermen’s Terminal ADA Compliance Phase 2: Additional Funding and Construction Authorization Request Commission Meeting | April 16, 2024 Jennifer Maietta – Director, Real Estate Asset Management Julie Yun – Waterfront Capital Project Manager Action Requested Request Commission Authorization from the Executive Director to: Request Commission authorization for the Executive Director to 1. Approve additional funding, and 2. Advertise and execute a major public works construction contract for the completion of the U00721 Fishermen’s Terminal ADA Compliance Phase 2 Project (CIP# C801198). This request is in the amount of $1,100,000 for a total estimated project cost of $2,890,000. 2 Project Background • Litigation Settlement Agreement (10/5/2020): – Port committed to address alleged Americans with Disabilities Act (ADA) code violations within the Fishermen’s Terminal parking areas by 10/5/2022. • Phase 1 FT ADA Compliance (C801198/U00658) – Construction completed by Port Construction Services (PCS): 1/8/2023 – Third-party post-construction survey reported remaining areas out of compliance with 2010 ADA design standards (e.g., ramps were too short and steep). • Phase 2 FT ADA Compliance (C801198/U00721): – Scope: Correct ramps, sidewalks and parking areas that are out of compliance (demolition, regrading, paving/pavement overlay, pavement marking, landscaping) – Construction will be performed by an external general contractor procured via major public works construction contract. 3 Risk Mitigation • Construction resource will be procured via Major Public Works Construction contract to establish contractual accountability and not-to-exceed cost limit for full delivery of design. • Engagement of the new Port Facilities Access Program Manager specializing in ADA requirements for review and guidance through duration of project. 4 Tenant Impact Mitigation • Tenant impact will be minimized through the following coordination: – External relations outreach and coordination. – Additional tenant-specific communication by on-site Real Estate and Maritime Operations staff. – Construction contract terms to include access and phasing accommodation – Timing of work to commence October 2024 after busy season. – Internal coordination to limit conflict with other projects occurring at Fishermen’s Terminal. 5 Funding Request • Additional Funding Request: $1,100,000 • Justification: 1. Tenant Impact: Minimize tenant impact through construction phasing and outreach. 2. Compliance: Phase 1 original construction did not meet ADA compliance requirements per project design. Phase 2 re-work will be required to meet full ADA compliance via external construction contract. 3. Litigation: The conditions of the Litigation Settlement Agreement have not been met, as Phase 1 construction did not meet ADA compliance requirements per project design. 4. Funding: Current project funding has been exhausted as of Phase 1 original project completion. Additional funding required to proceed with Phase 2 re-work scope. 6 Timeline Milestone Date Commission – Additional Funding and Construction Authorization Apr 2024 Advertisement Jun 2024 Phase 2 Construction start Oct 2024 Phase 2 Substantial Completion Dec 2024 7 Questions 8
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.